|
Design (Buildability)
|
I.01 |
Project modeling |
Considers the difference CAD - BIM |
3.99 |
Attribution: BIM = 1.00, CAD = 0.83, mixed designs in CAD and BIM authoring tools = 0.83. |
| I.02 |
Cloud use |
Considers compatibility in different design disciplines and integration in design teams |
3.75 |
Attribution: Yes = 1.00, No = 0.00. |
| I.03 |
Perimeter/GFA ratio |
Considers the façade’s influence (lower constructability than internal walls) |
3.52 |
4*square root of perimeter/area |
| I.04 |
Standardization ratio of GFA |
Considers the building’s standardization (standard pavements number) |
4.06 |
number of typical floor plans / total number of pavements |
| I.05 |
Presence of a design coordinator |
Considers the reduction of clashes in design and construction |
4.68 |
Attribution: Presence = 1.00, Absence = 0.00. |
| I.06 |
Absence of curve elements in façades/frames |
Considers the presence/absence of elements with low constructability |
3.40 |
Attribution: Absence = 1.00, Presence = 0.00. |
| I.07 |
Complete specification |
Considers the influence of design specifications on quality, productivity and constructability |
4.48 |
Attribution: Complete = 1.00, Incomplete or insufficient = 0.00. |
| I.08 |
Quality of blueprints |
Blueprints are still common in building works (despite digital documents): misunderstandings reduce constructability |
3.30 |
Sum of four criteria: content clarity (QC1), text readability (QC2), scale adequacy (QC3) and paper size (QC4). All have maximum attribution of 0.25 |
| I.09 |
Wall workforce productivity |
Considers using the workforce depending on the wall system |
4.72 |
Attribution based on an improved table of constructability from BDAS system |
| I.10 |
Transportation equipment |
Considers the difference between productivity among transportation equipment |
4.65 |
Attribution: Crane = 1.00, Elevator = 0.41, Winch = 0.16, Rope and pulley = 0.00. |
| I.11 |
Structure workforce productivity |
Considers using the workforce depending on the structural system |
4.61 |
Attribution based on an improved table of constructability from BDAS system |
| I.12 |
Frames’ standardization |
Considers the standardization of windows/doors |
4.53 |
Sum of SD and SW. SD Attribution: when more than 90 % of doors have up to three different types = 0.50, when the three main door types represent between 75 % and 90 % of total = 0.38, when the three main door types represent less than 75 % of total = 0.00. SW Attribution has the same criteria. |
| I.13 |
Columns’ standardization |
Considers the standardization in columns |
4.36 (if no pillars, weight = 0) |
Same criteria of I.13 in terms of standardization range. |
| I.14 |
Slab thickness’ standardization |
Considers the standardization of the slab thickness |
4.05 |
area of predominant thickness in the standard floor / the whole area of the standard floor |
| I.15 |
Constructability databases |
Considers the presence of constructability databases in the construction company |
2.94 |
Attribution: Presence = 1.00, Absence = 0.00. |
|
Production planning
|
I.16 |
Place influence |
Considers the building location in relation to building materials and specification |
3.56 |
Attribution: construction site does not preclude any material or technology use = 1.00, Precludes = 0.00. |
| I.17 |
Building site layout planning |
Considers the existence of layout planning in the construction space |
4.01 |
Attribution: Exists = 1.00, Does not exist = 0.00. |
| I.18 |
Production planning |
Considers the existence of production planning (e.g., formwork, positioning of tiles) |
3.93 |
Attribution: The production planning (e.g., formwork, position of tiles, and others) exists = 1.00, Does not exist = 0.00. |
| I.19 |
Space at the construction site for unloading |
Considers that space constraints reduce constructability |
3.98 |
Attribution: 18-wheeler truck space: 1.00, concrete-mixer truck space: 0.77, trucks need to load and unload outside the construction site: 0.00. |
| I.20 |
Deposit space |
Considers the presence of adequate storage space |
3.90 |
Attribution: Adequate space, dedicated only for the construction site itself = 1.00, Insufficient space or shared with other construction sites = 0.00. |
|
Execution
|
I.21 |
Organized construction site, health and safety-prone |
Considers the influence of construction site organization, health, and safety on constructability |
4.40 |
Attribution: Safe and organized site = 1.00, Unsafe/unorganized = 0.00. |
| I.22 |
Construction team meetings |
Considers the importance of meetings to reduce constructability problems in parallel with the execution phase |
4.22 |
The number of monthly meetings with the construction team (R) is compared with the number of months in construction (M). When R ≥ M, attribution = 1.00. When R < M, I.22 = R/M |
| I.23 |
Construction method standardization |
considers the importance of standardization in operational construction methods |
2.50 |
Attribution: Exists = 1.00, Does not exist = 0.00. |