Acessibilidade / Reportar erro

Primary consolidation settlement due to ramp loading: Terzaghi (1943) method revisited

Abstract

Terzaghi (1943) developed an empirical method for primary consolidation due to a load applied at constant rate (ramp load) until the end of construction at time tc. The method considers that the settlement at a time t during construction, can be evaluated admitting the load applied instantaneously at time t/2. In this research, two alternative modifications are proposed for this Terzaghi’s empirical recommendation. The first one is based on a variable fraction of time t and the second modification keeps Terzaghi’s suggestion (t/2) but makes reductions in the average degree of consolidation Uv. Computed results for different construction time factors Tv were compared to Olson (1977) analytical solution. The first approach yielded a maximum difference of approximately 2.40% while the second alternative gave results that are practically the same as those calculated by Olson’s solution. The validity of these new approaches was also proven by reproducing odometer test results with good agreement.

Keywords
Primary consolidation; Ramp loading; Settlement

1. Introduction

One of Terzaghi's most significant contributions to geotechnical engineering was the theory of one-dimensional consolidation (Terzaghi, 1923Terzaghi, K. (1923). Die berechnung der durchlassigkeitsziffer des tones aus dem verlauf der hydro-dynamischen spannungserscheinungen. Sitzungberichte Akademie der Wissenschaften, 132, 125-138., 1925Terzaghi, K. (1925). Erdbaumechanik auf bodenphysikalischer grundlage. Vienna: Franz Deuticke.), which was also a consequence of another Terzaghi’s (1923)Terzaghi, K. (1923). Die berechnung der durchlassigkeitsziffer des tones aus dem verlauf der hydro-dynamischen spannungserscheinungen. Sitzungberichte Akademie der Wissenschaften, 132, 125-138. fundamental contribution given by the principle of effective stresses in saturated soils of low permeability.

Terzaghi’s consolidation theory relies on some simplifying assumptions, among them the hypothesis of loading of infinite extent applied instantaneously. Several methods for estimating the excess of pore water pressure and primary consolidation settlement due to a non-instantaneous ramp loading have been presented in the literature (Terzaghi, 1943Terzaghi, K. (1943). Theoretical soil mechanics. New York: Wiley. ; Schiffman, 1958Schiffman, R.L. (1958). Consolidation of soil under time dependent loading and varying permeability. In Proceedings of the 37th Annual Meeting of the Highway Research Board (pp. 584-615), Washington DC.; Olson, 1977Olson, R. (1977). Consolidation under time dependent loading. Journal of the Geotechnical Engineering Division, 103(1), 55-60. http://dx.doi.org/10.1061/AJGEB6.0000369.
http://dx.doi.org/10.1061/AJGEB6.0000369...
; Zhu & Yin, 1998Zhu, G., & Yin, J. (1998). Consolidation of soil under depth-dependent ramp load. Canadian Geotechnical Journal, 35(2), 344-350. http://dx.doi.org/10.1139/t97-092.
http://dx.doi.org/10.1139/t97-092...
; Conte & Troncone, 2006Conte, E., & Troncone, A. (2006). One-dimensional consolidation under general time-dependent loading. Canadian Geotechnical Journal, 43(11), 1107-1116. http://dx.doi.org/10.1139/t06-064.
http://dx.doi.org/10.1139/t06-064...
; Hanna et al., 2013Hanna, D., Sivakugan, N., & Lovisa, J. (2013). Simple approach to consolidation due to constant rate loading in clays. International Journal of Geomechanics, 13(2), 193-196. http://dx.doi.org/10.1061/(ASCE)GM.1943-5622.0000195.
http://dx.doi.org/10.1061/(ASCE)GM.1943-...
; Carneiro et al., 2021Carneiro, R., Gerscovich, D., & Danziger, B. (2021). A simple approach to predict settlement due to constant rate loading in clays. Soil and Rocks, 44(2), 1107-1116. http://dx.doi.org/10.28927/SR.2021.057120.
http://dx.doi.org/10.28927/SR.2021.05712...
). The two most known approaches are the empirical method proposed by Terzaghi (1943)Terzaghi, K. (1943). Theoretical soil mechanics. New York: Wiley. and the analytical solution developed by Olson (1977)Olson, R. (1977). Consolidation under time dependent loading. Journal of the Geotechnical Engineering Division, 103(1), 55-60. http://dx.doi.org/10.1061/AJGEB6.0000369.
http://dx.doi.org/10.1061/AJGEB6.0000369...
.

Terzaghi (1943)Terzaghi, K. (1943). Theoretical soil mechanics. New York: Wiley. empirical method estimates the average degree of consolidation Uv at time factor Tv ≤ Tc by assuming the loading applied instantly at Tv/2, multiplied by the ratio between the load fraction applied at Tv and the total construction load applied at Tc. For the post-construction period (Tv > Tc), the average degree of consolidation is calculated considering the total load applied instantly at (Tv – Tc/2), according to Equation 1:

U c T v = T v T c U v T v 2 T v T c U v T v T c 2 T v > T c (1)

Olson (1977)Olson, R. (1977). Consolidation under time dependent loading. Journal of the Geotechnical Engineering Division, 103(1), 55-60. http://dx.doi.org/10.1061/AJGEB6.0000369.
http://dx.doi.org/10.1061/AJGEB6.0000369...
subdivided the ramp load into infinitesimal load increments and applied for each load increment the Terzaghi (1923Terzaghi, K. (1923). Die berechnung der durchlassigkeitsziffer des tones aus dem verlauf der hydro-dynamischen spannungserscheinungen. Sitzungberichte Akademie der Wissenschaften, 132, 125-138., 1925Terzaghi, K. (1925). Erdbaumechanik auf bodenphysikalischer grundlage. Vienna: Franz Deuticke.) consolidation solution for instantaneous loading. A differential equation was obtained and integrated over time, which permitted the calculation of excess pore water pressures and the average degree of consolidation (Equation 2).

U c T v = T v T c 1 1 T v m = 0 2 M 4 1 e M 2 T v T v T c 1 1 T C m = 0 2 M 4 e M 2 T c 1 e M 2 T v T v > T c (2)

where M=π22m+1

Terzaghi (1943)Terzaghi, K. (1943). Theoretical soil mechanics. New York: Wiley. empirical method tends to overestimate the average degree of consolidation when compared to Olson (1977)Olson, R. (1977). Consolidation under time dependent loading. Journal of the Geotechnical Engineering Division, 103(1), 55-60. http://dx.doi.org/10.1061/AJGEB6.0000369.
http://dx.doi.org/10.1061/AJGEB6.0000369...
solution, with a difference of about 10% (Hanna et al., 2013Hanna, D., Sivakugan, N., & Lovisa, J. (2013). Simple approach to consolidation due to constant rate loading in clays. International Journal of Geomechanics, 13(2), 193-196. http://dx.doi.org/10.1061/(ASCE)GM.1943-5622.0000195.
http://dx.doi.org/10.1061/(ASCE)GM.1943-...
). In order to decrease this difference, Hanna et al. (2013)Hanna, D., Sivakugan, N., & Lovisa, J. (2013). Simple approach to consolidation due to constant rate loading in clays. International Journal of Geomechanics, 13(2), 193-196. http://dx.doi.org/10.1061/(ASCE)GM.1943-5622.0000195.
http://dx.doi.org/10.1061/(ASCE)GM.1943-...
proposed a slight modification in Terzaghi’s method so that the ramp load is considered instantaneously applied at time factor Tf = 2Tv/5, during the construction period, instead of the generally used time factor fraction Tf = Tv/2.

The main objective of this technical note is to revisit Terzaghi (1943)Terzaghi, K. (1943). Theoretical soil mechanics. New York: Wiley. empirical method introducing two simple methodologies to improve primary settlement estimates, comparing their results with Olson (1977)Olson, R. (1977). Consolidation under time dependent loading. Journal of the Geotechnical Engineering Division, 103(1), 55-60. http://dx.doi.org/10.1061/AJGEB6.0000369.
http://dx.doi.org/10.1061/AJGEB6.0000369...
analytical solution and laboratory oedometer tests data.

2. Terzaghi (1943)Terzaghi, K. (1943). Theoretical soil mechanics. New York: Wiley. method revisited

2.1 Methodology 1: new time fractions

The adjustment of time factor fractions was carried out by assuming Olson (1977)Olson, R. (1977). Consolidation under time dependent loading. Journal of the Geotechnical Engineering Division, 103(1), 55-60. http://dx.doi.org/10.1061/AJGEB6.0000369.
http://dx.doi.org/10.1061/AJGEB6.0000369...
analytical solution given by a function f and the new approximated solution by a function g, both belonging to the same vector space. The Euclidean norm that estimates the distance between them should be as close to zero as possible. To calculate this distance, a sequence of equally spaced points (ΔTv = 0.01) was taken within the interval 0.01 ≤ Tc ≤ 2.

For different construction times Tc,Table 1 shows the adjusted time factor fractions Tf that may be used for Tv ≤ Tc and Tv > Tc with Terzaghi (1943)Terzaghi, K. (1943). Theoretical soil mechanics. New York: Wiley. method. In the post-construction period, the values of the average degree of consolidation Uv were computed assuming that the total load was instantaneously applied at time factor equal to (1 Tf)Tc. The computed data allowed a representation of time-dependent loading curves for several construction time factors, as shown in Figure 1 for Tc = 0.5.

Table 1
Time factor fractions Tf for clay layers with single drainage (0.05 ≤ Tc 2).
Figure 1
Uv – Tv curves for instantaneous (Terzaghi, 1925Terzaghi, K. (1925). Erdbaumechanik auf bodenphysikalischer grundlage. Vienna: Franz Deuticke.) and ramp loads for Tc = 0.5.

Based on the results listed in Table 1, a correlation (Equation 3) between the time factor fraction Tf and the construction Time Factor Tc could be obtained with coefficient of determination R2 = 0.994.

T f = 0.0090 T c 2 0.0845 T c + 0.4833 f o r 0 < T c 2 (3)

Considering a sequence of ΔUv curves separated by an increment of the construction time factor ΔTc = 0.1 within the interval 0.1 ≤ Tc 2, the curves in Figure 2 indicate that the constant time factor fraction Tv/2 may overestimate the average degree of consolidation up to ΔUv = 9.67% with respect to Olson (1977)Olson, R. (1977). Consolidation under time dependent loading. Journal of the Geotechnical Engineering Division, 103(1), 55-60. http://dx.doi.org/10.1061/AJGEB6.0000369.
http://dx.doi.org/10.1061/AJGEB6.0000369...
analytical solution at Tc = 2.

Figure 2
ΔUv vs Tv for 0.1 ≤ Tc 2.

On the other hand, the proposed methodology based on a variable time factor fraction yields a very good agreement with the analytical solution, with a overestimation of approximately ΔUv = 2.14% at Tc = 2.0, as can be seen in Figure 2.

2.2 Methodology 2: reduction of the average degree of consolidation

Another methodology to correct Terzaghi (1943)Terzaghi, K. (1943). Theoretical soil mechanics. New York: Wiley. method during the construction period was proposed by Hanna et al. (2013)Hanna, D., Sivakugan, N., & Lovisa, J. (2013). Simple approach to consolidation due to constant rate loading in clays. International Journal of Geomechanics, 13(2), 193-196. http://dx.doi.org/10.1061/(ASCE)GM.1943-5622.0000195.
http://dx.doi.org/10.1061/(ASCE)GM.1943-...
considering the load applied instantaneously at Tf = Tv/2 (that is, keeping Terzaghi’s recommendation) but considering a 10% reduction of the overestimated average degree of consolidation. Keeping the same methodology proposed by the authors but considering both construction and post-construction periods in the analysis, a second methodology is presented as follows.

During the construction period (Tv ≤ Tc), the best percentage of Uv reduction for a given construction time factor Tc was again obtained by calculating the Euclidean norm between the functions describing Olson (1977)Olson, R. (1977). Consolidation under time dependent loading. Journal of the Geotechnical Engineering Division, 103(1), 55-60. http://dx.doi.org/10.1061/AJGEB6.0000369.
http://dx.doi.org/10.1061/AJGEB6.0000369...
analytical solution and the new approximate method. The distance between both functions should be as close to zero as possible in order to minimize the error with respect to Olson’s results. For the post-construction period (Tv > Tc), the Time Factor Tv was incrementally increased until the average degree of consolidation Uv has practically reached the same value determined during the construction period at Tv = Tc. For several construction Time Factors, Table 2 shows the corresponding coefficients that should multiply the Uv values calculated with Terzaghi (1943)Terzaghi, K. (1943). Theoretical soil mechanics. New York: Wiley. empirical method for Tv ≤ Tc and Tv > Tc.

Table 2
Multiplying coefficients to reduce Uv calculated by Terzaghi (1943)Terzaghi, K. (1943). Theoretical soil mechanics. New York: Wiley. method for 0.05 ≤ Tc 2.

Considering the results in Table 2 it was possible to replot the ramp loading curve for Tc = 1.5 in Figure 3, which now appears practically superimposed to Olson (1977)Olson, R. (1977). Consolidation under time dependent loading. Journal of the Geotechnical Engineering Division, 103(1), 55-60. http://dx.doi.org/10.1061/AJGEB6.0000369.
http://dx.doi.org/10.1061/AJGEB6.0000369...
solution and gives more accurate predictions than those previously obtained with methodology 1.

Figure 3
Uv – Tv curves for instantaneous and ramp loads for Tc = 1.5.

3. Experimental validation

The accuracy of the two alternative methodologies was evaluated considering their abilities to predict oedometer test data.

Laboratory ramp loading oedometer tests were conducted by Sivakugan et al. (2014)Sivakugan, N., Lovisa, L., Ameratunga, J., & Das, B.M. (2014). Consolidation settlement due to ramp loading. International Journal of Geotechnical Engineering, 8(2), 191-196. http://dx.doi.org/10.1179/1939787913Y.0000000017.
http://dx.doi.org/10.1179/1939787913Y.00...
on artificially mixed kaolinite/sand blend that was mixed in equal proportions with the following characteristics: 0.6 m2/year (coefficient of consolidation), qc = 215.1 kPa (maximum load at the end of the ramp loading), Ho = 18.241 mm (initial specimen thickness), ΔH = 0.272 mm (total consolidation settlement), ρc = 0.22 mm (consolidation settlement at Tc). The ramp loading was applied by filling a bucket on the loading arm with scoops of sand over a period of 1-2 h. Figure 4 presents the experimental results for Tc = 1.60 with the predictions obtained by Olson (1977)Olson, R. (1977). Consolidation under time dependent loading. Journal of the Geotechnical Engineering Division, 103(1), 55-60. http://dx.doi.org/10.1061/AJGEB6.0000369.
http://dx.doi.org/10.1061/AJGEB6.0000369...
analytical solution and the two methodologies herein presented. In the settlement-time curves the time factor Tv was normalized with respect the construction time factor Tc and the consolidation settlement ρ at time t was normalized with respect to the settlement ρc at the end of the ramping load tc, which is equivalent to the ratio Uv/Uc where Uc is the average degree of consolidation at time factor Tc.

Figure 4
Experimental and theoretical normalized settlement ramp loads curves for Tc = 1.6, considering different methodologies.

As can be seen in Figure 4, the ramp loading laboratory tests clearly demonstrate that the normalized settlement-time plots fall within a narrow band, matching the theoretical predictions. The maximum observed difference in this case was about 5% between 0.2 < Tv/Tc < 0.50.

4. Conclusions

This technical note presented two methodologies that adapt Terzaghi (1943)Terzaghi, K. (1943). Theoretical soil mechanics. New York: Wiley. empirical method to calculate primary consolidation settlement due to a ramp loading. The first methodology is based on a variable time factor fraction Tf dependent on the construction time factor Tc, while the second methodology keeps Terzaghi (1943)Terzaghi, K. (1943). Theoretical soil mechanics. New York: Wiley. original time factor fraction Tf = Tv/2 for the construction period but corrects the settlement overestimation through a multiplying coefficient in order to reduce the average degree of consolidation Uv.

Both methodologies showed good agreement with experimental oedometer test data and the theoretical solution presented by Olson (1977)Olson, R. (1977). Consolidation under time dependent loading. Journal of the Geotechnical Engineering Division, 103(1), 55-60. http://dx.doi.org/10.1061/AJGEB6.0000369.
http://dx.doi.org/10.1061/AJGEB6.0000369...
. For the engineering practice, the main advantage of the described methodologies is to recommend the use of the well-known Terzaghi (1943)Terzaghi, K. (1943). Theoretical soil mechanics. New York: Wiley. empirical method but applying either of the two corrections: a) new time factor fractions easily determined through a correlation with the construction time factor; b) keeping the time factor fraction suggested by Terzaghi (Tf = Tv/2) but using a multiplying coefficient to reduce the average degree of consolidation Uv= 2. The second one yields predictions that are practically the same as those calculated by Olson (1977)Olson, R. (1977). Consolidation under time dependent loading. Journal of the Geotechnical Engineering Division, 103(1), 55-60. http://dx.doi.org/10.1061/AJGEB6.0000369.
http://dx.doi.org/10.1061/AJGEB6.0000369...
method.

List of symbols

cv coefficient of consolidation

m count parameter

qc maximum vertical load at the end of the ramp loading

tc duration of the ramping load

Ho initial specimen thickness

M normalized count parameter

Tc construction time factor in terms of layer thickness

Tf time factor fraction

Tv time factor in terms of layer thickness

Uc average degree of consolidation at Tc

Uv average degree of consolidation at Tv

ΔH total consolidation settlement.

ΔTv time factor increment

ΔUv absolute error

ρ consolidation settlement at time t

ρc consolidation settlement at time tc

Data availability

All data produced or examined in the course of the current study are included in this Technical Note.

Acknowledgements

The authors thank the Brazilian funding agency CAPES and the Pontifícia Universidade Católica do Rio de Janeiro (PUC-Rio) for their support.

  • Discussion open until May 31, 2024.

References

  • Carneiro, R., Gerscovich, D., & Danziger, B. (2021). A simple approach to predict settlement due to constant rate loading in clays. Soil and Rocks, 44(2), 1107-1116. http://dx.doi.org/10.28927/SR.2021.057120
    » http://dx.doi.org/10.28927/SR.2021.057120
  • Conte, E., & Troncone, A. (2006). One-dimensional consolidation under general time-dependent loading. Canadian Geotechnical Journal, 43(11), 1107-1116. http://dx.doi.org/10.1139/t06-064
    » http://dx.doi.org/10.1139/t06-064
  • Hanna, D., Sivakugan, N., & Lovisa, J. (2013). Simple approach to consolidation due to constant rate loading in clays. International Journal of Geomechanics, 13(2), 193-196. http://dx.doi.org/10.1061/(ASCE)GM.1943-5622.0000195
    » http://dx.doi.org/10.1061/(ASCE)GM.1943-5622.0000195
  • Olson, R. (1977). Consolidation under time dependent loading. Journal of the Geotechnical Engineering Division, 103(1), 55-60. http://dx.doi.org/10.1061/AJGEB6.0000369
    » http://dx.doi.org/10.1061/AJGEB6.0000369
  • Schiffman, R.L. (1958). Consolidation of soil under time dependent loading and varying permeability. In Proceedings of the 37th Annual Meeting of the Highway Research Board (pp. 584-615), Washington DC.
  • Sivakugan, N., Lovisa, L., Ameratunga, J., & Das, B.M. (2014). Consolidation settlement due to ramp loading. International Journal of Geotechnical Engineering, 8(2), 191-196. http://dx.doi.org/10.1179/1939787913Y.0000000017
    » http://dx.doi.org/10.1179/1939787913Y.0000000017
  • Terzaghi, K. (1923). Die berechnung der durchlassigkeitsziffer des tones aus dem verlauf der hydro-dynamischen spannungserscheinungen. Sitzungberichte Akademie der Wissenschaften, 132, 125-138.
  • Terzaghi, K. (1925). Erdbaumechanik auf bodenphysikalischer grundlage Vienna: Franz Deuticke.
  • Terzaghi, K. (1943). Theoretical soil mechanics New York: Wiley.
  • Zhu, G., & Yin, J. (1998). Consolidation of soil under depth-dependent ramp load. Canadian Geotechnical Journal, 35(2), 344-350. http://dx.doi.org/10.1139/t97-092
    » http://dx.doi.org/10.1139/t97-092

Publication Dates

  • Publication in this collection
    26 Jan 2024
  • Date of issue
    2024

History

  • Received
    29 Jan 2022
  • Accepted
    10 Nov 2023
Associação Brasileira de Mecânica dos Solos Av. Queiroz Filho, 1700 - Torre A, Sala 106, Cep: 05319-000, São Paulo - SP - Brasil, Tel: (11) 3833-0023 - São Paulo - SP - Brazil
E-mail: secretariat@soilsandrocks.com