Learning to repair plans and schedules using a relational (deictic) representation

Abstract

Unplanned and abnormal events may have a significant impact on the feasibility of plans and schedules which requires to repair them 'on-the-fly' to guarantee due date compliance of orders-in-progress and negotiating delivery conditions for new orders. In this work, a repair-based rescheduling approach based on the integration of intensive simulations with logical and relational reinforcement learning is proposed. Based on a relational (deictic) representation of schedule states, a number of repair operators have been designed to guide the search towards a goal state. The knowledge generated via simulation is encoded in a relational regression tree for the Q-value function defining the utility of applying a given repair operator at a given schedule state. A prototype implementation in Prolog language is discussed using a representative example of three batch extruders processing orders for four different products. The learning curve for the problem of inserting a new order vividly illustrates the advantages of logical and relational learning in rescheduling.

Automated planning; Artificial intelligence; Batch plants; Reinforcement learning; Relational modeling; Rescheduling


PROCESS SYSTEMS ENGINEERING

Learning to repair plans and schedules using a relational (deictic) representation

J. PalombariniI; E. MartínezII,* * To whom correspondence should be addressed This is an extended version of the manuscript presented at the PSE 2009 - 10th International Symposium on Process Systems Engineering, 2009, Salvador, Brazil, and published in Computer Aided Chemical Engineering, vol. 27, p. 1377-1382.

IUTN-Fac. Reg. V. María, Av. Universidad 450, Villa María 5900, Argentina

IIINGAR(CONICET-UTN), Fax: +54 342 4553439.Avellaneda 3657, S3002 GJC, Santa Fe, Argentina. E-mail: ecmarti@santafe-conicet.gob.ar

ABSTRACT

Unplanned and abnormal events may have a significant impact on the feasibility of plans and schedules which requires to repair them 'on-the-fly' to guarantee due date compliance of orders-in-progress and negotiating delivery conditions for new orders. In this work, a repair-based rescheduling approach based on the integration of intensive simulations with logical and relational reinforcement learning is proposed. Based on a relational (deictic) representation of schedule states, a number of repair operators have been designed to guide the search towards a goal state. The knowledge generated via simulation is encoded in a relational regression tree for the Q-value function defining the utility of applying a given repair operator at a given schedule state. A prototype implementation in Prolog language is discussed using a representative example of three batch extruders processing orders for four different products. The learning curve for the problem of inserting a new order vividly illustrates the advantages of logical and relational learning in rescheduling.

Keywords: Automated planning; Artificial intelligence; Batch plants; Reinforcement learning; Relational modeling; Rescheduling.

INTRODUCTION

Most of the existing works addressing schedule optimization in batch plants are based on the assumptions of complete information and a static and fully deterministic environment (Méndez et al., 2006). A pervasive assumption in the deterministic scheduling field has been that the optimized schedule, once released to the production floor, can be executed as planned. However, a schedule is typically subject to the intrinsic variability of a batch process environment where difficult-to-predict events occur as soon as it is released for execution: disruptions always occur and elaborated plans quickly become obsolete (Henning and Cerda, 2000). Examples of such disruptions include equipment failures, quality tests demanding reprocessing operations, arrival of rush orders and delays in material inputs from previous operations. The inability of most scheduling literature to address the general issue of uncertainty is often cited as a major reason for the lack of influence of current research in the field on industrial practice (Henning, 2009).

Continuous adaptation and repair of schedules while being executed is thus essential for efficient and robust operation. Rescheduling (or reactive scheduling) is the knowledge-intensive activity of updating an existing schedule in response to disruptions or other changes (Vieira et al, 2003). Basically, the options available are (1) simply shifting forwards all subsequent activities, (2) rescheduling only a subset of affected operations, or (3) generating an entirely new schedule for all of the remaining tasks. The first method is computationally inexpensive but requires plenty of slack and can lead to poor resource utilization (Herroelen and Leus, 2004). Generating a schedule from scratch maximizes schedule quality, but typically requires a high computational effort and may impose a huge number of schedule modifications (Zhu, et al., 2005). The option of partial rescheduling represents a sort of tradeoff: it aims at the identification of a schedule that provides the optimal combination of schedule efficiency and schedule stability at reasonable computational cost, bearing in mind that rescheduling decisions are taken without too much deliberation on the shop-floor.

Real-time rescheduling is a key issue in disruption management. For example, in refinery supply chains, disruptions such as crude arrival delay could make the current schedule infeasible and necessitate rescheduling of operations. Existing approaches for generating (near) optimal schedules for a real-world refinery typically require significantly large amounts of time. This is undesirable when rectification decisions need to be made in real-time. Furthermore, when the problem data given to the existing scheduling approaches are changed, as is the case during a disruption management scenario, rescheduling may follow different solution paths and result in substantially different schedules. A heuristic rescheduling strategy that overcomes both these shortcomings has been proposed by Adhitya et al. (2007). The key insight exploited in their approach is that any schedule can be broken down into operation blocks. Rescheduling is thus performed by modifying such blocks in the original schedule using simple heuristics to generate a new schedule that is feasible for the new supply chain situation. It is worth noting that rescheduling strategy avoids major operational changes by preserving blocks in the original schedule. The trade-off between performance and stability of the repaired schedule is a very important issue to be addressed.

Fast rescheduling in real-time is mandatory to account for unplanned and abnormal events by generating satisfying schedules rather than optimal ones (Vieira et al, 2003). Reactivity and responsiveness is a key issue in any rescheduling strategy which makes the capability of generating and representing knowledge about heuristics critical for repair-based scheduling using case-based reasoning (Miyashita, 2000). One such example is the CABINS framework for case-based rescheduling proposed by Miyashita and Sycara (1994) that heavily resorts to human experts. Based on domain-dependent past experience or know-how, evaluation of a repaired schedule in CABINS is done not only from its local and direct effects of repair activities in the resulting schedule, but also on the rather global and indirect influences in the final repaired schedule. Along similar ideas, another important work in the field of the so-called intelligent scheduling techniques are contributions by Zweben et al. (1994). Also, Zhang and Dietterich (1995) applied reinforcement learning to the scheduling problem and succeeded in resorting to repair-based rescheduling in NASA's space shuttle payload processing problem. Since the objective function in this type of project-oriented rescheduling problems is primarily minimizing makespan, the search for an optimal sequence of repair operators can be conveniently pruned (i.e., the search length is only 20-90 steps).

Schedule repairs in CABINS are based on expert's predictive capability of global effects of intermediate rescheduling activities. This is a severe limitation of using case-based reasoning in bath plant rescheduling. To overcome the issue of non-existing human experts for domain-specific scheduling problems, integrating intensive simulations with case-based reinforcement learning has been proposed by Miyashita (2000). The tricky issue with this approach is that resorting to a feature-based representation of schedule state is very inefficient and learning is very ineffective and generalization to unseen states is highly unreliable. Futhermore, repair operators are difficult to define in a propositional setting. In constrast, humans can succeed in rescheduling thousands of tasks and resources by increasingly learning a repair strategy using a natural abstraction of a schedule: a number of objects (tasks and resources) with attributes and relations (precedence, synchronization, etc.) among them.

Thus, for automated learning of domain-specific knowledge using simulation it is mandatory to represent schedule states and repair operators using a relational abstraction that highlights the very nature of interacting objects and their relationships. In this work, a novel rescheduling approach that combines a relational (deictic) representation of schedule states and repair operators with relational reinforcement learning is proposed. To learn a near-optimal policy using simulations, a relational reinforcement learning approach (Driessens, 2004; Croonenborghs, 2009) for interactive scheduling repair, bearing in mind different goals and scenarios, is proposed. To this aim, domain-specific heuristics for scheduling repair are developed using two general-purpose algorithms already available: TILDE and RRL (Džeroski et al, 2001; De Raedt, 2008).

REPAIR-BASED (RE)SCHEDULING

Fig. 1 depicts the repair-based optimization architecture where search control knowledge about repair operator selection is acquired through reinforcements using a schedule state simulator. In the simulation environment, an instance of the schedule is interactively modified by the learning agent using a set of repair operators until a goal is achieved or the impossibility of repairing the schedule is accepted. In each interaction, the learning agent receives information from the schedule situation or state s and then selects a repair operator to be applied to the current schedule, resulting in a new one. The resulting quality of the schedule after the repair operator has been applied is evaluated using the simulation environment via an objective or reward function r(s). The learning agent then updates its action-value function Q(s,a) that estimates the value or utility of resorting to the chosen repair operator a in a given schedule state s. Such an update is made using a reinforcement learning algorithm (Sutton and Barto, 1998) such as the well-known Q-learning rule. By accumulating enough experiences over many simulated interactions, the agent is able to learn an optimal policy for choosing the best repair operator at each schedule state. The main issue for learning is then how schedule states and actions must be represented for knowledge acquisition and iterative revision.


For repairing a schedule, the agent is given a goal function: goal S → {true, false} defining which states in the schedule are target states, e.g., states in which total tardiness is less than or equal to 1 working day. The objective of any schedule repair task can be phrased as: given a starting state for the schedule s1, find a sequence of repair operators a1, a2, ..., an with aiA such that:

where δ is the transition function, which is unknown to the learning agent.

Usually a precondition function pre S × A → {true, false} is used to specify which subset of repair operators can be applied at each state of the schedule to account for resource capabilities and precedence constraints (e.g., product recipes). This puts the following extra constraints on the action sequence:

Also, a reward function is used to approximate a repair policy from reinforcements based on simulations (Martínez, 1999):

A reward is thus only given when a repaired schedule is reached. This reward function is unknown to the learning agent, as it depends on the unknown transition function δ. Based on the reward function and simulation, the optimal policy: ai = π*(si) can be approximated using reinforcement learning algorithms (Sutton and Barto, 1998; Martínez, 1999). The optimal policy π* can be used to compute the shortest action-sequence to reach a repaired scheduled, so this optimal policy, or even an approximation thereof, can be used to improve responsiveness on the shop-floor to handle unplanned events and meaningful disturbances on the shop-floor.

Most research works on reinforcement learning focus on the computation of the optimal utility of states (i.e., the function V* or related values) to find the optimal policy π*. Once this function V* is known, it is easy to translate it into an optimal policy. The optimal action in a state s is the action that leads to the state with the highest V*–value:

where 0 < γ < 1 is a discount factor. As can be seen in equation 4, this translation requires an explicit model of the scheduling world through the use of the state transition function δ (and the reward function r). In rescheduling applications, building such a model of the problem is at least as hard as finding an optimal policy, so learning V* is not sufficient to learn the optimal repair policy. Therefore, instead of learning the utility of states V(s), an agent can learn directly a different value Q, which quantifies the utility of an action a in a given state s when following the optimal policy π* is used:

An action in a given state will be optimal if the action has the highest Q-value in that state. A simulation-based algorithm to learn the optimal policy is Q-learning (Watkins, 1989; Sutton and Barto, 1998). Q-learning is a simple algorithm that updates these Q-values incrementally while the reinforcement learning agent interacts with a real or simulated world. Fig. 2 shows a high level description of the algorithm. The value update rule in Q-learning is very simple:


where s' is the resulting state of using action a at state s.

The key issue in applying reinforcement learning in rescheduling is how a schedule state must be best represented so that the repair policy can be applied to unseen schedule states more effectively. Miyashita (2000) proposed to represent states and actions in a propositional format. This corresponds to describing each state (and possibly each action as well) as a feature vector with an attribute for some distinctive properties of the schedule state. The features used are the same as the ones used in CABINS, consisting of local and global features. Global features represent information related to the entire schedule, such as total tardiness and total work-in-process in the schedule. Local features are variables that are descriptive of the local schedule in the neighborhood of a given task, milestone or constraint conflict. Propositional representations are not adequate for learning in open planning worlds defined by tasks, their characteristic attributes and their relations to other tasks and resources.

A relational (deictic) representation that deals with the varying number of tasks in the planning world by defining a focal point for referencing objects in the schedule is proposed here as a much powerful alternative. To characterize transitions in the schedule state due to repair actions, a deictic representation resorts to constructs such as:

  • The first task in the new order.

  • The next task to be processed in the reactor.

  • Tasks related to the last order.

In a deictic representation, both scheduling states and repair operators (actions) are defined in relation to a given focal point (i.e., a task) as is shown in Fig. 3. These local repair operators move the position of a task alone; however, due to the ripple effects caused by tight resource-sharing constraints, other tasks may need to be moved as well, which is not desirable. Whenever the goal-state for the schedule cannot be achieved using primitive repair operators, more elaborate macro-operators can be used to implement a combination of basic repair operators such as task-swapping, batch-split or batch-merge until a goal state in the repaired schedule (e.g., order insertion without delaying other orders) is achieved.


To gain the most from a deictic representation of states and actions in the rescheduling problem, resorting to a relational interpretation of such relationships, as used in the “learning from interpretations” setting (De Raedt and Džeroski, 1994; Blockeel et al., 1999), is proposed. In this notation, each (state, action) pair will be represented as a set of relational facts.

RELATIONAL REINFORCEMENT LEARNING (RRL)

RRL algorithms are concerned with reinforcement learning in domains that exhibit structural properties and in which different kinds of related objects such as tasks and resources exist (Džeroski et al, 2001; De Raedt, 2008; van Otterlo, 2008). These kinds of domains are usually characterized by a very large and possibly unbounded number of different states and actions, as is the case with planning and scheduling worlds. In this kind of environment, most traditional reinforcement learning techniques break down. One reason why propositional RL algorithms fail is that they store the learned Q-values explicitly in a state-action table, with one value for each possible combination of states and actions. Rather than using an explicit state−action Q-table, RRL stores the Q-values in a logical regression tree (Blockeel and De Raedt, 1998). The relational version of the Q-learning algorithm is shown in Fig. 4. The computational implementation of the RRL algorithm needs to be able to deal successfully with:

  • the relational format for (states, actions)-pairs in which the examples are represented;

  • incremental data: the learner is given a continuous stream of (state, action, Q-value)-triplets and has to predict Q-values for (state, action)-pairs during learning, not after all examples have been processed;

  • a moving target: since the Q-values will gradually converge to the correct values, the function being learned may not be stable during simulation-based learning.


In RRL, states are represented as sets of first-order logical facts, and the learning algorithm can only see one state at a time. Actions are also represented relationally as predicates describing the action as a relationship between one or more variables. Because of the relational representation of states and actions and the inductive logic programming component of the RRL algorithm, there must exist some body of background knowledge which is generally true for the entire domain to facilate induction. After the Q-function hypothesis has been initialized, the RRL algorithm starts running learning episodes like in the standard Q-learning algorithm of Fig. 2 (Sutton and Barto, 1998; Džeroski et al, 2001). During each learning episode, all the encountered states and the selected actions are stored, together with the rewards related to each encountered (state, action)-pair. At the end of each episode, when the system encounters a goal state, it uses reward back-propagation and the current Q-function approximation to compute and update the corresponding Q-value approximation for each encountered (state, action)-pair in the episode. The algorithm then presents the set of (state, action, Q-value) triplets to a relational regression engine, which will use this set of Examples to update the current regression tree of the Q-function, and then the algorithm continues executing the next learning episode.

Several incremental relational regression techniques have been developed that meet the above requirements for RRL implementation: an incremental relational tree learner TG (Driessens et al., 2001), an instance based learner (Driessens and Ramon, 2003), a kernel-based method (Gärtner et al., 2003; Driessens et al., 2006) and a combination of a decision tree learner with an instance-based learner (Driessens and Džeroski, 2004). Of these algorithms, the TG is the most popular one, mainly because it is relatively easy to specify background knowledge in the form of a language bias. In the other methods, it is necessary to specify a distance function between modeled objects (Gärtner, 2008) or a kernel function is needed between (state, action)-pairs (Driessens et al., 2006).

The TG algorithm described in Fig. 5 is a relational regression algorithm that has been developed for policy representation in logical and relational learning (Driessens, 2004; De Raedt, 2008, van Otterlo, 2008). This incremental first order regression tree algorithm is used here for accumulating simulated experience in a compact representation of a repair-based policy based on Q-values for all repair operators available at each state s. Fig. 6 gives a small example of a first order regression tree for the Q-value function in a task (re)scheduling world trained using simulations to react to events and disturbances. A first-order decision tree can be easily translated into a Prolog decision list.



A first-order decision tree is a binary tree in which every internal node contains a test that is a conjunction of first-order literals. Also, every leaf (terminal node) of the tree contains a prediction (nominal for classification trees and real-valued for regression trees). Prediction with first-order trees is similar to prediction with propositional decision trees: every new instance is sorted down the tree. If the conjunction in a given node succeeds (fails) for that instance, it is propagated to the left (right) subtree. Once the instance arrives at a leaf node, the value of that leaf node is used as the prediction for that instance. TG stores the current tree together with statistics for all tests that can be used to decide how to split each leaf further. Every time an example (triplet) is inserted, it is sorted down the tree according to the tests in the internal nodes and, in the resulting leaf, the statistics of the tests are updated.

EXAMPLE

A small example problem proposed by Musier and Evans (1989) is considered to illustrate the use of repair operators for batch plant rescheduling. The plant is made up of 3 semicontinuous extruders that process customer orders for four products. Processing rates and cleanout requirements are detailed in Table 1. Order attributes corespond to product type, due date and size. In this section, this example is used to illustrate concepts like relational definition of schedule states and repair operators, global and focal (local) variables used in the relational model, and the overall process of repairing a schedule bearing in mind minimum increase of the total tardiness when a new order needs to be inserted. In learning to insert an order the situation before the sequence of repair operations is applied is described by: i) arrival of an order with given attributes that should be inserted in a randomly generated schedule state, and ii) the arriving order attributes are also randomly chosen. Variables used to represent scheduled states and repair operators in the relational format are given in Table 2.

The prototype application has been implemented in Visual Basic.NET 2005 Development Framework 2.0 SP2 and SWI Prolog 5.6.61 running under Windows Vista. The TILDE and RRL modules from The ACE Datamining System developed by the Machine Learning group at the University of Leuven have also been used. The overall architecture of the prototype is shown in Fig. 7.


At the beginning of each training episode, the prototype interface asks the user to generate a given number of orders with their corresponding attributes bounded over allowable ranges defined interactively. To generate the initial schedule state s0, these orders are randomly assigned to one of the three available extruders. Later on, the attributes of the order to be inserted -without increasing the total tardiness in the initial schedule- are generated and it is assigned arbitrarily to one of the extruders. The learning episode progresses by applying a sequence of repair operators until the goal state is reached. At the end of the episode, examples containing the schedule states found during it are archived in the knowledge base “Examples” along with the update made by the induction procedure of the relational regression tree, which resorts to the RRTL (Relational Regression Tree Learner) component of the prototype. This regression tree contains (in relational format) the repair policy learned from “Examples” from the current and previous episodes. Background knowledge, which is valid all over all the domain, is used by the RRTL component (regression tree) to answer queries regarding the Q-value of a given state-action pair or the best repair operator for a given schedule state. These queries are actually processed by the Prolog wrappers ConsultBestAction.exe and ConsultQ.exe, which made up a transparent interface between the .NET agent and the relational repair policy. Also, the RRTL module includes the functionality for discretizing continuous variables such as Total Tardiness and Average Tardiness in non-uniform real-valued intervals, so as to make the generated rules useful for Prolog wrappers. In the .NET application, different classes are used to model Agent, Environment, Actions and Policy using the files Policy.pl, ActState.pl, ActStateAction.pl and BackgroundKnowledge.pl. Finally, the .NET agent is fully equipped to handle situations where the agent cannot be inserted in the initial schedule. To this aim, the agent may modify order attributes such as date or size so as to insert the order. The prototype allows the user to interactively revise and accept/reject changes made to order attributes to insert it in the initial schedule without increasing the Total Tardiness of the resulting schedule.

To illustrate the advantages of relational reinforcement learning in order insertion, we consider the specific situation where there exist 10 orders already scheduled in the plant and a new order #11 must be inserted so that the Total Tardiness (TT) in the schedule is minimized. Example data for scheduled orders (#1 through #10) and the new order (#11) in a given episode are shown in Table 3. In each episode, a random schedule state for orders #1 through #10 is generated and a random insertion attempted for the new order (whose attributes are also randomly chosen), which in turn serves as the focal point for defining repair operators. The goal state for the repaired schedule is stated in terms of the TT: a maximum of 5% increase. Background knowledge such as "the number of orders scheduled for extruder #3 is larger than the number for extruder #2" is provided to speed up learning in the relational domain. In Fig. 8, the learning curve for the new order insertion rescheduling event is shown. As can be seen, learning occurs rather quickly in such way that, after 60 episodes, a near-optimal repair policy is obtained. As shown in Fig. 9, the number of repair steps required to reach the goal state is drastically reduced after a few training episodes. After 60 training episodes, only 8 repair steps are required, on average, to insert the 11th order.



Fig. 10 provides an example of applying the optimal sequence of repair operators from the schedule in Fig. 10 (a). Before the 11th order has been included, the Total Tardiness is 16.42 h. Once the arriving order (in white) has been inserted, the Total Tardiness has been increased to 27.21 h; orange tasks are used to indicate cleaning operations. Based on the learned repair policy, a DownLeftSwap operator should applied, which gives rise to the schedule in Fig. 10 (b) with a TT=31.56 h. Then a BatchSplit repair operator is applied which does not change TT. Then an UpRightJump repair operator is used, which lowers the TT to 21.86 h. Finally, by means of a DownRightSwap the goal state is reached with a Total Tardiness of 14.99 h., which is even lower than the TT in the initial schedule before the 11th order was inserted.




In the foregoing discussion, the rescheduling objective was the minimization of the total tardiness (TT) impact of inserting the incoming order without any account for preserving the structure of the existing schedule. Consider next a trade-off between tardiness increase and the number of changes made to the schedule required by the arriving order. To this end, the reward function for rescheduling is defined as the ratio between tardiness reduction and the number of steps required to modify the schedule by following a given repair strategy. As an illustrative example, the initial schedule for orders #1 through # 13 shown in Table 4 is considered. An arriving order (#14) must be inserted and a new schedule generated. In Table 4, for each extruder, orders are ordered in the same sequence as they were positioned in the initial schedule. The Total Tardiness of this initial schedule is 48.31 hs. The order # 14 that must be inserted has a small size ( 84 lbs ) for product type A, with a very near due date (1 day). To assess the qualiy of the rescheduling policy learned using RRL, insertion of order #14 into the existing schedule (Table 4) is compared with schedules corresponding to repair heuristics called 1-optimal, 2-optimal, 3-optimal and 4-optimal.

Fig. 11 (b) shows the 1-optimal schedule obtained from inserting order #14 following an initial insertion (see Fig. 11(a)). Note that order #14 is inserted so as to disturb the least the orders already scheduled. The corresponding reward function for the 1-optimal insertion is -1.09, resulting from an increase in the TT from 55.85 hs to 59.12 hs and requiring three repair steps. As a result, order # 14 is scheduled in extruder #1 without altering the previously scheduled order in this equipment.


To lower the increase in the TT due to order #14 insertion, the initial schedule in Table 4 must be altered to a certain degree. The heuristic 2-optimal is concerned with inserting order #14 in-between previously scheduled orders so as to find the insertion that gives the lowest increase in TT, but an increase in the number of insertion trials is required. Fig. 12 (b) shows the 2-optimal insertion from the initial schedule in Fig. 12 (a) that includes order #14. As shown, the TT is reduced from the initial 49.99 hs to 49.66 using the 2-optimal heuristics. The drawback is that 15 steps are needed to find the solution and all orders that were scheduled in extruder #1 are delayed as a result.


A much more aggressive strategy to reduce the TT of the schedule resulting from arbitrarily inserting order #14 is to apply the 2-optimal rescheduling heuristic to all orders so as to produce a major overhaul of the initial schedule. The very idea of the 3-optimal rescheduling heuristic is finding the best positions for orders #1 through #14 in the schedule by applying a sequence of rescheduling changes based on exhaustively moving orders one at a time. As can be seeen in Fig. 13 (b), the TT of the schedule is reduced from 55.69 hs to 14.86 hs by the 3-optimal heuristic. However, this significant reduction in the schedule's TT is the result of many changes to the initial schedule due to the more than 185 repair steps made.


In the 4-optimal heuristic, for each possible possible insertion in the initial schedule, the focal order (# 14) is swapped with every other order to find a final schedule that cannot be improved by merely swapping any pair of orders. As a result, the TT of the final schedule is reduced from 59.12 hs to 8.57 but the initial schedule has been dramatically altered, as can be seen in Fig. 14 (b).


In Fig. 15, order #14 insertion has been carried out using the rescheduling policy, resulting in the proposed RRL algorithm after 100 episodes with a learning rate α=0.1, a discount factor of γ=0.85 and softmax exploration. After only 7 repair operations, the TT has been reduced from 55.69 hs to 28.12 hs. Thus, the rescheduling policy not only succesfully inserts order #14, but also significantly reduces the TT without too many changes to the original schedule. It is worth noting that order insertion has been achieved by merging the small order #14 with order #6. Finally, in Fig. 16 a comparison is made of the different scheduling strategies using the chosen reward function, which highlights the advantage of simulation-based learning of a rescheduling policy using RRL.



CONCLUDING REMARKS

A novel approach for simulation-based development of a relational policy for automatic repair of plans and schedules using reinforcement learning has been proposed. The policy allows generation of a sequence of deictic (local) repair operators to achieve rescheduling goals to handle abnormal and unplanned events such as inserting an arriving order with minimum tardiness based on relational (deictic) representation of schedule states and repair operators. Representing schedule states using a relational abstraction is not only efficient to profit from, but also potentially a very natural choice to mimic the human ability to deal with rescheduling problems where relations between objects and focal points for defining repair strategies are typically used. Moreover, using relational modeling for learning from simulated examples is a very appealing approach to compile a vast amount of knowledge about rescheduling policies, where different types of abnormal events (order insertion, extruder failure, rush orders, reprocessing needed, etc.) can be generated separately and then compiled in the relational regression tree for the repair policy, regardless of the event used to generate the examples (triplets). This is a very appealing advantage of the proposed approach since the repair policy can be used to handle disruptive events that are even different from the ones used to generate the Q-function.

(Submitted: December 12, 2009 ; Revised: July 5, 2010 ; Accepted: July 12, 2010)

  • Adhitya, A., Srinivasan, R. and Karimi, I. A., Heuristic rescheduling of crude oil perations to manage abnormal supply chain events. AIChE J., 53, No. 2, p. 397 (2007).
  • Blockeel, H. and De Raedt, L., Top-down induction of first order logical decision trees. Artificial Intelligence, 101, No. 1/2, p. 285 (1998).
  • Croonenborghs, T., Model-assisted approaches to relational reinforcement learning. Ph.D. dissertation, Department of Computer Science, K. U. Leuven, Leuven, Belgium (2009).
  • De Raedt, L., Logical and relational learning. Springer-Verlag, Berlin, Germany (2008).
  • De Raedt, L. and Deroski, S., First order jk-clausal theories are PAC-learnable. Artificial Intelligence, 70, p. 375 (1994).
  • Driessens, K., Relational reinforcement learning. Ph.D. dissertation, Department of Computer Science, K. U. Leuven, Leuven, Belgium (2004).
  • Driessens, K., Ramon, J. and Blockeel, H., Speeding up relational reinforcement learning through the use of an incremental first order decision tree learner. Proceedings of the 13th European Conference on Machine Learning, De Raedt, L. and Flach, P. (Eds.), Springer-Verlag, 2167, 97 (2001).
  • Driessens, K. and Ramon, J., Relational instance based regression for relational reinforcement learning. Proceedings of the Twentieth International Conference on Machine Learning, AAAI Press, 123 (2003).
  • Driessens, K. and Deroski, S., Integrating guidance into relational reinforcement learning. Machine Learning, 57, 271 (2004).
  • Driessens, K., Ramon, J. and Gärtner, T., Graph kernels and Gaussian processes for relational reinforcement learning. Machine Learning, 64, No. 1/3, 91 (2006).
  • Deroski, S., De Raedt, L. and Driessens, K., Relational reinforcement learning. Machine Learning, 43, No. 1/2, p. 7 (2001).
  • Gärtner, T., Kernels for Structured Data. Series in Machine Perception and Artificial Intelligence, Vol. 72, World Scientific Publishing, Singapore (2008).
  • Gärtner, T., Driessens, K. and Ramon, J., Graph kernels and Gaussian processes for relational reinforcement learning. Proceedings of 13th International Conference Inductive Logic Programming, ILP 2003, Lecture Notes in Computer Science, Springer., 2835, 146 (2003).
  • Henning, G., Production Scheduling in the Process Industries: Current Trends, Emerging Challenges and Opportunities. Computer-Aided Chemical Engineering, 27, 23 (2009).
  • Henning, G. and Cerda, J., Knowledge-based predictive and reactive scheduling in industrial environments. Computers and Chemical Engineering, 24, 2315 (2000).
  • Herroelen, W. and Leus, R., Robust and reactive project scheduling: a review and classification of procedures. International Journal of Production Research, 42, 1599 (2004).
  • Martinez, E., Solving batch process scheduling/ planning tasks using reinforcement learning, Computers and Chemical Engineering, 23, S527 (1999).
  • Méndez, C., Cerdá, J., Harjunkoski, I., Grossmann, I., Fahl, M., State-of-the-art review of optimization methods for short-term scheduling of batch processes. Computers and Chemical Engineering, 30, 913 (2006).
  • Miyashita, K., Learning scheduling control through reinforcements, International. Transactions in Operational Research (Pergamon Press), 7, 125 (2000).
  • Miyashita, K. and Sycara, K., CABINS: a framework of knowledge acquisition and iterative revision for schedule improvement and iterative repair. Artificial Intelligence, 76, 377 (1994).
  • Musier, R., and Evans, L., An approximate method for the production scheduling of industrial batch processes with parallel units. Computers and Chemical Engineering, 13, 229 (1989).
  • Sutton, R. and  Barto,  A., Reinforcement Learning: An Introduction. MIT Press, Boston, MA (1998).
  • van Otterlo, M., The logic of adaptive behavior. Ph.D. dissertation, Twente University, The Netherlands (2008).
  • Vieira, G., Herrmann, J. and Lin, E., Rescheduling manufacturing systems: a framework of strategies, policies and methods.  J. of Scheduling, 6, 39 (2003).
  • Zhang, W. and Dietterich, T., Value Function Approximations and Job-Shop Scheduling. Pre-prints of Workshop on Value Function Approximation in Reinforcement Learning at ICML-95 (1995).
  • Zhu, G., Bard, J. and Yu, G., Disruption management for resource-constrained project scheduling. Journal of the Operational Research Society, 56, 365 (2005).
  • Zweben, M., Davis, E., Doun, B. and Deale, M., Iterative repair of scheduling and rescheduling. IEEE. Trans. Syst. Man Cybern., 23,  1588 (1993).
  • *
    To whom correspondence should be addressed
    This is an extended version of the manuscript presented at the PSE 2009 - 10th International Symposium on Process Systems Engineering, 2009, Salvador, Brazil, and published in Computer Aided Chemical Engineering, vol. 27, p. 1377-1382.
  • Publication Dates

    • Publication in this collection
      29 Nov 2010
    • Date of issue
      Sept 2010

    History

    • Accepted
      12 July 2010
    • Reviewed
      05 July 2010
    • Received
      12 Dec 2009
    Brazilian Society of Chemical Engineering Rua Líbero Badaró, 152 , 11. and., 01008-903 São Paulo SP Brazil, Tel.: +55 11 3107-8747, Fax.: +55 11 3104-4649, Fax: +55 11 3104-4649 - São Paulo - SP - Brazil
    E-mail: rgiudici@usp.br