Iran |
Asnaashari et al. (2009)ASNAASHARI, E. et al. Causes of construction delays in Iran : project management , logistics , technology and environment. In: ANNUAL ARCOM CONFERENCE, 25., Cardiff, 2009. Proceedings […] Cardiff, 2009., Pourrostam and Ismail (2011)POURROSTAM, T.; ISMAIL, A. Study of methods for minimizing construction delays: evidences from a developing country. Advanced Materials Research, v. 201-203, p. 2939-2942, 2011. , Pourrostam, Ismail and Mansourenejad (2011aPOURROSTAM, T.; ISMAIL, A.; MANSOURNEJAD, M. Identification of success factors in minimizing delays on construction projects in IAU - Shoushtar Branch - Iran. Applied Mechanics and Materials, v. 94-96, p. 2189-2193, 2011a. , 2011bPOURROSTAM, T.; ISMAIL, A.; MANSOURNEJAD, M. Identification and evaluation of causes and effects of change orders in building construction projects. Applied Mechanics and Materials, v. 94/96, p. 2261-2264, set. 2011b. ), Saeb, Khayat and Telvari (2016)SAEB, S.; KHAYAT, N.; TELVARI, A. Causes of delay in Khuzestan steel company construction projects. Industrial Engineering and Management Systems, v. 15, n. 4, p. 335-344, 2016. and Shahsavand, Marefat and Parchamijalal (2018)SHAHSAVAND, P.; MAREFAT, A.; PARCHAMIJALAL, M. Causes of delays in construction industry and comparative delay analysis techniques with SCL protocol. Engineering, Construction and Architectural Management, v. 25, n. 4, p. 497-533, 2018. |
12.0 |
Turkey |
Bilgin, Dikmen and Birgonul (2018)BILGIN, G.; DIKMEN, I.; BIRGONUL, M. T. An ontology-based approach for delay analysis in construction. KSCE Journal of Civil Engineering, v. 22, n. 2, p. 384-398, 2018. , Birgonul, Dikmen and Bektas (2015)BIRGONUL, M. T.; DIKMEN, I.; BEKTAS, S. Integrated approach to overcome shortcomings in current delay analysis practices. Journal of Construction Engineering and Management, v. 141, n. 4, p. 04014088, 2015. , Nielsen and Ösdemir (2013GÜNDÜZ, M.; NIELSEN, Y.; ÖSDEMIR, M. Quantification of delay factors using the relative importance index method for construction projects in Turkey. Journal of Management in Engineering, p. 133-139, apr. 2013. , 2015GUNDUZ, M.; NIELSEN, Y.; OZDEMIR, M. Fuzzy assessment model to estimate the probability of delay in Turkish construction projects. Journal of Management in Engineering, v. 31, n. 4, p. 04014055, 2015. ) and Kazaz, Ulubeyli and Tuncbilekli (2012)KAZAZ, A.; ULUBEYLI, S.; TUNCBILEKLI, N. A. Causes of delays in construction projects in Turkey. Journal of Civil Engineering and Management, v. 18, n. 3, p. 426-435, 2012. |
10.0 |
Egypt |
Aziz (2013)AZIZ, R. F. Ranking of delay factors in construction projects after Egyptian revolution. Alexandria Engineering Journal, v. 52, n. 3, p. 387-406, 2013. , El-Razek, Bassioni and Mobarak (2008)EL-RAZEK, M. E. A.; BASSIONI, H. A.; MOBARAK, M. Causes of delay in building construction projects in Egypt. Journal of Management in Engineering, v. 11, n. 2, p. 831-841, 2008. , Marzouk and El-Rasas (2014)MARZOUK, M. M.; EL-RASAS, T. I. Analyzing delay causes in egyptian construction projects. Journal of Advanced Research, v. 5, n. 1, p. 49-55, 2014. and Marzouk, El-Dokhmasey and El-Said (2008)MARZOUK, M.; EL-DOKHMASEY, A.; EL-SAID, M. Assessing construction engineering-related delays: Egyptian perspective. Journal of Professional Issues in Engineering Education and Practice, v. 134, n. 3, p. 315-326, 2008. |
8.0 |
USA |
Arditi and Robinson (1995)ARDITI, D.; ROBINSON, M. A. Concurrent delays in construction litigation. Cost Engineering, v. 37, n. 7, p. 20-30, 1995. , Trauner et al. (2009)TRAUNER, T. J. et al. Construction delays: understanding them clearly, analyzing them correctly. 2nd. ed. San Diego: Elsevier Butterworth-Heinemann, 2009. , Arditi, Nayak and Damci (2017)ARDITI, D.; NAYAK, S.; DAMCI, A. Effect of organizational culture on delay in construction. International Journal of Project Management, v. 35, n. 2, p. 136-147, 2017. and Kog (2018)KOG, Y. C. Major construction delay factors in Portugal, the UK, and the US. Practice Periodical on Structural Design and Construction, v. 23, n. 4, p. 04018024, 2018. |
8.0 |
India |
Rathinakumar, Vignesh and Dhivagar (2017)RATHINAKUMAR, V.; VIGNESH, T.; DHIVAGAR, K. Perception of construction participants in construction delays: a case study in Tamilnadu, India. IOP Conference Series: Earth and Environmental Science, v. 80, n. 1, 2017. , Doloi et al. (2012)DOLOI, H. et al. Analysing factors affecting delays in Indian construction projects. International Journal of Project Management, v. 30, n. 4, p. 479-489, 2012. and Hasan and Jha (2019)HASAN, A.; JHA, K. N. Client and contractor roles in schedule incentive/disincentive projects. Engineering, Construction and Architectural Management, v. 26, n. 3, p. 386-407, 2019. |
6.0 |
Malaysia |
Abdul-Rahman et al. (2006)ABDUL-RAHMAN, H. et al. Delay mitigation in the malaysian construction industry. Journal of Construction Engineering and Management, v. 132, n. 2, p. 125-133, 2006. , Hasmori et al. (2018)HASMORI, M. F. et al. Significant factors of construction delays among contractors in Klang Valley and its mitigation. International Journal of Integrated Engineering, v. 10, n. 2, p. 32-36, 2018. and Mydin et al. (2014b)MYDIN, M. A. O. et al. Imperative causes of delays in construction projects from developers’ outlook. MATEC Web of Conferences, v. 10, p. 06005, 2014b. |
6.0 |
Pakistan |
Gardezi, Manarvi and Gardezi (2014)GARDEZI, S. S. S.; MANARVI, I. A.; GARDEZI, S. J. S. Time extension factors in construction industry of Pakistan. Procedia Engineering, v. 77, p. 96-204, 2014., Khahro and Memon (2018)KHAHRO, S. H.; MEMON, Z. A. Non excusable delays in construction industry : a causal study. Engineering, Technology & Applied Science Research, v. 8, n. 6, p. 3561-3564, 2018. and Khan and Gul (2017)KHAN, R. A.; GUL, W. Empirical study of critical risk factors causing delays in construction projects. In: INTERNATIONAL CONFERENCE ON INTELLIGENT DATA ACQUISITION AND ADVANCED COMPUTING SYSTEMS: TECHNOLOGY AND APPLICATIONS, 9., Bucharest, 2017. Proceedings […] Bucharest, 2017. |
6.0 |