Abstract
Oil exploration is complex and very expensive, presenting long-term returns and considerable risks of accidents. Saving time is the guideline of any optimization method to reduce drilling costs and CO2 emissions. Highly variable performances are found in any oilfield, even in similar depth ranges, due to multiple interactions between the many factors involved in the drilling operations. Understanding such gaps is complex, as different technologies and levels of energy are used in each bit run along an exploration campaign, affecting in different ways their performances. The objective of the methodology presented in this article is to provide tools to identify which are the factors and how they affect the productive time used to drill oilwells, allowing to measure the contributions of each factor in increasing the efficiency of the drilling operations. A case study analyzes a 35-year exploratory campaign offshore Brazil, where data of the 109 wells drilled in an oilfield is used to benchmark different performances, demonstrating the advantages of the methodology in oilwell planning and in finding the paths for reducing drilling costs and CO2 emissions. As drilling for O&G, CCUS and geothermal wells is expected to continue yet for decades, the learnings and the economic benefits for the operators will extended in the long terms to the whole society.
Keywords:
benchmarking; Drilling Economics; Amorim curve; decarbonization
1. Introduction
Oil wells are typically drilled in sections to prevent formations from collapsing, from blowing out oil and gas, and also to avoid contaminating drilling fluids with formation water. At the end of each section, a steel casing is lowered and cemented. The following sections are drilled, using smaller bits, and cased until the final target of the program is reached.
A multiplicity of factors act simultaneously while drilling, producing varying performances along the trajectory drilled. For a bit to drill, two types of stresses are transmitted by the drill string: compression of the cutting structure against the rock to crush it, and torque to rotate the bit and change the point of incidence of the cutting elements of the bit. The energy applied is complemented with hydraulic power delivered by fluids, pumped through the string steel pipes to come out at the bit nozzles, and blast the cuttings at the bottom, which are lifted to the surface.
The ideal is to drill each section using a single bit
Where applicable, use cheaper bits; low-tech bits, however, do not last long and present higher risk of losing moving parts, being also vulnerable to formations that abrade the bit gage
Where applicable, use expensive bits that last longer and produce higher rates of penetration
The objective of this article is to contribute to the optimization methods in the task of extending the life of drilling bits and tools, improve drilling performances, shorten the overall time spent drilling the well, reduce costs and the environmental impact. Providing solutions is a typical action of PDCA cycles: learn from the experience and improve results in future wells (Prashar, 2017).
1.1 Campos basin and Albacora Leste
The basins of the pre-salt polygon in Brazil (ANP, 2022) were formed during the rifting of the Gondwana Supercontinent, which gave birth to the South Atlantic ocean, the African and the South American continents (Mohriak 2003). Pre-salt evaporites were deposited in a shallow lagoonal environment, under a semi-arid climate and relatively stable tectonic conditions, creating an extensive sedimentary package. Faulting caused by salt tectonics created efficient hydrocarbon migration pathways from the pre-salt source rocks (Porfirio, 2009).
In 2006, Petrobras started searching for reservoirs below the evaporitic strata in the pre-salt polygon, initially complex and very costly. Oil exploration in Brazil experienced a new boom after the discovery of the first pre-salt reservoirs in the BM-S-11 block, in Santos basin. This deflagrated a transition from mature fields with post-salt reservoirs producing heavier hydrocarbons, to pre-salt reservoirs producing lighter hydrocarbons. Nowadays, 98% of the Brazilian hydrocarbon production comes from offshore fields, of which 75% from pre-salt reservoirs (ANP/BPPGN, 2023).
For three decades, extensions of the reservoirs of the Albacora field, in the Campos basin, were searched in deeper surrounding waters. This campaign led to the discovery of Albacora Leste field, pictured in Figure 1, starting in 1986 with well 3-RJS-360 and ceasing in 2018. The field production reached a peak in 2007, stabilizing from 2011 onwards (ANP, 2016).
In parallel to the pre-salt hydrocarbon search, Petrobras began to offer mature fields to the market. With potential pre-salt reservoirs yet to be confirmed, Albacora Leste was sold to PRIO in 2023 (EPBR, 2020). Current status of the oilfield: 70 decommissioned wells, 7 wells injecting, 14 shut down and 18 temporarily abandoned (ANP, 2023).
This article uses data from the 109 wells drilled in Albacora Leste field, in water depths ranging between 1061 and 1956 m (ANP, 2023). The research analyzed a total of 495 rollercone, fixed cutter and coring runs, described in Table 1, with a robust representation of 100% of the universe.
2. Methodology
The cost per meter achieved after a bit is run is a unique, non-linear and non-stochastic event (Van Kampen, 1992). Calculated by Equation 1, the value of CM represents a unique entry in the database. Every result in the database was affected by the complex aspects related to geology, shape of the trajectory, drilling technology, operational practices, bit prices, daily fees related to the rig, special tools and technicians, and especially to the time spent drilling a segment MD.
Equation 1 - Cost per meter
CM - cost per meter drilled of MD extension ($/m)
CB - price of the bit ($)
CH - rental rates of rig + special tools + infrastructure ($/h)
TT - trip time to remove a drilling bit from the well, change it and lower the next one (h)
HR - hours of rotation spent drilling the extension MD (h)
MD - extension drilled by the bit during the HR period (m)
-
CB and CH values are found in contracts or price lists (Amorim Jr. 2008)
-
TT is generated by mathematical models (Ardekani and Shadizadeh 2013)
The evolution of CMi x MDi, seen in Figure 2, begins with a rapid initial decay of CM, followed by a period of stabilization. As the bit drills, it progressively loses the sharpness of the cutting elements, meanwhile HR increases undefinedly, until the bit is pulled out.
If a bit does not drill to the end of the section and at some point CMi rises, this will compromise the total cost of the section for every additional meter drilled. Unless pulling the whole string to the surface, there is no way to verify the sharpness of the cutting structures, the bit gauge diameter or the conditions of bearings. If cones or blades of fixed cutter bits are lost in the hole, unplanned trips will be needed for fishing, milling and removing debris until the well is clean.
Premature pulling represents investing in a new bit and in the cost of the time to change it; late decisions to pull it might result in loss of gauge diameter and extra time to ream the undergauged segment of the well. An empirical guidance is that bits should be pulled before CMi increases by 3% from the lowest CM achieved (Amorim Jr., 2008).
For the purposes of the research, the moment of pulling a bit out of the well is a unique event. When pulled, bit serial number, type, depth out, length drilled, hours, date, well name, WOB, RPM, flow rate, pumping pressure, IADC wear (McGehe et al., 1992) well inclination etc. are noted. This set of data represents the KPIs of the drilling process used by the present methodology.
2.1 The fingerprint of the oilfield
The chart in Figure 3 plots CM values versus well depth, achieved when drilling the 109 wells in Albacora Leste. It represents the unique fingerprint of the field, as containing the elements of the mainspring concept of the methodology related to the cost per meter.
Noticeable is the gap of data at the bottom left, due to the water depth. The fact is that most dots are compressed at the bottom, and the vertical column of dots at 2500 m. A benchmark and a formula at the bottom are used to compare results produced by different sets of practices and technologies. The benchmark is produced by the parametric fit of all the costs per meter achieved in the basin.
The chart has no restrictions at the Y-axis, showing every CM value achieved. Due to the high vertical dispersion, it is almost useless, except for spotting specific results and researching the factors involved to understand the reasons of a bit performance.
Outliers are important to identify bad data (Smiti, 2020). Their presence can be attributed to registering errors, mis-reporting, sampling errors and to exceptional but true values, a misconcept of outliers analyzed in this article. If a dataset has been fully validated no outliers will remain, as every bit used in the campaign was run intending to accomplish a specific objective. High values of CM are due to bits not used until they are fully worn, like when drilling cement, shoe and a short length before pulled out to change BHA, and due to the nature of the operation, as sidetracking or coring.
2.2 Parametric fit of drilling
During a drilling operation a gamma of resources act simultaneously to overcome the geological environment, using variable energy levels and producing variable results under different drill string vibration modes. The present methodology provides the parametric fit of the drilling KPIs, modelling them in function of the deterministic variable of the process, which is the measured well depth.
It is desirable to have a correlation coefficient R2 converging to 1.0 when modelling data using linear, sinusoidal and low polynomial parametric fits, a criterion which does not apply to the reality of the highly variable results seen in Figure 3 (MathWorks 2024). In such environments, if low-order polynomial fits provide unreliable models, high-order polynomials provide spurious wiggles between the data points (Rust, 2002).
Despite the parametric fit adopted, the highly variable performances will always result in low coefficients of correlation. Fortunately, there are good models with low correlation coefficients, which is the solution demonstrated in this article (Minitab 2019).
2.3 Parametric fit of drilling performances
Bit performances are very sensible in the efforts to overcome the geological constraints. Due to using many different bit technologies and drilling parameters, the result in any oilfield is a high dispersion of performances along the measured depth, seen in Figure 4 for rates of penetration.
Most parametric fits for ROP found in literature (Payne and Abbassian, 1996), (Stapenhurst, 2009), (Wiktorski, Kuznetcov and Sui, 2017), (Oyedere and Gray 2020), (A. Jabbar, et al. 2022), (Shaygan and Jamshidi 2022), (Wan, et al. 2023) and (Zeng, et al. 2024) were done to model specific environments with high correlation coefficients, willing to predict ROP under similar conditions.
In a different direction, logarithmic fit is adopted in this research as a wider and reliable solution for modelling ROP in any oilfield and for well planning. Polynomial fits also work for ROP, but presenting fluctuations along the benchmark, especially in smaller datasets. Experience shows that as the exploration campaign evolves, polynomial fits will slowly evolve to logarithmic fits.
The benchmark seen in Figure 4 attests the decline of ROP along the measured depth, which is naturally expected. Rates of penetration can be estimated in future well plans by using the planned depth out D of a bit in Equation 2, being factors a and b provided by the benchmark formula.
Equation 2 - Generic formula for the logarithmic fit
a - multiplying factor
D - depth out of the bit
b - variable that defines the theoretical point where the trend curve meets the Y-axis
-
The higher is the module of factor a, more curvilinear is the benchmark
-
If a is negative, as in Figure 4, it means that performances naturally decay with well depth
-
If a is low and close to 1, it means an almost linear variation of performance versus well depth
-
If a is positive, the benchmark is modelling long lengths drilled and high penetration rates in the deeper sections, flagging successful actions adopted by the optimization method
2.4 Parametric fit of costs per meter
The objective of the research is finding the set of conditions which provide the lowest drilling costs. Parametric fit of costs per meter is rare in literature due to limitations of accessing financial data and the complete records of drilling performances for a whole oilfield, but also due to the high complexity of understanding the subject.
An exponential fit was first used to model CM using a limited database (Bourgoyne et al., 1986), being later demonstrated to be a valid model of the natural tendency of increasing costs per meter versus well depth (Amorim Jr., 2008). The exponential fit, proposed as a wide solution for modelling CM, is a reliable solution for well planning in any oilfield.
The trendline satisfactorily benchmarks the evolution of CM in front of the changing physical and chemical constraints along the well. The fit can be considered a universal model for the industry as the algorithm solves any instance of the problem efficiently (Murtagh, 2025).
The high dispersion, seen in Fig. 3, is predictable in any oilfield due to inherit the dispersion of each of the elements that are part of Equation 1. To avoid that, the Y-scale of Figure 5 was limited to exhibit only CM values under $20000/m. In the chart, values below the benchmark were produced by long runs and higher ROP; values above the benchmark are related to additional drilling time, poor bit selection, low parameters, very short sections and string resonance.
The cost per meter in any future well plan can be estimated by using the expected depth out of a bit D in Equation 3, and factors k1 and k2 provided by the benchmark formula
Equation 3 - Generic formula of the exponential fit
where: CM - cost per meter predicted at the depth D ($/m); k1 - variable that defines the theoretical point where the trend line meets the Y-axis; k2 - exponential variable that reflects how CM changes with the increase of depth D; D - depth out of the bit (m)
-
Variable k1 is always positive, as there are no negative costs
-
The magnitude of k2 defines the shape and curvature of the line
-
Values of k2 close to zero cause the trendline to become almost straight, like in Figure 5
-
If k2 is positive, increasing k2 flags difficulties as rock hardness, abrasiveness and vibration harmonics of the drill string, meaning that CM naturally increases with well depth
-
If k2 is negative, CM decreases and flags the success of the optimization method adopted
-
Increasing water depths burden drilling costs and displace the curve up and to the right
This is a dynamic process. As the exploratory campaign evolves, k1 and k2 change with every new result and slowly modify the fingerprint. The benchmark is displaced down if improvements are made by more energy-efficient operations, and vice-versa.
The cost of drilling any segment can be calculated by integrating Equation 4 between any depths D1 and D2, and resolving the exponential formula.
Equation 4 - Expected cost of drilling from depth D1 to D2
Equation 5 - Resolution for any interval D1 and D2
The result of the integer is illustrated by a gray area in Figure 6. The cost of drilling a whole offshore well in the area, which is a most relevant information for the OPEX, can be estimated by using D1 as the water depth, and D2 the predicted final depth of the planned well. The cost of drilling an onshore well can be predicted by using D1 = 0.
2.5 Measuring the financial impact of more efficient technology
The only path to reduce costs per meter is minimizing the time spent to complete the planned work, done by providing long bit runs, high ROPs and by mitigating drilling vibrations.
More expensive technologies can be justified if resulting in saved rig time enough to pay the higher prices charged (Amorim Jr., Moutinho et al., 2024). The time saved is directly proportional to the financial savings provided in relation to the field benchmark:
Equation 6 - Financial savings due to more efficient drilling
Where, Finsav - financial savings ($); ΔCM - financial gap of CM in relation to the field benchmark ($)
Equation 7 - Time saved by more efficient drilling
Where, ND - time (days)
2.6 Environmental impact of more efficient technology
As all the energy used in drilling rigs is generated locally by powerful electric-diesel generators, time reductions contribute to minimizing day-and-night CO2 emissions. Being the volume of diesel consumed a direct function of rig power and time, the least time it takes to drill the trajectory, the lower will be the total energy consumed, the drilling costs and the GHG emissions.
Diesel-electric generators emit 2.6 to 2.7 ton CO2/m3 of diesel to generate electricity; to these add 0.2 to 0.5 ton/m3 related to the transportation of fuel to the remote locations (Carvalho, 2011), (Kamboh et al., 2012), (Pavkovic, Sedic and Guzovic, 2016), (University of Exeter 2022), totalizing 2.8 to 3.2 ton CO2/m3 of diesel.
For didactic purposes 3.0 ton CO2/m3 of diesel were adopted in Equation 8.
Equation 8 - Emission of CO2 per m3 of diesel
Where, RigCO2 - emissions of CO2 (ton); Vd - volume of diesel (m3)
Jack-ups - 20 ton diesel/day or 60 ton of CO2/day
Semi-submersible rigs - 25 ton diesel/day or 75 ton of CO2/day
Drill ships - 30 ton diesel/day or 90 ton of CO2/day
The mass of CO2 emissions reduced by the optimization process, calculated by Equation 9, is proportional to the number of days saved in the drilling process.
Equation 9 - Mass of CO2 emissions saved daily by more efficient drilling
Where, MDCO2 - mass of CO2 saved by the optimization method (ton); RigCO2 - daily emissions of CO2 by a drilling unit (ton/day)
Using the example in item 2.5, the environmental impact of the test would be 4 days x 90 tons CO2/day, saving 360 tons of CO2 emissions. Besides the savings of $4 million, the anticipation of production is another benefit of the optimization process.
3. Discussion and case study
Increases in the efficiency of a closed system rely on maximizing the output of work in relation to the amount of energy entering the system (Ang, et al. 2022). The desired maximum output of work here discussed is drilling each of the sections of the trajectory in the least time.
The most important factor of the optimization method is CM. Its value embeds the cost of all resources used and the overall time spent to overcome the existing challenges until completing the planned work. The more efficient is the system, the less resources and time are used in the transformation processes. The main objectives are identifying the factors related to increased efficiency, done by measuring the impact provided by each factor in the drilling process.
The dataset was filtered to research the drilling technology, resulting in the modified fingerprint seen in Figure 7. The chart demonstrates that the 58 coring jobs, seen in Table 1, were responsible for almost all high-cost operations. The following sections will analyze solely performances of the rollercone and fixed cutter bits. This is done by filtering off coring jobs, which are expensive special operations for retrieving in-situ samples of fresh rock (Santos, 2020).
The approach can be replicated for any KPI as bit diameter, WOB, RPM, flow rate, size of PDC cutters, IADC of the rollercone bit, usage of RSS or downhole motor, inclination etc. to evaluate the impact of each factor in the costs per meter.
3.1 Field record of the longest run in Albacora Leste
The points in the highest part of the chart in Figure 8 are of greatest interest. The largest extension drilled in a single run in the field was 1851 m, set in 2005 by a 12.¼”, 16 mm PDC bit with six blades. It was run using an RSS tool, which combines a downhole motor to increase the RPM at the bit and a guidance tool (Andrade et al., 2021). Close to the field record, the other four results seen were achieved by 8.½” PDC bits with six blades, 16 mm cutters. All five bits were run with RSS tools, pulled with well inclinations above 57°.
-
Noticeable different benchmarks denote that bit technology is a relevant factor regarding MD, the total length drilled at each bit run
-
Both factors a in the benchmark formula are positive, providing an increasing trend for MD
-
Due to the magnitude of factors a, both benchmarks are curvilinear; the higher value of a for PDC bits indicates a faster growing curve than for rollercone bits
-
The longest runs were achieved by PDC bits; due to the high cost of large diameter PDC bits, rollercone bits are preponderant in shallower sections
-
Despite being more expensive, they present a lower risk of leaving junk in the well, PDC bits drilled longer in depths above 2400 m
This section demonstrated the success of the optimization methods, with the MD increasing as wells get deeper, provided by the tougher bits used in deeper sections. Such charts are able to provide valuable insights for project engineers, anticipating tendencies invisible when looking at tables, analyzing field records or estimating averages of the best runs.
3.2 Field record of the longest bit life in Albacora Leste
The longest time drilling in a single run was 185 hours, achieved by an 18.⅛†PDC bit, seven blades, 16 mm cutters, run with an RSS tool in a vertical section. The field record, seen in Figure 9, is close to other four black dots, which are 16†and 12.¼” bits with six blades, 16 mm PDC cutters.
-
Different benchmarks denote that bit technology is a relevant factor regarding HR, or bit life
-
Due to the magnitude of a in both formulas, the benchmarks are curvilinear; both factors a are positive, reflecting an increase in the trend in time drilling in a single run
-
The higher value of a for PDC bits indicates a faster growing curve
-
The trend lines show that PDC bits are expected to drill longer in sections deeper than 2600 m
-
No rollercone bits were pulled deeper than 4000 m, an opportunity for the development of new technologies for drilling hard formations (Amorim Jr., Santos, et al., 2021)
The increasing benchmarks are the proof of success in developing tougher bits for the deepest sections, as bit life is naturally expected to decrease with depth and well temperature.
3.3 Field record of penetration rate in Albacora Leste
The highest ROP achieved in the field in a single run was 44.8 m/h, set in 2001 by a 17.½” steel tooth IADC 115M rollercone bit, built with bearings designed to run with downhole motors in directional wells (McGehee, D.Y. et al., 1992).
The five ROP field records are seen at about 2000 m in Figure 10. Seen in white dots, four of those were achieved by 17.½" IADC 115M bits, run in vertical sections using a downhole motor, benefiting from an increased total RPM and higher ROP. The 4th best ROP was achieved by a 12.¼" PDC bit, six blades, 19 mm cutters, run with a RSS tool, pulled with 29º of inclination. Please note that Figure 10 and Figure 4 are the same chart, but presenting performances filtered to demonstrate the power of the insights produced.
-
As predicted, there is a noticeable dispersion of ROP results around the benchmark in any depth
-
The benchmarks are virtually similar; this demonstrates that the bit technology is of lower relevance regarding the ROPs achieved in the Albacora Leste field
-
Two similar formulas modeled superposed and had almost straight, parallel decreasing lines
The low inclination of the curves demonstrates that the optimization method developed bits to drill faster in deeper sections, but not enough to reverse the natural tendency of decreasing ROPs.
3.4 Field record of cost per meter in Albacora Leste
The Y-axis of Figure 11 was limited to $15000 to provide focus at the lowest CM values. The field record of CM was 1181 US$/m, depicted in red at 1935 m at the bottom left of the chart. It was set by the 17.½” steel tooth bit which achieved the ROP field record, seen in section 3.3, showing the importance of saving time to the optimization process.
-
The chart above shows two almost straight exponentials, slightly increasing for rollercone bits, as naturally expected, and slightly decreasing for the PDC bits
-
Factor k2 is positive for rollercone bits and negative for PDC bits
-
The trendlines are very different, meaning that bit technology is relevant to the drilling costs
-
Although paradoxical, CM decreases for PDC bits with depth due to the development of good solutions for the deepest sections, providing many long runs with higher ROPs
-
The bit with the longest length drilled was pulled at 3549 m, CM = $2,863; it did not generate the lowest CM in the field, demonstrating the relative importance of field records
-
PDC bits pulled deeper than 2400 m are expected to be more economical
There is a visible opportunity for developing rollercone bits for drilling deeper than 4000 m to explore the pre-salt layers, as there are no results at that depth. The simulation of a test of a rollercone bit, seen above in blue, uses the rollercone benchmark as the objective. If the rollercone bit is pulled at 4500 m, it would save about $4000/m. With operational costs of a drill ship around $1 million/day, by drilling 1000 m the financial impact of the test would be $4 million, with a ND shortage of 4 days in drilling time and proportional CO2 emissions savings.
Besides these records, the highest gap, which is the biggest difference between any CM result and the benchmark value at the depth out, is even more important in the process. The technical limit, a utopic CM value for bit runs with a drilling efficiency of 100%, is the objective of the optimization process, as the ideal drilling conditions will be found at the contour conditions of the run.
3.5 Environmental impact of drilling rigs
A last example of the powerful insights about drilling operations provided by the methodology is seen in Figure 12. The Y-axis was limited to $20000/m for didactical purposes.
The chart in Figure 12 compares the CM produced by drill ships, pictured in light red dots, and semi-submersible rigs, pictured in light green dots. The conclusion is that the drilling efficiency of the rigs is not the same, as drill ships (DS) are slightly less efficient than semi-submersible rigs (SS), demonstrated by comparing both benchmarks.
As drill ships are not anchored, the rig demands more power than SS rigs due to the dynamic positioning system. Also, variable forces act in function of weather and wind speed (FAŸ 1990), besides the currents which stress drilling risers laterally along all the water depth, and waves which request rapid changes in instant power (Huang, Yang and Li, 2025).
4. Conclusions
The methodology attests the success of the optimization method in testing and developing more efficient drilling technologies. It was demonstrated that fingerprints are able to provide new visions of how different technologies and resources are able to influence the results in O&G exploration, fulfilling the absence of peer-reviewed holistic methodologies to benchmark drilling performances.
The case study discussed the field records, established along the drilling campaign in Albacora Leste, under a broader perspective. It was demonstrated that field records are not an absolute target to be chased. Besides that, some of the records were produced in shallower sections, meanwhile other runs in deeper sections provided a higher economic impact.
The outputs seen in the article are useful examples of tools for predicting drilling performances and costs. Demonstrated was the ability to research any factor related to a higher drilling efficiency, and to measure the financial and environmental gains in relation to different benchmarks.
Drilling for O&G will continue for decades until the cost of other sources of energy becomes lower than the cost of energy generated by hydrocarbons. In that sense, the methodology provides solutions that also contribute to ESG causes, optimizing drilling operations for CCUS and geothermal wells where the learnings will be applied in the long term to the society.
Acknowledgments
The authors praise Petrobras for releasing the necessary data to complete the research. We also praise the efforts made by the Agência Nacional de Petróleo (ANP) in releasing for public access valuable data about the O&G industry. Finally, we are grateful for the financial support of the project PRH-33.1, resolution ANP nº 918/2023, encouraging the researchers to publish scientific papers in a field of knowledge essential for the energy matrix of Brazil.
Acronymous
- ESG Environmental, Social and Governance
- FC Fixed Cutter
- GHG Greenhouse Gases
- KPI Key Performance Indices
- PDCA Plan, Do, Check, Act
- ND Number of Days
- PDC Polycrystalline Diamond Compact
- RC Rollercone
- ROP Rate of Penetration
- SS Semi-submersible rig
- WOB Weight on Bit
References
- 1 AL-ABDULJABBAR, Ahmad; MAHMOUD, Ahmed A.; SALAHELDIN, Elkatatny; MAHMOUD, Abughaban. Artificial neural networks-based correlation for evaluating the rate of penetration in a vertical carbonate formation for an entire oil field. Journal of Petroleum Science and Engineering, 2022.
- 1 AMORIM Jr., Dalmo S. Metodologia para a redução de custos na perfuração de poços de petróleo e gás. São Paulo, 2008.
- 1 AMORIM Jr., Dalmo S.; SANTOS, Edmilson Moutinho dos; SANTOS, Otto L. A.; BORGES, José Umberto A.; RITTERSHAUSEN, João H.; AMORIM, Milena A. R. CO2 Reduction in oil well drilling. In: INTERNATIONAL GAS RESEARCH CONFERENCE, 12, 2024. Banff, CA, 2024.
- 1 AMORIM Jr., Dalmo S.; SANTOS, Otto L. A.; AZEVEDO, Ricardo C.; CHIEREGATI, Ana Carolina. A solution for funding the development of technology in oil well. Journal of Petroleum Exploration and Production Technology (Springer), n. 11, p. 243-252, 2021.
- 1 ANDRADE, C. P. S.; SAAVEDRA, J. L.; TUNKIEL, A.; SUI, Dan. Rotary Steerable Systems: mathematical modeling and their case study. Journal of Petroleum Exploration and Production Technology, p. 2743-2761, 2021.
- 1 ANG, Tze-Zhang; SALEM, Mohamed; KAMAROL, Mohamed; DAS, Himadry S.; NAZARI, Mohammad A.; PRABAHARAN, N. A comprehensive study of renewable energy sources: classifications, challenges and suggestions. Energy Strategy Reviews, 2022.
-
1 ANP. Albacora Leste. 2016. Disponível em: https://www.gov.br/anp/pt-br/assuntos/exploracao-e-producao-de-oleo-e-gas/desenvolvimento-e-producao/pd/albacora_leste.pdf Acesso em: 2023.
» https://www.gov.br/anp/pt-br/assuntos/exploracao-e-producao-de-oleo-e-gas/desenvolvimento-e-producao/pd/albacora_leste.pdf -
1 ANP. Mapas de E&P. 2022. Disponível em: https://www.gov.br/anp/pt-br/assuntos/exploracao-e-producao-de-oleo-e-gas/dados-tecnicos/mapas-e-p Acesso em: 2023.
» https://www.gov.br/anp/pt-br/assuntos/exploracao-e-producao-de-oleo-e-gas/dados-tecnicos/mapas-e-p -
1 ANP. Tabela de poços. 02 16, 2023. Disponível em: https://www.gov.br/anp/pt-br/assuntos/exploracao-e-producao-de-oleo-e-gas/dados-tecnicos/ad/tabela-de-pocos.xlsx
» https://www.gov.br/anp/pt-br/assuntos/exploracao-e-producao-de-oleo-e-gas/dados-tecnicos/ad/tabela-de-pocos.xlsx -
1 ANP/BPPGN. Boletim da Produção de Petróleo e Gás Natural. 2023. Disponível em: https://www.gov.br/anp/pt-br/centrais-de-conteudo/publicacoes/boletins-anp/boletins/arquivos-bmppgn/2023/boletim-junho-pdf.pdf Acesso em: 2023.
» https://www.gov.br/anp/pt-br/centrais-de-conteudo/publicacoes/boletins-anp/boletins/arquivos-bmppgn/2023/boletim-junho-pdf.pdf - 1 ARDEKANI, Omid S.; SHADIZADEH, Seyed R. Development of drilling trip time model for southern Iranian oil. JPEPT, p.287-295, 2013.
- 1 BOURGOYNE, Adam T.; KEITH, K. Millheim; MARTIN, E. Chenevert; YOUNG JÚNIOR, F. S. Applied Drilling Engineering. SPE, 1986.
- 1 CARVALHO, Carlos Henrique R. Emissões relativas de poluentes do transporte motorizado de passageiros nos grandes centros urbanos brasileiros. IPEA, p. 42, 2011.
-
1 EPBR. Petrobras vai vender Albacora e Albacora Leste. 09 25, 2020. Disponível em: https://epbr.com.br/petrobras-vai-vender-albacora-e-albacora-leste/ Acesso em: 2023.
» https://epbr.com.br/petrobras-vai-vender-albacora-e-albacora-leste/ - 1 FAŸ, Hubert. Dynamic positioning systems: principles, design, and applications. Paris, 1990.
- 1 HUANG, Fang F.; YANG, Jin; LI, Bin. Dynamic characteristics and safety analysis of drill strings in deepwater open hole drilling. Energy Exploration & Exploitation, 2025.
-
1 IPIECA. Drilling rigs. 2023. Disponível em: https://www.ipieca.org/resources/energy-efficiency-compendium
» https://www.ipieca.org/resources/energy-efficiency-compendium - 1 KAMBOH, Shakeel A.; ABDUL, Q. Jakhrani; AL-KHALID, Othman; ANDREW, R. H. Rigid, and Saleem R. Samo. Estimation of carbon footprints from diesel generator emissions. In: INTERNATIONAL CONFERENCE IN GREEN AND UBIQUITOUS TECHNOLOGY. SARAWAK, 2, 2012. p. 4.
-
1 MATHWORKS. Parametric Fitting. 2024. Disponível em: https://www.mathworks.com/help/curvefit/parametric-fitting.html
» https://www.mathworks.com/help/curvefit/parametric-fitting.html - 1 MAZEN, Ahmed Z.; RAHMANIAN, Nejat; MUJTABA, Iqbal M. M.; HASSANPOUR, Ali Effective mechanical specific energy: a new approach for evaluating PDC bit performance and cutters wear. Journal of Petroleum Science and Engineering, 10, 2021.
- 1 MCGEHEE, D. Y. et al. The IADC Roller Bit Dull grading system. In: IADC/SPE DRILLING CONFERENCE, Louisiana, USA: IADC/SPE, 1992. p. 819-834.
- 1 MCGEHEE, D.Y. et al. The IADC Roller Bit classification system. In: IADC/SPE 23937. Louisiana, USA: Society of Petroleum Engineers, 1992. p. 801-818.
-
1 MINITAB. Análise de regressão: como interpretar o R-quadrado e avaliar a qualidade de ajuste? 2019. Disponível em: https://blog.minitab.com/pt/analise-de-regressao-como-interpretar-o-r-quadrado-e-avaliar-a-qualidade-de-ajuste
» https://blog.minitab.com/pt/analise-de-regressao-como-interpretar-o-r-quadrado-e-avaliar-a-qualidade-de-ajuste - 1 MOHRIAK, Webster U. Bacias sedimentares da margem continental brasileira. Geologia, Tectônica e Recursos Minerais do Brasil, p. 87-94, 2003.
- 1 MURTAGH, Jack. The math mystery that connects sudoku, flight schedules and protein folding. Scientific American, 2025.
- 1 OYEDERE, Mayowa; KEN, Gray. ROP and TOB optimization using machine learning classification algorithms. Journal of Natural Gas Science and Engineering, 02 25, p. 13, 2020.
- 1 PAVKOVIC, Danijel; SEDIC, Almir; GUZOVIC, Zvonimir. Oil drilling rig diesel power-plant fuel efficiency improvement potentials through rule-based generator scheduling and utilization of battery energy storage system. Energy Conversion and Management, 05 06, p. 194-211, 2016.
- 1 PAYNE, M. L.; ABBASSIAN, F. Advanced torque and drag considerations in extended-reach wells. In: IADC/SPE DRILLING CONFERENCE. New Orleans, 1996.
- 1 PORFIRIO, L. L. P. Estudo do reservatório de Coquinas do Grupo Lagoa Feia (Eocretáceo) na acumulação de Linguado, sudoeste da Bacia de Campos. UNESP, Rio Claro, SP, 2009, p. 41.
- 1 PRASHAR, Anupama. Adopting PDCA (Plan-Do-Check-Act) cycle for energy optimization in energy-intensive SMEs. Journal of Cleaner Production, p. 17, 2017.
-
1 ROUSSEFF, Dilma V. Lei nº 12527. 2011. Disponível em: https://www.planalto.gov.br/ccivil_03/_ato2011-2014/2011/lei/l12527.htm Acesso em: 17 nov. 2023.
» https://www.planalto.gov.br/ccivil_03/_ato2011-2014/2011/lei/l12527.htm - 1 RUST, Bert W. Fitting nature's basic functions. Part III: exponentials, sinusoids, and nonlinear least squares. Computing in Science & Engineering, 2002.
- 1 SANTOS, Priscila T. Caracterização tectono-estratigráfica e faciológica dos reservatórios carbonáticos do pré-sal do campo de Búzios. Dissertação (Mestrado) - Universidade Estadual do Rio de Janeiro, 2020. 257 p.
- 1 SHAYGAN, Kaveh; SAEID, Jamshidi. Prediction of rate of penetration in directional drilling using data mining techniques. Journal of Petroleum Science and Engineering, 11, 2022.
- 1 SMITI, Abir. A critical overview of outlier detection methods. Computer Science Review, 2020.
- 1 STAPENHURST, Tim. The benchmarking book. Edited by Butterworth-Heinemann. Oxford: Elsevier, 2009. 1 v.
-
1 UNIVERSITY OF EXETER. Calculation of CO2 emissions. 10 11, 2022. Disponível em: https://people.exeter.ac.uk/TWDavies/energy_conversion/Calculation%20of%20CO2%20emissions%20from%20fuels.htm
» https://people.exeter.ac.uk/TWDavies/energy_conversion/Calculation%20of%20CO2%20emissions%20from%20fuels.htm - 1 VAN KAMPEN, N. G. Stochastic processes in physics and chemistry. 4 ed.. Oxford, EN: Elsevier, 1992.
- 1 WAN, Youwei; LIU, Xiangjun; XIONG, Jian; LIANG, Lixi. Intelligent prediction of drilling rate of penetration based on method-data dual validity analysis. SPE Journal, 10, 2023.
- 1 WIKTORSKI, Ekaterina; KUZNETCOV, Artem; SUI, Dan. ROP optimization and modeling in directional drilling process. Edited by Society of Petroleum Engineers. In: SPE BERGEN ONE DAY SEMINAR. Bergen, Norway, 2017. 14.
- 1 ZENG, Kan H.; MIN, Wu; CHENG, D.; LU, Xiao Yang; ZHE, J. Ma. Prediction of rate of penetration using gaussian process regression and bayesian optimization for drilling process. 2024.