Project management in public-private partnerships: a conceptual framework based on a systematic literature review

Gestão de projetos em parcerias público-privadas: uma estrutura conceitual baseada em uma revisão sistemática da literatura

Abstract:

Despite the increasing number of Public-Private Partnerships projects, the results have shown little effectiveness and difficulties in several aspects of project management. This study performs a systematic literature review combining bibliometric analysis and content analysis to identify the challenges in managing these projects and techniques to overcome them, highlighting the critical success factors for project management. The results indicate an increasing number of researches in the field, but there is still a lack of systematization of the management tools and absence of critical success factors during the accomplishment of this type of project. This study proposes a systematization of these elements throughout the project cycle, allowing project managers to visualize challenges and techniques to increase the results related to the main success factors of each stage.

Keywords:
Project management; Public-private-partnerships; Systematic literature review

Resumo:

Apesar do crescente número de projetos de Parcerias Público-Privadas, os resultados têm apontado pouca eficácia e dificuldades em diversos aspectos da gestão de projetos. Este estudo realiza uma revisão sistemática de literatura, combinando análise bibliométrica e análise conteúdo para identificar quais os desafios na gestão desses projetos e técnicas para superá-los, destacando os fatores críticos de sucesso para gestão de projetos. Os resultados apontam que o número de pesquisas é crescente, mas ainda há falta de sistematização das ferramentas de gestão e ausência dos fatores críticos de sucesso ao longo da realização deste tipo de projeto. Este estudo propõe então uma sistematização desses elementos ao longo do ciclo do projeto, sendo subsídio para gestores de projetos visualizarem desafios e técnicas para aumentarem os resultados relacionados aos principais fatores de sucesso de cada etapa.

Palavras-chave:
Gestão de projetos; Parcerias-público-privadas; Revisão sistemática de literatura

1 Introduction

The relevance and popularity of the Public-Private Partnership projects (PPPs) were intensified in the 80s and 90s with governments, historically recognized as basic infrastructure providers for the population, faced with the challenge of reducing public deficits and increasing investment in public infrastructure (Tang et al., 2010Tang, L., Shen, Q., & Cheng, E. W. (2010). A review of studies on public–private partnership projects in the construction industry. International Journal of Project Management, 28(7), 683-694. http://dx.doi.org/10.1016/j.ijproman.2009.11.009.
http://dx.doi.org/10.1016/j.ijproman.200...
); PPPs also gained strength in times of international crisis as of mid-2007 to 2008 (Osei-Kyei & Chan, 2015Osei-Kyei, R., & Chan, A. P. (2015). Review of studies on the Critical Success Factors for Public–Private Partnership (PPP) projects from 1990 to 2013. International Journal of Project Management, 33(6), 1335-1346. http://dx.doi.org/10.1016/j.ijproman.2015.02.008.
http://dx.doi.org/10.1016/j.ijproman.201...
). In this sense, studies show that the main objective of the PPP projects is the transference of risks from the public sector to the private sector as a way to facilitate and accelerate infrastructure plans for the common good, on the other hand this relationship causes various conflicts of interest (Hwang et al., 2013Hwang, B. G., Zhao, X., & Gay, M. J. S. (2013). Public private partnership projects in Singapore: Factors, critical risks and preferred risk allocation from the perspective of contractors. International Journal of Project Management, 31(3), 424-433. http://dx.doi.org/10.1016/j.ijproman.2012.08.003.
http://dx.doi.org/10.1016/j.ijproman.201...
; Liu, J., et al., 2016bLiu, T., Wang, Y., & Wilkinson, S. (2016). Identifying critical factors affecting the effectiveness and efficiency of tendering processes in Public–Private Partnerships (PPPs): A comparative analysis of Australia and China. International Journal of Project Management, 34(4), 701-716. http://dx.doi.org/10.1016/j.ijproman.2016.01.004.
http://dx.doi.org/10.1016/j.ijproman.201...
).

Despite the popularity of PPP projects, the results of such projects are still presented as inefficient (Flyvbjerg, 2013Flyvbjerg, B. (2013). Quality control and due diligence in project management: getting decisions right by taking the outside view. International Journal of Project Management, 31(5), 760-774. http://dx.doi.org/10.1016/j.ijproman.2012.10.007.
http://dx.doi.org/10.1016/j.ijproman.201...
) or with critical success factors poorly explored and systematized (Liu, T., et al., 2016aLiu, J., Gao, R., Cheah, C. Y., & Luo, J. (2016). Incentive mechanism for inhibiting investors’ opportunistic behavior in PPP projects. International Journal of Project Management, 34(7), 1102-1111. http://dx.doi.org/10.1016/j.ijproman.2016.05.013.
http://dx.doi.org/10.1016/j.ijproman.201...
). Concentrated mostly in asian context and more specifically in China (Zhang et al., 2016aZhang, S., Chan, A. P., Feng, Y., Duan, H., & Ke, Y. (2016a). Critical review on PPP Research–A search from the Chinese and International Journals. International Journal of Project Management, 34(4), 597-612. http://dx.doi.org/10.1016/j.ijproman.2016.02.008.
http://dx.doi.org/10.1016/j.ijproman.201...
), qualitative surveys as the one done by and Verweij (2015b)Verweij, S. (2015b). Producing satisfactory outcomes in the implementation phase of PPP infrastructure projects: A fuzzy set qualitative comparative analysis of 27 road constructions in the Netherlands. International Journal of Project Management, 33(8), 1877-1887. http://dx.doi.org/10.1016/j.ijproman.2015.08.006.
http://dx.doi.org/10.1016/j.ijproman.201...
highlight the use of bad indicators for evaluating management between different stakeholders and general outcomes of PPP projects. In Brazil, although the use of this type of project is recent (Federal law regulating PPPs was enforce in 2004 - Brasil, 2004Brasil. (2004, 31 de dezembro). Lei nº 11.079 de 30 de dezembro de 2004. Institui normas gerais para licitação e contratação de parceria público-privada no âmbito da administração pública. Brasília, DF: Diário Oficial da República Federativa do Brasil. Retrieved in 2017, August 11, from http://www.planalto.gov.br/ccivil_03/_ato2004-2006/2004/Lei/L11079.htm
http://www.planalto.gov.br/ccivil_03/_at...
), there is a high expectation that this is one of the solutions to overcome deficiencies in the country infrastructure, encouraged by hosting of major international events (World Cup and Olympics) in the last five years. The reality, however, points out that despite all promises, this model has great difficulties to take off in the country, especially because of bureaucracies barriers, uncertainty for investors working with volatile governments, lack of tradition in the area and corruption scandals in recent years involving both parties (public and private institutions) (Thamer & Lazzarini, 2015Thamer, R., & Lazzarini, S. (2015). Projetos de parceria público-privada: fatores que influenciam o avanço dessas iniciativas. Revista de Administração Pública, 49(4), 819-846. http://dx.doi.org/10.1590/0034-7612119746.
http://dx.doi.org/10.1590/0034-761211974...
).

In this sense, one of the most critical points raised is the relationship management between the public and private body, which bring different interests and cultures in a long-term project. Despite the contributions of Wang & Liu (2015)Wang, Y., & Liu, J. (2015). Evaluation of the excess revenue sharing ratio in PPP projects using principal–agent models. International Journal of Project Management, 33(6), 1317-1324. http://dx.doi.org/10.1016/j.ijproman.2015.03.002.
http://dx.doi.org/10.1016/j.ijproman.201...
analyzing excessive rates of profitability and its relation to the risks assumed by the private partner and of Zhang et al. (2015)Zhang, S., Gao, Y., Feng, Z., & Sun, W. (2015). PPP application in infrastructure development in China: institutional analysis and implications. International Journal of Project Management, 33(3), 497-509. http://dx.doi.org/10.1016/j.ijproman.2014.06.006.
http://dx.doi.org/10.1016/j.ijproman.201...
that focus on systematizing governance models for the implementation phase of the project, the literature lacks a review to examine the challenges, solution proposals and success factors from a global perspective, that considers entire life cycle of this type of project, from the definition phase to long-term project maintenance.

Thus, in order fill this research gap, this study aims to carry out an analysis and systematization of the literature on public-private partnerships in the project management (PM) field, seeking answer for the following research questions (RQs): RQ1: What are the main challenges for PM in the context of PPPs? RQ2: What techniques have been used to solve or mitigate the PM difficulties in PPPs? RQ3: How the PM success factors apply to the PPP context?

Given the recent BNDES report (Pinto & Ang, 2015Pinto, H. A. C., & Ang, H. G. (2015). Estruturação de Projetos de PPP e Concessão no Brasil: diagnóstico do modelo brasileiro e propostas de aperfeiçoamento. Washington: International Finance Corporation - World Bank Group.) indicating that, today, more than ever, it is important discuss the PPP model in Brazil, this study aims to fill this literature gap by systematizing key concepts for successful project management in PPP, a topic of increasing academic interest (Quelin et al., 2014Quelin, B., Cabral, S., Lazzarini, S. G., & Kivleniece, I. (2014). The Private Scope in Public-Private Partnerships: An International Cross-Sector Study. Business Policy & Strategy, 2014(1), 15727. http://dx.doi.org/10.5465/ambpp.2014.15727abstract.
http://dx.doi.org/10.5465/ambpp.2014.157...
), and to bring higher input and a greater understanding of the subject to practitioners on the most important points to consider when performing projects of this nature, given the difficulty that exists to make this model work engage in many emerging countries, as in Brazil. As a consequence, this research also aims to bring a better understanding on public-private interactions that can greatly assist the design and execution of PPPs which meet the needs of the population and bring welfare, appointed as required by Thamer & Lazzarini (2015)Thamer, R., & Lazzarini, S. (2015). Projetos de parceria público-privada: fatores que influenciam o avanço dessas iniciativas. Revista de Administração Pública, 49(4), 819-846. http://dx.doi.org/10.1590/0034-7612119746.
http://dx.doi.org/10.1590/0034-761211974...
. To achieve these goals, this research includes the identification of the most influential articles, relevant research initiatives and studies, the identification of the most common elements from challenges in managing such projects. The methodological approach for the systematic literature review combines two methods: a bibliometric approach and content analysis. The sample was extracted from the scientific bases Web of Knowledge, Scopus and International Journal of Project Management (journal with highest impact factor in project management area, according the Journal Citation Report).

This article is structured as follows: section 2 presents a literature review on the topic, Section 3 presents the methodological approach; Section 4 presents the literature review based on the results of bibliometric analysis, network analysis and content analysis; Section 5 presents the discussion of the results obtained by bibliometric analysis and content analysis, finally, section 6 presents a conclusion and contributions of this research.

2 Literature review

The PPP concept begins in the moment that the public sector decides to solve the financial constraints to provide public facilities and services, recurring to the private sector skilss to increase efficiency, effectiveness and quality of services offered to the population (Treasury, 2006Treasury, H. M. (2006). Public private partnerships: the governments approach. London: United Kingdom for The Stationery Office.). Despite strong growth in the realization of PPP between the 80 and 90, private investments in public infrastructure can be found since the 18th century in several countries. In Europe we have the example of the Suez Canal and railroads, examples can also be found United States, China and Japan (Kumaraswamy & Morris, 2002Kumaraswamy, M. M., & Morris, D. A. (2002). Build-operate-transfer-type procurement in Asian megaprojects. Journal of Construction Engineering and Management, 128(2), 93-102. http://dx.doi.org/10.1061/(ASCE)0733-9364(2002)128:2(93).
http://dx.doi.org/10.1061/(ASCE)0733-936...
)

Through PPPs the public sector employs private resources to carry out public infrastructure works (Skietrys et al., 2008Skietrys, E., Raipa, A., & Bartkus, E. V. (2008). Dimensions of the efficiency of public-private partnership. The Engineering Economist, 58(3)), benefiting from the expertise of companies and the use of efficient management practices for the development of public works (Akintoye et al., 2003Akintoye, A., Hardcastle, C., Beck, M., Chinyio, E., & Asenova, D. (2003). Achieving best value in private finance initiative project procurement. Construction Management and Economics, 21(5), 461-470. http://dx.doi.org/10.1080/0144619032000087285.
http://dx.doi.org/10.1080/01446190320000...
). One of the main characteristics of PPPs is risk sharing between the public and private sector (Ke et al., 2010aKe, Y., Wang, S., Chan, A. P., & Lam, P. T. (2010a). Preferred risk allocation in China’s public-private partnertship (PPP) projects. International Journal of Project Management, 28(5), 482-492. https://doi.org/10.1016/j.ijproman.2009.08.007.
https://doi.org/ https://doi.org/10.1016...
), the risks are identified and allocated to the part with best skills, techniques and resources to mitigate them (Li et al., 2005aLi, B., Akintoye, A., Edwards, P. J., & Hardcastle, C. (2005a). Critical success factors for PPP/PFI projects in the UK construction industry. Construction Management and Economics, 23(5), 459-471. http://dx.doi.org/10.1080/01446190500041537.
http://dx.doi.org/10.1080/01446190500041...
). Tang et al. (2010)Tang, L., Shen, Q., & Cheng, E. W. (2010). A review of studies on public–private partnership projects in the construction industry. International Journal of Project Management, 28(7), 683-694. http://dx.doi.org/10.1016/j.ijproman.2009.11.009.
http://dx.doi.org/10.1016/j.ijproman.200...
point out advantageous aspects of PPPs found in several studies: improving the partnership between the public and private sectors, better risk management, clearer government policies, critical success factors disclosure, improved contract maturity and more appropriate financial analysis.

In this context, various types of partnership began to be made between government and the private sector. According to Li et al. (2005a)Li, B., Akintoye, A., Edwards, P. J., & Hardcastle, C. (2005a). Critical success factors for PPP/PFI projects in the UK construction industry. Construction Management and Economics, 23(5), 459-471. http://dx.doi.org/10.1080/01446190500041537.
http://dx.doi.org/10.1080/01446190500041...
the UK government recognizes eight different forms of this partnership model: Asset Sales: it is selling surplus assets of the public sector, the broader market: introduces the skills of private sector funding to help better use of assets of the public sector. Business Sales: it is the sale of shares in public enterprises by flotation or trade sale, Partnership Companies: includes the introduction of the property of the private sector in state owned enterprises, while preserving the public interest through legislation, regulations, etc. Private Finance Initiative, joint ventures, in which public companies and industry partners pool their resources together and live under joint management. Investments in partnerships, in which the public sector contributes to the financing of investment by the private sector, to ensure that the public sector takes part in the return generated. Political partnerships, in which individuals from the private sector, or parts, are involved in the development or implementation of public sector policies. The Private Finance Initiative ia the most common model in the UK and other countries.

The PPPs allow governments to focus their attention and resources on their core competencies without needing to spend the public funds in complex projects which are unfamiliar to them (Cumming, 2007Cumming, D. (2007). Government policy towards entrepreneurial finance: innovation investment funds. Journal of Business Venturing, 22(2), 193-235. http://dx.doi.org/10.1016/j.jbusvent.2005.12.002.
http://dx.doi.org/10.1016/j.jbusvent.200...
). By applying techniques, experience, technology and innovation of the private sector the resources, assets, the knowledge of the public sector can be used more efficiently by reducing costs and increasing the quality of facilities and utilities (Edkins & Smyth, 2006Edkins, A. J., & Smyth, H. J. (2006). Contractual management in PPP projects: evaluation of legal versus relational contracting for service delivery. Journal of Professional Issues in Engineering Education and Practice, 132(1), 82-93. http://dx.doi.org/10.1061/(ASCE)1052-3928(2006)132:1(82).
http://dx.doi.org/10.1061/(ASCE)1052-392...
). Regarding economy and efficient use of resources, PPPs can produce a large reduction in the cost of public projects because the private sector brings greater discipline to the execution of projects which reduces the risk of cost overruns and project delays; additionally due to private sector interest in recovering their investments the PPP model leads to a reduction in the project life cycle costs and guarantees the expected return rate for government investment (Li & Akintoye, 2003Li, B., & Akintoye, A. (2003). An overview of public-private partnership (pp. 3-30). Blackwell Science: Oxford, UK.).

Despite the many advantages presented by PPPs Kumaraswamy & Zhang (2001)Kumaraswamy, M. M., & Zhang, X. Q. (2001). Governmental role in BOT-led infrastructure development. International Journal of Project Management, 19(4), 195-205. http://dx.doi.org/10.1016/S0263-7863(99)00069-1.
http://dx.doi.org/10.1016/S0263-7863(99)...
present several cases of PPP which had problems such as cost overruns, unrealistic price and revenue projections and legal disputes between the private sector and the government. Flyvbjerg (2013)Flyvbjerg, B. (2013). Quality control and due diligence in project management: getting decisions right by taking the outside view. International Journal of Project Management, 31(5), 760-774. http://dx.doi.org/10.1016/j.ijproman.2012.10.007.
http://dx.doi.org/10.1016/j.ijproman.201...
points out that most of the mega-projects exceed the budget, present schedule delays and fail to deliver the expected results, it is suggested that the main cause for these problems are failures in planning caused by ineffective planning methods that don’t use distributional data from similar enterprises or misrepresentation of the facts motivated by interests of planners to achieve an objective their own interest, for example, win the bid for a project. Other obstacles to the adoption of PPPs are high transaction costs, unattractive financial market, lack of appropriate skills, incomplete risk transfer, higher rates to end users (Aritua et al., 2009Aritua, B., Smith, N. J., & Bower, D. (2009). Construction client multi-projects–A complex adaptive systems perspective. International Journal of Project Management, 27(1), 72-79. http://dx.doi.org/10.1016/j.ijproman.2008.02.005.
http://dx.doi.org/10.1016/j.ijproman.200...
).

The benefits of adopting PPPs, potential barriers to success and complexity of PPP project management, particularly in the areas of risk management, relationship management, finance and critical success factors contribute to the importance of an extensive review and structuring of PPP project management studies that will contribute to the practitioners to be better informed and prepared, which will increase the chances of successful implementation of PPPs.

3 Research method

Project Management (PM) and Public-Private Partnership (PPP) topics, despite the high intersection, need to be reviewed to organize the existing literature. In order to answer the research questions, this study proposes a systematic literature review (SLR) to evaluate the studies that have synergy with these two issues.

SLR is composed of a multiple method, comprising a bibliometric network analysis and subsequent analysis of content. A bibliometric analysis with networks provides the construction of an overview of the issues from a quantitative and unbiased approach, while the content analysis can identify and summarize the main challenges, solutions and PM success factors in PPPs (Carvalho et al., 2013Carvalho, M., Fleury, A., & Lopes, A. P. (2013). An overview of the literature on technology roadmapping (TRM): contributions and trends. Technological Forecasting and Social Change, 80(7), 1418-1437. http://dx.doi.org/10.1016/j.techfore.2012.11.008.
http://dx.doi.org/10.1016/j.techfore.201...
).

3.1 Sample colection

For the construction of the initial sampling, this study did a search for publications indexed in two academic scientific basis, Web of Science and Scopus, whose search process was triangulated with searches in the journal International Journal of Project Management - IJPM.

The Web of Science was initially chosen because covers only the results of most relevant journals (journals with impact factor (JCR) calculated in the period from 1980 to 2014) of several other databases such as ProQuest, Wiley and Scopus (Carvalho et al., 2013Carvalho, M., Fleury, A., & Lopes, A. P. (2013). An overview of the literature on technology roadmapping (TRM): contributions and trends. Technological Forecasting and Social Change, 80(7), 1418-1437. http://dx.doi.org/10.1016/j.techfore.2012.11.008.
http://dx.doi.org/10.1016/j.techfore.201...
).

Thus, for the first data collection, held in September 2016, a search by the union of strings of words was made: “project management” and “public private partnership*” in the Web of Science. The research result was filtered to display only “articles” in the parameter “document types”, as these are publications that have gone through the review process (Carvalho et al., 2013Carvalho, M., Fleury, A., & Lopes, A. P. (2013). An overview of the literature on technology roadmapping (TRM): contributions and trends. Technological Forecasting and Social Change, 80(7), 1418-1437. http://dx.doi.org/10.1016/j.techfore.2012.11.008.
http://dx.doi.org/10.1016/j.techfore.201...
). The size of the sample was collected 23 articles.

Then searches were conducted in the scientific basis Scopus, which like Web of Science is also a database aggregator, but also presents articles journal that are not classified by impact factor metrics - JCR from Thomson Reuters. Following the same process, the searching and filtering described above for the Web of Science were presented 238 results.

The last phase for the sample publications in this study included the search for journal articles in the most relevant PM area, IJPM, according to the JCR impact factor of 2.885. Whereas the articles in this journal are also analyzed in the other two bases, this quest served as a critical review of the results of the previous searches. The result was 123 samples, with an intersection of only 37% with the sum of the samples from the databases. Web of Science and Scopus. With the composition of the three different searches, the result was a total of 319 different publications.

3.2 Studies selection

The samples were stored in an Excel spreadsheet, containing all information relevant to each publication (title, year of publication, number of citations, keywords, abstract, etc.). To identify which of the studies had effective relationship with the studied subjects, a quick scan was performed in three steps (Croom, 2009Croom, S. (2009). Introduction to research methodology in operations management. In C. Karlsson (Ed.), Researching operations management (pp. 42-83). Routledge: Taylor & Francis Group.), as shown in Figure 1.

Figure 1
Process for selection of studies.

As Figure 1 indicates, in the first stage were evaluated titles and keywords of the articles, by all researchers of the group. Those that were clearly outside the scope were removed from the sample and, if this first analysis was inconclusive (lack of consensus), the articles remained in the sample. After filtering the first, 72 files were considered within the scope and 109 inconclusive, thus achieving 181 results. In the second step, to the 109 items that could not be classified as inside or outside of the subjects was performed similar validation process of abstracts. At the end of this second stage, the sample contained 88 items classified as within the scope and 36 articles still lacking of consensus among researchers. In the last stage, the 36 articles were read by complete and 11 of them were directly related to the topics of PM and PPP, composing a final sample of 99 articles for analysis bibliometric data.

To perform the content analysis, we selected only the most relevant items according to their impact factor. To calculate the impact factor of each article, it was considered according Equation 1, the average number of citations and the journal impact factor in which was published by the Journal Citation Report (JCR) and held in Takey & Carvalho (2016)Takey, S. M., & Carvalho, M. M. (2016). Fuzzy front end of systemic innovations: A conceptual framework based on a systematic literature review. Technological Forecasting and Social Change, 111, 97-109. http://dx.doi.org/10.1016/j.techfore.2016.06.011.
http://dx.doi.org/10.1016/j.techfore.201...
.

I = C * J C R + 1 (1)

Whereas the equation impact factor (1), Pareto analysis was performed to select 24% of items (24 items in this case) that represent more than 80% of the sample impact total for content analysis (Takey & Carvalho, 2016Takey, S. M., & Carvalho, M. M. (2016). Fuzzy front end of systemic innovations: A conceptual framework based on a systematic literature review. Technological Forecasting and Social Change, 111, 97-109. http://dx.doi.org/10.1016/j.techfore.2016.06.011.
http://dx.doi.org/10.1016/j.techfore.201...
).

3.3 Data analysis

The first part of the data analysis comprises a bibliometric study and analysis of separate networks in three stages. The objective of the first stage of the bibliometric analysis was identification of the most relevant journals for the subject and the development of publications on the subject among the years. To identify the most relevant journals, it was considered the following factors: number of publications (Np), Number Quote (Nc) and Impact Factor (Fi). Periodicals were ordered according number of quotes. Then, as a way of assessing how publications have evolved over time, the number of stratified Publications by journal per year was assessed.

For the second step, in order to characterize the publications on the subject changes in the number of publications per year, it were analyzed considering the method and the focus of study. For the definition of the categories method, it was used the reference scheme proposed by Carvalho et al. (2013)Carvalho, M., Fleury, A., & Lopes, A. P. (2013). An overview of the literature on technology roadmapping (TRM): contributions and trends. Technological Forecasting and Social Change, 80(7), 1418-1437. http://dx.doi.org/10.1016/j.techfore.2012.11.008.
http://dx.doi.org/10.1016/j.techfore.201...
, and, for setting the focus of study categories, it was used an adaptation scheme proposed by Tang et al. (2010)Tang, L., Shen, Q., & Cheng, E. W. (2010). A review of studies on public–private partnership projects in the construction industry. International Journal of Project Management, 28(7), 683-694. http://dx.doi.org/10.1016/j.ijproman.2009.11.009.
http://dx.doi.org/10.1016/j.ijproman.200...
, considering a single set of categories for both types of studies: conceptual and empirical. The category of Concession Period was unified with the category of Finance. Table 1 shows the encoding scheme used to classify the articles and the results are presented in Appendix A Appendix A Characterization of studies according to method and focus. Reference Method Focus 1 Grimsey & Lewis (2002) PE2 T2 2 Bing et al. (2005) PE1 T2 3 Zhang (2005) PE1 T4 4 El-Gohary et al. (2006) PC2 T1 5 Smyth & Edkins (2007) PE1 T1 6 Van Marrewijk et al. (2008) PE2 T4 7 Medda (2007) PC2 T2 8 Toor & Ogunlana (2010) PE1 T4 9 Shen et al. (2006) PE2 T2 10 Kumaraswamy & Zhang (2001) PC1 T4 11 Ke et al. (2010a) PE1 T2 12 Tang et al. (2010) PC1 T4 13 Aritua et al. (2009) PC2 T4 14 Li et al. (2005a) PE1 T4 15 Van Marrewijk (2007) PE2 T4 16 Clifton & Duffield (2006) PC2 T4 17 Jin & Zhang (2011) PE1 T2 18 Zhang (2007) PC2 T2 19 Reijniers (1994) PE2 T4 20 Hwang et al. (2013) PE1 T2 21 Yeo & Tiong (2000) PE2 T2 22 Flyvbjerg (2013) PE2 T4 23 Bachy & Hameri (1997) PC2 T4 24 De Lemos et al. (2004) PE2 T2 25 Zou et al. (2014) PE1 T4 26 Singh & Kalidindi (2006) PE2 T2 27 Devapriya (2006) PC2 T3 28 Ke et al. (2010b) PE1 T2 29 Edelenbos & Klijn (2009) PE1 T4 30 Daube et al. (2008) PC2 T3 31 Li et al. (2005b) PE1 T3 32 Yu & Kwon (2011) PE1 T4 33 Xu et al. (2012) PE2 T3 34 Yang et al. (2010) PE1 T4 35 Yuan et al. (2009) PE1 T4 36 Biesenthal & Wilden (2014) PC1 T4 37 Edkins & Smyth (2006) PE1 T1 38 Liu & Wilkinson (2014b) PE2 T3 39 De Schepper et al. (2014) PE2 T1 40 Ling et al. (2014) PE1 T1 41 Carbonara et al. (2014) PE2 T5 42 Tang & Shen (2013) PE1 T1 43 Jacobson & Ok Choi (2008) PE2 T4 44 Cheung & Chan (2011) PE1 T2 45 Osei-Kyei & Chan (2015) PC1 T4 46 Guo et al. (2014) PE2 T2 47 Kakabadse et al. (2007) PE2 T3 48 Verweij (2015a) PE2 T4 49 Liu et al. (2014b) PC2 T3 50 Henisz (2006) PE2 T2 51 Codecasa & Ponzini (2011) PE2 T4 52 Edelenbos & Teisman (2008) PE2 T4 53 Pitsis et al. (2014) PC2 T4 54 Liu et al. (2014a) PC2 T4 55 Jefferies & McGeorge (2009) PE2 T3 56 Heravi & Hajihosseini (2011) PE2 T2 57 Ye et al. (2014) PE1 T3 58 Kwak et al. (2014) PE2 T4 59 Fogelberg & Thorpenberg (2012) PE2 T1 60 Roumboutsos & Pantelias (2015) PE2 T2 61 Chen et al. (2006) PC2 T1 62 Lenferink et al. (2013) PE2 T1 63 Chowdhury et al. (2011) PC2 T1 64 Henjewele et al. (2014) PE2 T4 65 Dulaimi et al. (2010) PE2 T4 66 Rajan et al. (2013) PC2 T4 67 Wang (2015) PE2 T2 68 Chou & Pramudawardhani (2015) PE1 T3 69 Bayley (2003) PE2 T3 70 Yun et al. (2015) PE1 T4 71 Mistarihi et al. (2013) PE2 T1 72 Mota & Moreira (2015) PC2 T4 73 Liu & Wilkinson (2014a) PE2 T4 74 Carpintero & Petersen (2015) PE2 T2 75 Liu et al. (2015) PC1 T4 76 Atmo & Duffield (2014) PC2 T3 77 Chang (2013) PC1 T2 78 Abdul-Aziz (2012) PE2 T1 79 Kayaga & Zhe (2007) PE2 T4 80 Santosh Kumar Delhi et al. (2012) PE2 T4 81 Skander & Préfontaine (2014) PE2 T1 82 Perić (2012) PE2 T4 83 Amponsah & Forbes (2012) PC2 T4 84 Lilley (2005) PC1 T2 85 Zhang et al. (2016b) PC2 T5 86 Padalkar & Gopinath (2016) PC1 T4 87 Roberts & Siemiatycki (2015) PE2 T1 88 Lavlinskii et al. (2016) PC2 T4 89 Keck (1996) PE2 T4 90 Hughes (2005) PE2 T4 91 Pankratz & Walkenmeyer (2005) PC1 T4 92 Lenferink et al. (2014) PC2 T4 93 Chou & Leatemia (2016) PC2 T4 94 De Clerck & Demeulemeester (2016) PC2 T3 95 Loosemore & Cheung (2015) PE2 T2 96 Cheng et al. (2016) PE1 T4 97 Koops et al. (2016) PE1 T4 98 Liu, T., et al. (2016a) PE1 T4 99 Verweij (2015b) PC2 T1 .

Table 1
Codification scheme for articles classification.

For the third stage, we considered the 24 publications of highest impact factor as the sample for content analysis. The articles were analyzed for the development of two networks: Co-occurrence Keyword (The relationship between the items is determined based on the number of documents in which they occur together), Bibliographic sharing (The relationship between the items is determined based on the references they share). For the development of networks, it was used the software VOSviewer version 1.6.5; the database built for analysis was in CSV (Comma Separated Values) format in the export of Scopus. Finally, in order to understand the relevance of the articles to the dynamics of publications on the subject, an assessment of the evolution of the number of citations per article stratified per year was conducted.

Next, a content analysis was performed through the full text of the articles, in two phases: categorization and find connections. In this analysis, it was made a review of the project management constructs applied to the environment of public-private partnerships. Then, to answer the research questions are synthesise in a theoretical model the main challenges and techniques of project management and how these impact the success of projects in PPPs and how they fit into each stage of the project life cycle, from the moment that the state draws a project and decide that a partnership with the private sector will be beneficial to post-project implementation time.

4 Results

4.1 Sample caracterization

Considering the number of publications (Np), the number of citations (Nc) and the impact factor (Fi) described in Table 2, it was identified the “International Journal of Project Management” as the main vehicle for publication theme, featuring 57% of the publications, 70% of the citations and 86% of the sample impact factor considered, in addition to having the largest JCR sample (3.411). However, evaluating the number of citations and impact factor, it can be identified two other relevant vehicles: the “Construction Management and Economics”, with 6% of the publications, 11% of the citations and 3% of the impact factor - it’s relevance is due mainly to a specific publication: the article Zhang (2005)Zhang, X. (2005). Critical success factors for public–private partnerships in infrastructure development. Journal of Construction Engineering and Management, 131(1), 3-14. http://dx.doi.org/10.1061/(ASCE)0733-9364(2005)131:1(3).
http://dx.doi.org/10.1061/(ASCE)0733-936...
, with 7% of the citations and 2% of the sample impact factor. The second is the ”Journal of Construction Engineering and Management”, with 2% of the publications, 7% of the citations and 5% of the impact factor - in this case, the relevance is due mainly to the article Li et al. (2005a)Li, B., Akintoye, A., Edwards, P. J., & Hardcastle, C. (2005a). Critical success factors for PPP/PFI projects in the UK construction industry. Construction Management and Economics, 23(5), 459-471. http://dx.doi.org/10.1080/01446190500041537.
http://dx.doi.org/10.1080/01446190500041...
, that has 6% of the quote and 5% of the sample impact factor. Both articles are focused on critical success factors for PPPs. Because the search strategy, it could be expected a greater representation of the “International Journal of Project Management”. Comparing the results of this study with the results obtained by Tang et al.(2010)Tang, L., Shen, Q., & Cheng, E. W. (2010). A review of studies on public–private partnership projects in the construction industry. International Journal of Project Management, 28(7), 683-694. http://dx.doi.org/10.1016/j.ijproman.2009.11.009.
http://dx.doi.org/10.1016/j.ijproman.200...
, it can be seen that the first 4 pointed periodic coincide in both studies, despite this present study have included papers from 1994 to 2016 and focus on project management topic at PPP, while the study of Tang et al. (2010)Tang, L., Shen, Q., & Cheng, E. W. (2010). A review of studies on public–private partnership projects in the construction industry. International Journal of Project Management, 28(7), 683-694. http://dx.doi.org/10.1016/j.ijproman.2009.11.009.
http://dx.doi.org/10.1016/j.ijproman.200...
has articles from 1998 to 2007 and has a broader focus on PPP projects.

Table 2
Number of publications, citations and impact factor of the periodicals of the sample.

Evaluating the number of publications per journal per year according to the data shown in Table 3, we find that the first article related to PPP and Project Management was published in 1994 in the “International Journal of Project Management”. However, between 1994 and 2002 just four articles were published, in which these 3 were in “International Journal of Project Management”. In the period 2002 to 2006, it were published 18 articles, a number of approximately 3.6 times greater than the previous period, with approximately 56% of the period articles published in “International Journal of Project Management”. In the period between 2007 and 2011, it were published 24 articles, representing an increase of 33% over the previous period, with approximately 83% of the articles of the period published in the “International Journal of Project Management”. Finally, for the period between 2012 to 2016, it were published 52 articles, a number approximately 2.2 times greater than the previous period, with 29 articles published in “International Journal of Project Management” (approximately 56%). From these figures it can be concluded that the subject has been little explored between 1997 and 2001 (5% of publications), had a period of consistent publications between 2002 and 2011 (42% of posts) and in the last five years showed a large growth (53% of publications), showing that PPPs are a trend not only in the practical field, but are in high growth publications in the academic field as well. Throughout the period between 1994 to 2016, the “International Journal of Project Management” has emerged as the dissemination channel with the greater number of relevant publications on the subject, keeping rates of at least 56% of publications.

Table 3
Number of publications by periodical and year.

In the bibliographic coupling network (see Figure 2), the lines connecting the items that share references and the line width determines the intensity of this sharing. Thus, the temporal component influences the establishment of relations, as older articles have less reference share with other old ones, but with young ones (when they were already cited for further evidence) it can be identify three distinct groups of articles that share references at higher intensity. Group 1 showed greater focus on Project Management. In group 2, with an emphasis on risk management, it can be seen the greatest amount of relations in sample of articles, showing that there is a consolidated literature on risk management topic in PPPs. The strongest relationship occurs between Hwang et al. (2013)Hwang, B. G., Zhao, X., & Gay, M. J. S. (2013). Public private partnership projects in Singapore: Factors, critical risks and preferred risk allocation from the perspective of contractors. International Journal of Project Management, 31(3), 424-433. http://dx.doi.org/10.1016/j.ijproman.2012.08.003.
http://dx.doi.org/10.1016/j.ijproman.201...
(connections 7) and Ke et al. (2010a)Ke, Y., Wang, S., Chan, A. P., & Lam, P. T. (2010a). Preferred risk allocation in China’s public-private partnertship (PPP) projects. International Journal of Project Management, 28(5), 482-492. https://doi.org/10.1016/j.ijproman.2009.08.007.
https://doi.org/ https://doi.org/10.1016...
(6 connections) in the risk allocation context. Article Jin & Zhang (2011)Jin, X. H., & Zhang, G. (2011). Modelling optimal risk allocation in PPP projects using artificial neural networks. International Journal of Project Management, 29(5), 591-603. http://dx.doi.org/10.1016/j.ijproman.2010.07.011.
http://dx.doi.org/10.1016/j.ijproman.201...
(8 connections) focuses on risk allocation, while the article Shen et al. (2006)Shen, L. Y., Platten, A., & Deng, X. P. (2006). Role of public private partnerships to manage risks in public sector projects in Hong Kong. International Journal of Project Management, 24(7), 587-594. http://dx.doi.org/10.1016/j.ijproman.2006.07.006.
http://dx.doi.org/10.1016/j.ijproman.200...
focuses on the context of PPPs role for risk management in public sector projects. Group 3 is primarily critical success factors and stakeholder management, with a low share of references, indicating that these topics are still not consolidated. Finally, the article Tang et al. (2010)Tang, L., Shen, Q., & Cheng, E. W. (2010). A review of studies on public–private partnership projects in the construction industry. International Journal of Project Management, 28(7), 683-694. http://dx.doi.org/10.1016/j.ijproman.2009.11.009.
http://dx.doi.org/10.1016/j.ijproman.200...
(10 connections), been a review article in PPP project management in the construction industry, is the only item that connects all the groups and has a great intensity sharing with Ke et al. (2010a)Ke, Y., Wang, S., Chan, A. P., & Lam, P. T. (2010a). Preferred risk allocation in China’s public-private partnertship (PPP) projects. International Journal of Project Management, 28(5), 482-492. https://doi.org/10.1016/j.ijproman.2009.08.007.
https://doi.org/ https://doi.org/10.1016...
and Hwang et al. (2013)Hwang, B. G., Zhao, X., & Gay, M. J. S. (2013). Public private partnership projects in Singapore: Factors, critical risks and preferred risk allocation from the perspective of contractors. International Journal of Project Management, 31(3), 424-433. http://dx.doi.org/10.1016/j.ijproman.2012.08.003.
http://dx.doi.org/10.1016/j.ijproman.201...
.

Figure 2
Bibliographic Coupling Network.

4.2 Main themes

The bibliometric network analysis allows to evaluate trends in the topic. In the co occurrence network keywords shown in Figure 3, the lines connects the joints keywords cited in the sample and the line width demonstrates the strength of these relationships. To simplify the network, different synonyms for Public-Private Partnerships (Public-Private Partnerships) were edited to be represented by this spelling, as well as Private Finance Initiatives synonyms (Private Finance Initiatives) were edited to be represented by this spelling. The filter used for analysis was a minimum of three occurrences of each keyword, which resulted in a sample of 17 keywords that met the requirement and total 155 quotes. The three most often cited keywords were: Public-Private Partnerships (51 quotes), Project Management (18 quotes) and Risk Management (10 citations). In addition to stronger relationships between PPP and Project Management, it is worth noting the connections between PPP and Risk Allocation, PPPs and Initiative Private Financing, PPP and Critical Success Factors, as main focus of discussion at the intersection of these themes, and justifying also with these being the categories of classification of studies focuses, mentioned above (Relationship, Risk, Finance and Success Factors and Project).

Figure 3
Keyword co-occurrence network.

Table 4 shows the changes in trends of publications classified by the method and the focus of the study into four periods: Period 1: 1994-2001, Period 2: from 2002 to 2006, Period 3: 2007-2011 and Period 4: 2012-2016.

Table 4
Publications by period grouped according to the Method and Focus of the study.

Considering the focus of this study, about 47% of the studies are related to Project success factors (T4) which includes critical success factors for structuring PPPs and PPP projects, best practices and project management methodologies in PPPs. This topic has consistently been addressed since the first article in 1994, being the only topic to present growth trend among all periods. The second most discussed focus is Risk (T2), which includes best practices and methodologies for risk management, allocation and risk reducing in PPPs. Despite an upward trend between the first and second periods, the topic do not grow in publications between the second and third period, but resumed the growth trend between the third and fourth quarter, proving to be a relevant topic. The relationship of topics (T1) (including the understanding of the relationship between the public and private spheres, between the actors involved in PPPs and best practices and methodologies for management of relationships) and Finance (T3) (understanding of the financial dimension of PPP, financial modeling and studies on PPPs, study the concession periods, PPP pricing methods and best practices and methodologies for finance in PPPs) presents the greatest variation between the third and fourth periods, which features a strong growth trend in the topics and as potential areas for future studies.

As for the methodological studies, it can be seen a prevalence of empirical methods (67 posts) on conceptual methods (32 posts). Between empirical methods, the case study is the most used (42 publications), showing that issues related to the theme are still being explored in different contexts and dimensions. The consolidation of knowledge in PPPs and project management in PPPs is presented as a substantial challenge as regional and specific characteristics of each country and legislation, economic and political environment. Culture and behavior of the public and private sectors generate different specific challenges for each application. Moreover, the nature of PPP projects, to be “made once”, difficult to standardize approaches. However, some issues, such as risk allocation, have evolved through empirical studies such as surveys and have begun to be addressed in mathematical models for defining models generalizable.

The PPP project management theme can benefit even more by comprehensive and consistent literature review that seek to compare features in different contexts to the consolidation of an universal and generalizable knowledge on the subject. This method is the least used, but shows a strong growth trend between the fourth and fifth period, indicating an effort to consolidate the great empirical knowledge base generated.

5 Discussion

The purpose of this article is to contribute to theory by answering the three research questions set out in the introduction section. Combining the key issues of analysis regarding challenges, techniques and critical success factors, a conceptual framework oriented to the PPP project life cycle is proposed, as shown in Figure 4.

Figure 4
Conceptual framework based on literatura analysis.

The life cycle of a PPP project begins with the creation of the business case, where the public sector decides whether the PPP model provides better value for money (VfM) then developing properly (Clifton & Duffield, 2006Clifton, C., & Duffield, C. F. (2006). Improved PFI/PPP service outcomes through the integration of Alliance principles. International Journal of Project Management, 24(7), 573-586. http://dx.doi.org/10.1016/j.ijproman.2006.07.005.
http://dx.doi.org/10.1016/j.ijproman.200...
). Then it is sent a proposal to tenderers, which must carry out the declaration of interest. Soon after defining the interested parts, there is a bidding process to select a partner from the private sector able to meet the budget expectations, techniques and proven experience to the project, in which there is a negotiation with a final list of bidders to choose partner and signature of the contract (De Lemos et al., 2004De Lemos, T., Eaton, D., Betts, M., & de Almeida, L. T. (2004). Risk management in the Lusoponte concession: a case study of the two bridges in Lisbon, Portugal. International Journal of Project Management, 22(1), 63-73. http://dx.doi.org/10.1016/S0263-7863(03)00013-9.
http://dx.doi.org/10.1016/S0263-7863(03)...
). All the mentioned steps which happens begore the signing of contract will be treated from now as the phase pre-project of PPP.

On-project, the two parties (public and private sectors) organizes the project planning in more detail. At this stage the goals, conditions, milestones and project activities are discussed. With the validation of the two parties, the implementation of the project is made up until the finalization of the defined scope and evaluation of what has been built (Reijniers, 1994Reijniers, J. J. A. M. (1994). Organization of public-private partnership projects: the timely prevention of pitfalls. International Journal of Project Management, 12(3), 137-142. http://dx.doi.org/10.1016/0263-7863(94)90028-0.
http://dx.doi.org/10.1016/0263-7863(94)9...
).

After its conclusion, comes in a phase of post-project, where usually the private party carry out the operation of the project/system created until expiration or termination of the partnership contract (Clifton & Duffield, 2006Clifton, C., & Duffield, C. F. (2006). Improved PFI/PPP service outcomes through the integration of Alliance principles. International Journal of Project Management, 24(7), 573-586. http://dx.doi.org/10.1016/j.ijproman.2006.07.005.
http://dx.doi.org/10.1016/j.ijproman.200...
).

5.1 Challenges

As the first item in content analysis, Table 5 indicates the main challenges encountered in managing PPP projects.

Table 5
Challenges in Project Management of PPPs.

It is observed in Table 5, that literature emphasis more the challenges before or on-project (9), while less emphasis is given to the challenges of post-project phase (5).

In the analysis of the challenges in the pre-project phase, it is dominant issues on the PPP project risk management which, according to Grimsey & Lewis (2002)Grimsey, D., & Lewis, M. K. (2002). Evaluating the risks of public private partnerships for infrastructure projects. International Journal of Project Management, 20(2), 107-118. http://dx.doi.org/10.1016/S0263-7863(00)00040-5.
http://dx.doi.org/10.1016/S0263-7863(00)...
, is one of the major points of divergence between the different stakeholders participating on the project. There is also a concern in understanding the different interests and abilities of stakeholders and, as Bing et al. (2005)Bing, L., Akintoye, A., Edwards, P. J., & Hardcastle, C. (2005). The allocation of risk in PPP/PFI construction projects in the UK. International Journal of Project Management, 23(1), 25-35. http://dx.doi.org/10.1016/j.ijproman.2004.04.006.
http://dx.doi.org/10.1016/j.ijproman.200...
points out, metting the goals of the public sector by passing most of the risks to the private sector. Some publications (Bachy & Hameri, 1997Bachy, G., & Hameri, A. P. (1997). What to be implemented at the early stage of a large-scale project. International Journal of Project Management, 15(4), 211-218. http://dx.doi.org/10.1016/S0263-7863(96)00070-1.
http://dx.doi.org/10.1016/S0263-7863(96)...
; Bing et al., 2005Bing, L., Akintoye, A., Edwards, P. J., & Hardcastle, C. (2005). The allocation of risk in PPP/PFI construction projects in the UK. International Journal of Project Management, 23(1), 25-35. http://dx.doi.org/10.1016/j.ijproman.2004.04.006.
http://dx.doi.org/10.1016/j.ijproman.200...
; Shen et al., 2006Shen, L. Y., Platten, A., & Deng, X. P. (2006). Role of public private partnerships to manage risks in public sector projects in Hong Kong. International Journal of Project Management, 24(7), 587-594. http://dx.doi.org/10.1016/j.ijproman.2006.07.006.
http://dx.doi.org/10.1016/j.ijproman.200...
; Ke et al., 2010aKe, Y., Wang, S., Chan, A. P., & Lam, P. T. (2010a). Preferred risk allocation in China’s public-private partnertship (PPP) projects. International Journal of Project Management, 28(5), 482-492. https://doi.org/10.1016/j.ijproman.2009.08.007.
https://doi.org/ https://doi.org/10.1016...
; Hwang et al., 2013Hwang, B. G., Zhao, X., & Gay, M. J. S. (2013). Public private partnership projects in Singapore: Factors, critical risks and preferred risk allocation from the perspective of contractors. International Journal of Project Management, 31(3), 424-433. http://dx.doi.org/10.1016/j.ijproman.2012.08.003.
http://dx.doi.org/10.1016/j.ijproman.201...
), study specifically the creation of models to facilitate the allocation of risk between public and private, using different forms of classification of items contained in the project risks while Medda (2007)Medda, F. (2007). A game theory approach for the allocation of risks in transport public private partnerships. International Journal of Project Management, 25(3), 213-218. http://dx.doi.org/10.1016/j.ijproman.2006.06.003.
http://dx.doi.org/10.1016/j.ijproman.200...
points possible moral problems in the form of division of these items and other studies (Reijniers, 1994Reijniers, J. J. A. M. (1994). Organization of public-private partnership projects: the timely prevention of pitfalls. International Journal of Project Management, 12(3), 137-142. http://dx.doi.org/10.1016/0263-7863(94)90028-0.
http://dx.doi.org/10.1016/0263-7863(94)9...
; Jin & Zhang, 2011Jin, X. H., & Zhang, G. (2011). Modelling optimal risk allocation in PPP projects using artificial neural networks. International Journal of Project Management, 29(5), 591-603. http://dx.doi.org/10.1016/j.ijproman.2010.07.011.
http://dx.doi.org/10.1016/j.ijproman.201...
; Flyvbjerg, 2013Flyvbjerg, B. (2013). Quality control and due diligence in project management: getting decisions right by taking the outside view. International Journal of Project Management, 31(5), 760-774. http://dx.doi.org/10.1016/j.ijproman.2012.10.007.
http://dx.doi.org/10.1016/j.ijproman.201...
) identify flaws in the assessment of the risks involved. Finally, another popular challenge pointed, both in the literature review of Tang et al. (2010)Tang, L., Shen, Q., & Cheng, E. W. (2010). A review of studies on public–private partnership projects in the construction industry. International Journal of Project Management, 28(7), 683-694. http://dx.doi.org/10.1016/j.ijproman.2009.11.009.
http://dx.doi.org/10.1016/j.ijproman.200...
and other studies (Yeo & Tiong, 2000Yeo, K. T., & Tiong, R. L. (2000). Positive management of differences for risk reduction in BOT projects. International Journal of Project Management, 18(4), 257-265. http://dx.doi.org/10.1016/S0263-7863(99)00018-6.
http://dx.doi.org/10.1016/S0263-7863(99)...
; Kumaraswamy & Zhang, 2001Kumaraswamy, M. M., & Zhang, X. Q. (2001). Governmental role in BOT-led infrastructure development. International Journal of Project Management, 19(4), 195-205. http://dx.doi.org/10.1016/S0263-7863(99)00069-1.
http://dx.doi.org/10.1016/S0263-7863(99)...
; De Lemos et al., 2004De Lemos, T., Eaton, D., Betts, M., & de Almeida, L. T. (2004). Risk management in the Lusoponte concession: a case study of the two bridges in Lisbon, Portugal. International Journal of Project Management, 22(1), 63-73. http://dx.doi.org/10.1016/S0263-7863(03)00013-9.
http://dx.doi.org/10.1016/S0263-7863(03)...
), is the challenge of maintaining a political and national economic environment that encourages large private investments in conjunction with the public sector.

on-project, the main challenges are the financial factors involved, and Yeo & Tiong (2000)Yeo, K. T., & Tiong, R. L. (2000). Positive management of differences for risk reduction in BOT projects. International Journal of Project Management, 18(4), 257-265. http://dx.doi.org/10.1016/S0263-7863(99)00018-6.
http://dx.doi.org/10.1016/S0263-7863(99)...
raises the challenge of maintaining the funds involved in the project's long-term and Flyvbjerg (2013)Flyvbjerg, B. (2013). Quality control and due diligence in project management: getting decisions right by taking the outside view. International Journal of Project Management, 31(5), 760-774. http://dx.doi.org/10.1016/j.ijproman.2012.10.007.
http://dx.doi.org/10.1016/j.ijproman.201...
raises the attentionfor wrong estimates to support the long-term planning, which may result in cancellation of the project by not metting the budget. From the point of view of challenges in project planning and design, some studies (Bachy & Hameri, 1997Bachy, G., & Hameri, A. P. (1997). What to be implemented at the early stage of a large-scale project. International Journal of Project Management, 15(4), 211-218. http://dx.doi.org/10.1016/S0263-7863(96)00070-1.
http://dx.doi.org/10.1016/S0263-7863(96)...
; De Lemos et al., 2004De Lemos, T., Eaton, D., Betts, M., & de Almeida, L. T. (2004). Risk management in the Lusoponte concession: a case study of the two bridges in Lisbon, Portugal. International Journal of Project Management, 22(1), 63-73. http://dx.doi.org/10.1016/S0263-7863(03)00013-9.
http://dx.doi.org/10.1016/S0263-7863(03)...
) show cases that demonstrate the negative and tragic consequences of ill done plans. Phase “on-project” is also marked by great challenges in maintaining and developing a good relationship between public and private organizations. Besides Reijniers (1994)Reijniers, J. J. A. M. (1994). Organization of public-private partnership projects: the timely prevention of pitfalls. International Journal of Project Management, 12(3), 137-142. http://dx.doi.org/10.1016/0263-7863(94)90028-0.
http://dx.doi.org/10.1016/0263-7863(94)9...
points out that organizational cultures are very different, which brings challenges to mutual understanding, and also, along with Tang et al. (2010)Tang, L., Shen, Q., & Cheng, E. W. (2010). A review of studies on public–private partnership projects in the construction industry. International Journal of Project Management, 28(7), 683-694. http://dx.doi.org/10.1016/j.ijproman.2009.11.009.
http://dx.doi.org/10.1016/j.ijproman.200...
and Smyth & Edkins (2007)Smyth, H., & Edkins, A. (2007). Relationship management in the management of PFI/PPP projects in the UK. International Journal of Project Management, 25(3), 232-240. http://dx.doi.org/10.1016/j.ijproman.2006.08.003.
http://dx.doi.org/10.1016/j.ijproman.200...
, states that the level of relationship and exchange of feedback between the organizations is very low. Finally, other references (Yeo & Tiong, 2000Yeo, K. T., & Tiong, R. L. (2000). Positive management of differences for risk reduction in BOT projects. International Journal of Project Management, 18(4), 257-265. http://dx.doi.org/10.1016/S0263-7863(99)00018-6.
http://dx.doi.org/10.1016/S0263-7863(99)...
; Li et al., 2005aLi, B., Akintoye, A., Edwards, P. J., & Hardcastle, C. (2005a). Critical success factors for PPP/PFI projects in the UK construction industry. Construction Management and Economics, 23(5), 459-471. http://dx.doi.org/10.1080/01446190500041537.
http://dx.doi.org/10.1080/01446190500041...
) point out the difficulties in managing the internal culture environment of the project team, composed of professionals from these different cultures together.

In the post-project phase, despite being the result of actions taken (or not taken) in the previous phases of the project, the post-project phase is when the team is faced with challenges of evaluating the project results, and various studies (Reijniers,1994Reijniers, J. J. A. M. (1994). Organization of public-private partnership projects: the timely prevention of pitfalls. International Journal of Project Management, 12(3), 137-142. http://dx.doi.org/10.1016/0263-7863(94)90028-0.
http://dx.doi.org/10.1016/0263-7863(94)9...
; Yeo & Tiong 2000Yeo, K. T., & Tiong, R. L. (2000). Positive management of differences for risk reduction in BOT projects. International Journal of Project Management, 18(4), 257-265. http://dx.doi.org/10.1016/S0263-7863(99)00018-6.
http://dx.doi.org/10.1016/S0263-7863(99)...
; Van Marrewijk et al., 2008Van Marrewijk, A., Clegg, S. R., Pitsis, T. S., & Veenswijk, M. (2008). Managing public–private megaprojects: Paradoxes, complexity, and project design. International Journal of Project Management, 26(6), 591-600. http://dx.doi.org/10.1016/j.ijproman.2007.09.007.
http://dx.doi.org/10.1016/j.ijproman.200...
; Flyvbjerg, 2013Flyvbjerg, B. (2013). Quality control and due diligence in project management: getting decisions right by taking the outside view. International Journal of Project Management, 31(5), 760-774. http://dx.doi.org/10.1016/j.ijproman.2012.10.007.
http://dx.doi.org/10.1016/j.ijproman.201...
) mention outcomes generally far worse than expected in the planning phase in PPP projects. Kumaraswamy & Zhang (2001)Kumaraswamy, M. M., & Zhang, X. Q. (2001). Governmental role in BOT-led infrastructure development. International Journal of Project Management, 19(4), 195-205. http://dx.doi.org/10.1016/S0263-7863(99)00069-1.
http://dx.doi.org/10.1016/S0263-7863(99)...
identify difficulties regarding the approval of public opinion, while Toor & Ogunlana (2010)Toor, S.-R., & Ogunlana, S. O. (2010). Beyond the ‘iron triangle’: stakeholder perception of key performance indicators (KPIs) for large-scale public sector development projects. International Journal of Project Management, 28(3), 228-236. http://dx.doi.org/10.1016/j.ijproman.2009.05.005.
http://dx.doi.org/10.1016/j.ijproman.200...
raises an important discussion on how to evaluate success in PPP projects. Finally, Yeo & Tiong (2000)Yeo, K. T., & Tiong, R. L. (2000). Positive management of differences for risk reduction in BOT projects. International Journal of Project Management, 18(4), 257-265. http://dx.doi.org/10.1016/S0263-7863(99)00018-6.
http://dx.doi.org/10.1016/S0263-7863(99)...
indicate that defining the rates for the end user later on is a major problem of this phase, which ends up generating disagreement and dissatisfaction.

5.2 Techniques

The main techniques to overcome or mitigate some of the challenges raised are systematized in Table 6. It is observed that there is greater emphasis on techniques to the stage on-project (16), while the post-project phase, received little attention (2).

Table 6
Techniques to increase success in PPPs.

In the pre-project phase, Bing et al (2005)Bing, L., Akintoye, A., Edwards, P. J., & Hardcastle, C. (2005). The allocation of risk in PPP/PFI construction projects in the UK. International Journal of Project Management, 23(1), 25-35. http://dx.doi.org/10.1016/j.ijproman.2004.04.006.
http://dx.doi.org/10.1016/j.ijproman.200...
and several other studies (Grimsey & Lewis, 2002Grimsey, D., & Lewis, M. K. (2002). Evaluating the risks of public private partnerships for infrastructure projects. International Journal of Project Management, 20(2), 107-118. http://dx.doi.org/10.1016/S0263-7863(00)00040-5.
http://dx.doi.org/10.1016/S0263-7863(00)...
; Shen et al., 2006Shen, L. Y., Platten, A., & Deng, X. P. (2006). Role of public private partnerships to manage risks in public sector projects in Hong Kong. International Journal of Project Management, 24(7), 587-594. http://dx.doi.org/10.1016/j.ijproman.2006.07.006.
http://dx.doi.org/10.1016/j.ijproman.200...
; Ke et al., 2010bKe, Y., Wang, S., & Chan, A. P. (2010b). Risk allocation in public-private partnership infrastructure projects: comparative study. Journal of Infrastructure Systems, 16(4), 343-351. http://dx.doi.org/10.1061/(ASCE)IS.1943-555X.0000030.
http://dx.doi.org/10.1061/(ASCE)IS.1943-...
) focus on systematizing, allocation suggestions of joint ventures in PPP projects between the public and private sectors, from surveys to understand the preferences of project managers and analysis of case studies. Clifton & Duffield (2006)Clifton, C., & Duffield, C. F. (2006). Improved PFI/PPP service outcomes through the integration of Alliance principles. International Journal of Project Management, 24(7), 573-586. http://dx.doi.org/10.1016/j.ijproman.2006.07.005.
http://dx.doi.org/10.1016/j.ijproman.200...
and Zhang (2007)Zhang, H. (2007). A redefinition of the project risk process: using vulnerability to open up the event-consequence link. International Journal of Project Management, 25(7), 694-701. http://dx.doi.org/10.1016/j.ijproman.2007.02.004.
http://dx.doi.org/10.1016/j.ijproman.200...
suggest tools for reducing unforeseen events in the project by offering other forms of risk analysis or inclusion of project vulnerability analysis tools. Finally, Kumaraswamy & Zhang (2001)Kumaraswamy, M. M., & Zhang, X. Q. (2001). Governmental role in BOT-led infrastructure development. International Journal of Project Management, 19(4), 195-205. http://dx.doi.org/10.1016/S0263-7863(99)00069-1.
http://dx.doi.org/10.1016/S0263-7863(99)...
also shows ways of selecting of private sector bidders for the project.

On stage “on-project”, to avoid big unexpected events in the project, Flyvbjerg (2013)Flyvbjerg, B. (2013). Quality control and due diligence in project management: getting decisions right by taking the outside view. International Journal of Project Management, 31(5), 760-774. http://dx.doi.org/10.1016/j.ijproman.2012.10.007.
http://dx.doi.org/10.1016/j.ijproman.201...
proposes both an external review to assess the estimates used in the planning as a method to reward and punish good and bad estimates, while Kumaraswamy & Zhang (2001)Kumaraswamy, M. M., & Zhang, X. Q. (2001). Governmental role in BOT-led infrastructure development. International Journal of Project Management, 19(4), 195-205. http://dx.doi.org/10.1016/S0263-7863(99)00069-1.
http://dx.doi.org/10.1016/S0263-7863(99)...
care to propose frameworks and regulatory frameworks to minimize the effect of unforeseen arising from political and national economic environment. Several studies (Li et al., 2005aLi, B., Akintoye, A., Edwards, P. J., & Hardcastle, C. (2005a). Critical success factors for PPP/PFI projects in the UK construction industry. Construction Management and Economics, 23(5), 459-471. http://dx.doi.org/10.1080/01446190500041537.
http://dx.doi.org/10.1080/01446190500041...
; El-Gohary et al., 2006El-Gohary, N. M., Osman, H., & El-Diraby, T. E. (2006). Stakeholder management for public private partnerships. International Journal of Project Management, 24(7), 595-604. http://dx.doi.org/10.1016/j.ijproman.2006.07.009.
http://dx.doi.org/10.1016/j.ijproman.200...
; Smyth & Edkins, 2007Smyth, H., & Edkins, A. (2007). Relationship management in the management of PFI/PPP projects in the UK. International Journal of Project Management, 25(3), 232-240. http://dx.doi.org/10.1016/j.ijproman.2006.08.003.
http://dx.doi.org/10.1016/j.ijproman.200...
; Tang et al., 2010Tang, L., Shen, Q., & Cheng, E. W. (2010). A review of studies on public–private partnership projects in the construction industry. International Journal of Project Management, 28(7), 683-694. http://dx.doi.org/10.1016/j.ijproman.2009.11.009.
http://dx.doi.org/10.1016/j.ijproman.200...
; Yeo & Tiong, 2000Yeo, K. T., & Tiong, R. L. (2000). Positive management of differences for risk reduction in BOT projects. International Journal of Project Management, 18(4), 257-265. http://dx.doi.org/10.1016/S0263-7863(99)00018-6.
http://dx.doi.org/10.1016/S0263-7863(99)...
) proposes tools to improve the efficiency in relationshipbetween organizations, as increased traffic information between the players, techniques of Relationship Management or concerns to establish a win-win relationship. Other studies Reijniers (1994)Reijniers, J. J. A. M. (1994). Organization of public-private partnership projects: the timely prevention of pitfalls. International Journal of Project Management, 12(3), 137-142. http://dx.doi.org/10.1016/0263-7863(94)90028-0.
http://dx.doi.org/10.1016/0263-7863(94)9...
and Kumaraswamy & Zhang (2001)Kumaraswamy, M. M., & Zhang, X. Q. (2001). Governmental role in BOT-led infrastructure development. International Journal of Project Management, 19(4), 195-205. http://dx.doi.org/10.1016/S0263-7863(99)00069-1.
http://dx.doi.org/10.1016/S0263-7863(99)...
, draw attention to forms of continuous evaluation of the project to monitor its progress.

Finally, in the post-project phase, the literature shows few tools for post-project PPP phase. Kumaraswamy & Zhang (2001)Kumaraswamy, M. M., & Zhang, X. Q. (2001). Governmental role in BOT-led infrastructure development. International Journal of Project Management, 19(4), 195-205. http://dx.doi.org/10.1016/S0263-7863(99)00069-1.
http://dx.doi.org/10.1016/S0263-7863(99)...
point out the need to set billing mechanisms to the private partner, which does not harm the profitability of the operation, while Toor & Ogunlana (2010)Toor, S.-R., & Ogunlana, S. O. (2010). Beyond the ‘iron triangle’: stakeholder perception of key performance indicators (KPIs) for large-scale public sector development projects. International Journal of Project Management, 28(3), 228-236. http://dx.doi.org/10.1016/j.ijproman.2009.05.005.
http://dx.doi.org/10.1016/j.ijproman.200...
is mentioned to present ways to evaluate the success of PPP projects more broadly than the classic triad assessment of “budget, time and scope”.

5.3 Critical Success Factors of PM in PPP

Similarly to the previous sections this content analysis extracts from articles the critical success factors (CSF) of PM in PPP projects. CSF are separated at each stage of the project and summarized in Table 7.

Table 7
Critical Success Factors in PPPs.

The CSF of the pre-project phase highlights risk management, which plays an important role in the partnership between the public and private sectors. In this sense, Grimsey & Lewis (2002)Grimsey, D., & Lewis, M. K. (2002). Evaluating the risks of public private partnerships for infrastructure projects. International Journal of Project Management, 20(2), 107-118. http://dx.doi.org/10.1016/S0263-7863(00)00040-5.
http://dx.doi.org/10.1016/S0263-7863(00)...
stated that the different needs of each of the parties need to be satisfied in the risk allocation process. Similarly, Bing et al. (2005)Bing, L., Akintoye, A., Edwards, P. J., & Hardcastle, C. (2005). The allocation of risk in PPP/PFI construction projects in the UK. International Journal of Project Management, 23(1), 25-35. http://dx.doi.org/10.1016/j.ijproman.2004.04.006.
http://dx.doi.org/10.1016/j.ijproman.200...
suggest that the two parties need to reach a mutual agreement in allocating acceptable risks to both parties before signing the contract. This subject of the importance of allocating appropriate risk early in the project is also raised in other studies (Reijniers, 1994Reijniers, J. J. A. M. (1994). Organization of public-private partnership projects: the timely prevention of pitfalls. International Journal of Project Management, 12(3), 137-142. http://dx.doi.org/10.1016/0263-7863(94)90028-0.
http://dx.doi.org/10.1016/0263-7863(94)9...
; De Lemos et al., 2004De Lemos, T., Eaton, D., Betts, M., & de Almeida, L. T. (2004). Risk management in the Lusoponte concession: a case study of the two bridges in Lisbon, Portugal. International Journal of Project Management, 22(1), 63-73. http://dx.doi.org/10.1016/S0263-7863(03)00013-9.
http://dx.doi.org/10.1016/S0263-7863(03)...
; Shen et al., 2006Shen, L. Y., Platten, A., & Deng, X. P. (2006). Role of public private partnerships to manage risks in public sector projects in Hong Kong. International Journal of Project Management, 24(7), 587-594. http://dx.doi.org/10.1016/j.ijproman.2006.07.006.
http://dx.doi.org/10.1016/j.ijproman.200...
; Ke et al., 2010aKe, Y., Wang, S., Chan, A. P., & Lam, P. T. (2010a). Preferred risk allocation in China’s public-private partnertship (PPP) projects. International Journal of Project Management, 28(5), 482-492. https://doi.org/10.1016/j.ijproman.2009.08.007.
https://doi.org/ https://doi.org/10.1016...
; Jin & Zhang, 2011Jin, X. H., & Zhang, G. (2011). Modelling optimal risk allocation in PPP projects using artificial neural networks. International Journal of Project Management, 29(5), 591-603. http://dx.doi.org/10.1016/j.ijproman.2010.07.011.
http://dx.doi.org/10.1016/j.ijproman.201...
). Kumaraswamy & Zhang (2001)Kumaraswamy, M. M., & Zhang, X. Q. (2001). Governmental role in BOT-led infrastructure development. International Journal of Project Management, 19(4), 195-205. http://dx.doi.org/10.1016/S0263-7863(99)00069-1.
http://dx.doi.org/10.1016/S0263-7863(99)...
indicate that another critical factor for the project's success is to create a well structured process of evaluating the bidders to ensure the best supplier, even at this point, the process should carry out an auditon to ensure control over the estimates by each of the proponents (Bachy & Hameri, 1997Bachy, G., & Hameri, A. P. (1997). What to be implemented at the early stage of a large-scale project. International Journal of Project Management, 15(4), 211-218. http://dx.doi.org/10.1016/S0263-7863(96)00070-1.
http://dx.doi.org/10.1016/S0263-7863(96)...
; Flyvbjerg, 2013Flyvbjerg, B. (2013). Quality control and due diligence in project management: getting decisions right by taking the outside view. International Journal of Project Management, 31(5), 760-774. http://dx.doi.org/10.1016/j.ijproman.2012.10.007.
http://dx.doi.org/10.1016/j.ijproman.201...
). In Tang et al. (2010)Tang, L., Shen, Q., & Cheng, E. W. (2010). A review of studies on public–private partnership projects in the construction industry. International Journal of Project Management, 28(7), 683-694. http://dx.doi.org/10.1016/j.ijproman.2009.11.009.
http://dx.doi.org/10.1016/j.ijproman.200...
, Zhang (2005)Zhang, X. (2005). Critical success factors for public–private partnerships in infrastructure development. Journal of Construction Engineering and Management, 131(1), 3-14. http://dx.doi.org/10.1061/(ASCE)0733-9364(2005)131:1(3).
http://dx.doi.org/10.1061/(ASCE)0733-936...
is also used as a reference for survey of project's CSF in PPP, for the pre-project stage were cited: favorable environment for investment, economic feasibility, reliable partnership with strong technical competence, solid financial package, appropriate allocation of risk with reliable contractual arrangements (Tang et al., 2010Tang, L., Shen, Q., & Cheng, E. W. (2010). A review of studies on public–private partnership projects in the construction industry. International Journal of Project Management, 28(7), 683-694. http://dx.doi.org/10.1016/j.ijproman.2009.11.009.
http://dx.doi.org/10.1016/j.ijproman.200...
). This last question of the need for a contract with well defined scope and avoid rework later is also a success factor evidenced in (Reijniers, 1994Reijniers, J. J. A. M. (1994). Organization of public-private partnership projects: the timely prevention of pitfalls. International Journal of Project Management, 12(3), 137-142. http://dx.doi.org/10.1016/0263-7863(94)90028-0.
http://dx.doi.org/10.1016/0263-7863(94)9...
; De Lemos et al, 2004De Lemos, T., Eaton, D., Betts, M., & de Almeida, L. T. (2004). Risk management in the Lusoponte concession: a case study of the two bridges in Lisbon, Portugal. International Journal of Project Management, 22(1), 63-73. http://dx.doi.org/10.1016/S0263-7863(03)00013-9.
http://dx.doi.org/10.1016/S0263-7863(03)...
). For construction projects, especially the careful choice of where the project will be developed, has an important role in the outcome of the project as a whole, according to Yeo & Tiong (2000)Yeo, K. T., & Tiong, R. L. (2000). Positive management of differences for risk reduction in BOT projects. International Journal of Project Management, 18(4), 257-265. http://dx.doi.org/10.1016/S0263-7863(99)00018-6.
http://dx.doi.org/10.1016/S0263-7863(99)...
. As in Tang et al. (2010)Tang, L., Shen, Q., & Cheng, E. W. (2010). A review of studies on public–private partnership projects in the construction industry. International Journal of Project Management, 28(7), 683-694. http://dx.doi.org/10.1016/j.ijproman.2009.11.009.
http://dx.doi.org/10.1016/j.ijproman.200...
, the same authors point to the need to create a favorable investment environment where rates of return are attractive to the private sector and consequently the balancing of the interests of stakeholders of the project (Yeo & Tiong 2000Yeo, K. T., & Tiong, R. L. (2000). Positive management of differences for risk reduction in BOT projects. International Journal of Project Management, 18(4), 257-265. http://dx.doi.org/10.1016/S0263-7863(99)00018-6.
http://dx.doi.org/10.1016/S0263-7863(99)...
).

CSF on-project, particularly at the planning stage and construction of the project, an important point raised in literature is stakeholder management. In this regard it is crucial for the project to get involved local stakeholders throughout the entire project so that they feel that their interests are being contemplated (El-Gohary et al.,2006El-Gohary, N. M., Osman, H., & El-Diraby, T. E. (2006). Stakeholder management for public private partnerships. International Journal of Project Management, 24(7), 595-604. http://dx.doi.org/10.1016/j.ijproman.2006.07.009.
http://dx.doi.org/10.1016/j.ijproman.200...
). This continuous involvement of stakeholders in the project is also addressed by other studies of the sample (Reijniers, 1994Reijniers, J. J. A. M. (1994). Organization of public-private partnership projects: the timely prevention of pitfalls. International Journal of Project Management, 12(3), 137-142. http://dx.doi.org/10.1016/0263-7863(94)90028-0.
http://dx.doi.org/10.1016/0263-7863(94)9...
; Bachy & Hameri, 1997Bachy, G., & Hameri, A. P. (1997). What to be implemented at the early stage of a large-scale project. International Journal of Project Management, 15(4), 211-218. http://dx.doi.org/10.1016/S0263-7863(96)00070-1.
http://dx.doi.org/10.1016/S0263-7863(96)...
; Kumaraswamy & Zhang, 2001Kumaraswamy, M. M., & Zhang, X. Q. (2001). Governmental role in BOT-led infrastructure development. International Journal of Project Management, 19(4), 195-205. http://dx.doi.org/10.1016/S0263-7863(99)00069-1.
http://dx.doi.org/10.1016/S0263-7863(99)...
). Another subject that is important in this relationship between stakeholders is the trust between the parties, that when established, promote win-win results on-project (Smyth & Edkins, 2007Smyth, H., & Edkins, A. (2007). Relationship management in the management of PFI/PPP projects in the UK. International Journal of Project Management, 25(3), 232-240. http://dx.doi.org/10.1016/j.ijproman.2006.08.003.
http://dx.doi.org/10.1016/j.ijproman.200...
). Another aspect also commented as a critical success factor for the PPP projects is the management of its internal culture. When the internal culture of the team is aligned with the project's external expectations there is a tendency for greater cooperation between the parties, to achieve the project objectives (Van Marrewijk, 2007Van Marrewijk, A. (2007). Managing project culture: the case of Environ Megaproject. International Journal of Project Management, 25(3), 290-299. http://dx.doi.org/10.1016/j.ijproman.2006.11.004.
http://dx.doi.org/10.1016/j.ijproman.200...
; Van Marrewijk et al, 2008Van Marrewijk, A., Clegg, S. R., Pitsis, T. S., & Veenswijk, M. (2008). Managing public–private megaprojects: Paradoxes, complexity, and project design. International Journal of Project Management, 26(6), 591-600. http://dx.doi.org/10.1016/j.ijproman.2007.09.007.
http://dx.doi.org/10.1016/j.ijproman.200...
). The planning stage as a whole is regarded as critical to the project by some authors (Reijniers, 1994Reijniers, J. J. A. M. (1994). Organization of public-private partnership projects: the timely prevention of pitfalls. International Journal of Project Management, 12(3), 137-142. http://dx.doi.org/10.1016/0263-7863(94)90028-0.
http://dx.doi.org/10.1016/0263-7863(94)9...
; Clifton & Duffield, 2006Clifton, C., & Duffield, C. F. (2006). Improved PFI/PPP service outcomes through the integration of Alliance principles. International Journal of Project Management, 24(7), 573-586. http://dx.doi.org/10.1016/j.ijproman.2006.07.005.
http://dx.doi.org/10.1016/j.ijproman.200...
) as well as quality management especially at the beginning of the project (Flyvbjerg, 2013Flyvbjerg, B. (2013). Quality control and due diligence in project management: getting decisions right by taking the outside view. International Journal of Project Management, 31(5), 760-774. http://dx.doi.org/10.1016/j.ijproman.2012.10.007.
http://dx.doi.org/10.1016/j.ijproman.201...
). Similarly to other projects in other contexts, achieving budgets, deadlines and requirements are still the most critical success factors for PPP projects. In addition, metrics such as safety, efficiency of resource use and effectiveness (doing the right thing) are highly relevant to the perceived success of the project by the stakeholders (Toor & Ogunlana, 2010Toor, S.-R., & Ogunlana, S. O. (2010). Beyond the ‘iron triangle’: stakeholder perception of key performance indicators (KPIs) for large-scale public sector development projects. International Journal of Project Management, 28(3), 228-236. http://dx.doi.org/10.1016/j.ijproman.2009.05.005.
http://dx.doi.org/10.1016/j.ijproman.200...
). Reijniers (1994)Reijniers, J. J. A. M. (1994). Organization of public-private partnership projects: the timely prevention of pitfalls. International Journal of Project Management, 12(3), 137-142. http://dx.doi.org/10.1016/0263-7863(94)90028-0.
http://dx.doi.org/10.1016/0263-7863(94)9...
allude to other success factors as the creation of metrics, clear goals and outcomes to guide the project team, which in turn must be independent, qualified, working with proven techniques and methods on the market (Yeo & Tiong, 2000Yeo, K. T., & Tiong, R. L. (2000). Positive management of differences for risk reduction in BOT projects. International Journal of Project Management, 18(4), 257-265. http://dx.doi.org/10.1016/S0263-7863(99)00018-6.
http://dx.doi.org/10.1016/S0263-7863(99)...
) and report to the managers of the two sectors, and managers must constantly monitor the work on the proposed metrics and results. During the whole project, the entrepreneurial character of the private sector should also be encouraged to foster better outcomes for the project (Yeo & Tiong 2000Yeo, K. T., & Tiong, R. L. (2000). Positive management of differences for risk reduction in BOT projects. International Journal of Project Management, 18(4), 257-265. http://dx.doi.org/10.1016/S0263-7863(99)00018-6.
http://dx.doi.org/10.1016/S0263-7863(99)...
; Flyvbjerg, 2013Flyvbjerg, B. (2013). Quality control and due diligence in project management: getting decisions right by taking the outside view. International Journal of Project Management, 31(5), 760-774. http://dx.doi.org/10.1016/j.ijproman.2012.10.007.
http://dx.doi.org/10.1016/j.ijproman.201...
).

Some critical success factors raised above also have impacts on post-project. The continued involvement of the stakeholders in the project is one of these examples. El-Gohary et al. (2006)El-Gohary, N. M., Osman, H., & El-Diraby, T. E. (2006). Stakeholder management for public private partnerships. International Journal of Project Management, 24(7), 595-604. http://dx.doi.org/10.1016/j.ijproman.2006.07.009.
http://dx.doi.org/10.1016/j.ijproman.200...
states that global stakeholders have a greater concern for project monitoring to ensure that project impacts are still within the estimated during the planning phase, it is a feature that persists until the end of the contract, which is of great importance especially for the private sector, which tends to take greater risks on-project as a whole (Clifton & Duffield, 2006Clifton, C., & Duffield, C. F. (2006). Improved PFI/PPP service outcomes through the integration of Alliance principles. International Journal of Project Management, 24(7), 573-586. http://dx.doi.org/10.1016/j.ijproman.2006.07.005.
http://dx.doi.org/10.1016/j.ijproman.200...
).

The findings on critical success factors of this research corroborate the study of Osei-Kyei & Chan (2015)Osei-Kyei, R., & Chan, A. P. (2015). Review of studies on the Critical Success Factors for Public–Private Partnership (PPP) projects from 1990 to 2013. International Journal of Project Management, 33(6), 1335-1346. http://dx.doi.org/10.1016/j.ijproman.2015.02.008.
http://dx.doi.org/10.1016/j.ijproman.201...
, which in turn worked just these issues of CSF in PPP projects. Analyzing the studies of Osei-Kyei & Chan (2015)Osei-Kyei, R., & Chan, A. P. (2015). Review of studies on the Critical Success Factors for Public–Private Partnership (PPP) projects from 1990 to 2013. International Journal of Project Management, 33(6), 1335-1346. http://dx.doi.org/10.1016/j.ijproman.2015.02.008.
http://dx.doi.org/10.1016/j.ijproman.201...
and Liu, T., et al. (2016a), it is clear that risk management, allocation and appropriate sharing of risk, reliable consortium beneficial legal agreements the two sides, clear project scope definition, as well as a management, stakeholder proper choice of supplier process procurement, transparent and competitive commitment and continuous monitoring in the project by both parties, trust between them and clear definition of responsibilities between the two sectors are the most important aspects to be considered for PM in PM this project template. The studies are complementary, so that in Osei- yei & Chan (2015), highlight the environmental conditions and skills of the parties as CSF at various points like - political and community support for the project, stable economy, financial capacity of the private sector and guarantees provided by the public sector, long-term demand for the project and political stability - whereas the present study complements the first work with factors linked to culture and attention to the iron triangle (scope / quality, cost and time) as important for these projects: design project culture, the internal culture of the team alignment, using proven techniques and methods on the market to meet budget, schedule, quality and safety within the specified requirements.

The projects developed in the public private partnership model presents a rich field of study for project management, as usually involve contexts of large projects and high complexity, where there are multiple stakeholders (public, private, community, etc.) and often the project period with its concesion can reach decades, thus requiring procurement processes and complex contractual definitions. This environment covers in depth risk management, stakeholder management as well as addresses competition themes, competence, monitoring, sustainability, among others. Thus the process of systematization of the challenges, techniques and critical success factors for project management in PPP is complex as it needs to capture knowledge of specific project contexts in different areas and produced in different countries and environments.

Our findings show that most of the challenges, techniques and project success factors identified in the literature are concentrated mainly in the previous steps to contract signing. The perceptions found in this systematic literature review are consistent with the study by Liu, T., et al. (2016a), except for the issues intrinsic to the public sector such as, government powers and governance of their structures that permeate all stages of the project, all other factors are related to previous activities that take place before the project starts, they are the factors related to the creation of a business case, building a a suitable briefing for the project to third parties and the factors linked to competition between the private sector for competitive and transparent processes. Unlike the usual project management we found great occurrences of points of attention not only in the planning stage, but also during the implementation of this, which points out that the management of stakeholders in this project model has a particular aspect.

Table 8 shows a distribution of references to Critical Success Factors, Challenges and Techniques, grouped by project phase.

Table 8
Number of publications grouped by topic and project phase.

Another important insight of the literature review is that the challenges, techniques and critical success factors, are often heavily influenced by the context and environment variables where the project is located, as different studies point to different points of attention. In this way, the practitioner needs, in addition to analyzing the points already raised attention in the literature due to past projects, understand and adapt adequately to the environmental demands of the project. This insight has its bases in contingency theory, which can be synthesized by Scott (1981Scott, W. R. (1981). Organisations. Englewood Cliffs: Rational, Natural and Open Systems., p. 114) in the phrase: “The best way to organize depends on the nature of the environment in which the organization needs to relate.”

6 Conclusion

The current literature on project management in the context of public private partnerships addresses as major issues the challenges, techniques and success factors in this project format, but does so separately and without reference to their impact on the project life cycle, thus hindering the analysis for a researcher or practitioner in the area to understand what are the major focuses of attention and opportunities to be explored.

To fill this gap in the literature, this study realizes a systematic literature review based on the main journals and authors of these themes to systematize and facilitate the knowledge of these areas, mainly from a perspective of the different phases of the project, which facilitates understanding and focuses the attention of managers to specific challenges of each period for the long-term view.For this purpose, this study developed a bibliometric analysis based on 99 articles relevant to the PM and PPP context, and a content analysis around the 24 publications with major impact in the academy.

The bibliometric analysis, no only explains the increrasingly importance of public private partnership theme for literature and practice as an alternative to enable complex works of great impact to society, points to stakeholder management, risk management and analysis of the critical success factors as main = focuses of attention for PM in projects of this nature. Content analysis, in turn, identified how each of these focuses of attention impact the project during its life cycle, with an emphasis on the early stages of it. The main difficulties and challenges of this model of project show that many problems on-project occur due to failures or ill defined and / or planned activities in its beginning, but that sometimes only arise at later stages.

The results thus bring contributions to academy organizing the knowledge on the area and providing a rich discussion of potential studies to be conducted in project management in PPP. The findings also provide for practitioners - a greater understanding of the challenges that must be concerned during each phase of the project and the techniques used today to solve or mitigate these challenges, as well as which of the success factors are more relevant. The study also shows the importance for practitioners to use these findings from the initial stages of the project, where exactly there is a greater focus of attention to be considered.

Considering the limitations of scope and time frame of this research, this study is limited to a number of scientific basis and the combination of keywords searched displayed in the search method section and possibly previous studies in the area may have been left out of the final sample. As the objective of this research was to focus on quality and not quantity, as discussed above, it is believed that the selected studies are sufficient to identify the current state of the PM literature on PPP and the most relevant information for the area.

Note that there is no correlation between the authors of this research with the selected items. One indication is that there are no jobs selected in the same country where this research was conducted.

As detailed in themethod section for content analysis articles were analyzed and reviewed by different people to reduce possible biases and inconsistencies. Still, the content analysis stage is more susceptible to human error and the interpretation, categorization, and clustering information intra and inter articles.

This systematic literature review presents both academic implications as to practitioners in the field. To academy, the findings show a fertile literature field that can be better exploited (Thamer & Lazzarini, 2015Thamer, R., & Lazzarini, S. (2015). Projetos de parceria público-privada: fatores que influenciam o avanço dessas iniciativas. Revista de Administração Pública, 49(4), 819-846. http://dx.doi.org/10.1590/0034-7612119746.
http://dx.doi.org/10.1590/0034-761211974...
), because it is a comprehensive field, with various consequences for important issues such as risk management and stakeholder management, which in turn can be referenced for risk and stakeholder management from other areas (Tang et al., 2010Tang, L., Shen, Q., & Cheng, E. W. (2010). A review of studies on public–private partnership projects in the construction industry. International Journal of Project Management, 28(7), 683-694. http://dx.doi.org/10.1016/j.ijproman.2009.11.009.
http://dx.doi.org/10.1016/j.ijproman.200...
). In this sense, it was found several points that could be better exploited by future research. Toor & Ogunlana (2010)Toor, S.-R., & Ogunlana, S. O. (2010). Beyond the ‘iron triangle’: stakeholder perception of key performance indicators (KPIs) for large-scale public sector development projects. International Journal of Project Management, 28(3), 228-236. http://dx.doi.org/10.1016/j.ijproman.2009.05.005.
http://dx.doi.org/10.1016/j.ijproman.200...
indicates that there are few studies that combine quantitative to qualitative studies for evaluation of projects and creation of key performance indicators (KPI) of PPP projects, as well as a relationship with these critical success factors identified in literature. Work on KPI's could also assist in studies of decision-making tools in this type of project (Aritua et al., 2009Aritua, B., Smith, N. J., & Bower, D. (2009). Construction client multi-projects–A complex adaptive systems perspective. International Journal of Project Management, 27(1), 72-79. http://dx.doi.org/10.1016/j.ijproman.2008.02.005.
http://dx.doi.org/10.1016/j.ijproman.200...
). In relation to risk management, Jin & Zhang (2011)Jin, X. H., & Zhang, G. (2011). Modelling optimal risk allocation in PPP projects using artificial neural networks. International Journal of Project Management, 29(5), 591-603. http://dx.doi.org/10.1016/j.ijproman.2010.07.011.
http://dx.doi.org/10.1016/j.ijproman.201...
point to the creation of models based on neural networks to improve estimates and reduce risks on-project, while the risk sharing study with the hybrid model of alliance can deliver results beneficial for both parties (Clifton & Duffield, 2006Clifton, C., & Duffield, C. F. (2006). Improved PFI/PPP service outcomes through the integration of Alliance principles. International Journal of Project Management, 24(7), 573-586. http://dx.doi.org/10.1016/j.ijproman.2006.07.005.
http://dx.doi.org/10.1016/j.ijproman.200...
). As the model of Alliance, it could be conducted studies to identify cases of success in PPPs to increase the attractiveness of this project for the private sector (Hwang et al., 2013Hwang, B. G., Zhao, X., & Gay, M. J. S. (2013). Public private partnership projects in Singapore: Factors, critical risks and preferred risk allocation from the perspective of contractors. International Journal of Project Management, 31(3), 424-433. http://dx.doi.org/10.1016/j.ijproman.2012.08.003.
http://dx.doi.org/10.1016/j.ijproman.201...
). Another area that could be considered is the dichotomy between models of management hard and soft for PPPs (Yeo & Tiong, 2000Yeo, K. T., & Tiong, R. L. (2000). Positive management of differences for risk reduction in BOT projects. International Journal of Project Management, 18(4), 257-265. http://dx.doi.org/10.1016/S0263-7863(99)00018-6.
http://dx.doi.org/10.1016/S0263-7863(99)...
). Thamer & Lazzarini suggest further studies on the factors: trust, culture and incentives in building these partnerships, more efficient and transparent mechanisms for PPP approval step.

For practitioners in the field, it is clear that the challenges faced on-project, as well as the methods and techniques to overcome these difficulties to achieve the critical success factors need to be analyzed separately within each design time and that most concern of managers in this area is concentrated at the beginning of the project, showing that if some points have been forgotten or made without due attention, problems may appear in the result of the project, hindering the overall success.

Appendix A  Characterization of studies according to method and focus.

Reference Method Focus
1 Grimsey & Lewis (2002)Grimsey, D., & Lewis, M. K. (2002). Evaluating the risks of public private partnerships for infrastructure projects. International Journal of Project Management, 20(2), 107-118. http://dx.doi.org/10.1016/S0263-7863(00)00040-5.
http://dx.doi.org/10.1016/S0263-7863(00)...
PE2 T2
2 Bing et al. (2005)Bing, L., Akintoye, A., Edwards, P. J., & Hardcastle, C. (2005). The allocation of risk in PPP/PFI construction projects in the UK. International Journal of Project Management, 23(1), 25-35. http://dx.doi.org/10.1016/j.ijproman.2004.04.006.
http://dx.doi.org/10.1016/j.ijproman.200...
PE1 T2
3 Zhang (2005)Zhang, X. (2005). Critical success factors for public–private partnerships in infrastructure development. Journal of Construction Engineering and Management, 131(1), 3-14. http://dx.doi.org/10.1061/(ASCE)0733-9364(2005)131:1(3).
http://dx.doi.org/10.1061/(ASCE)0733-936...
PE1 T4
4 El-Gohary et al. (2006)El-Gohary, N. M., Osman, H., & El-Diraby, T. E. (2006). Stakeholder management for public private partnerships. International Journal of Project Management, 24(7), 595-604. http://dx.doi.org/10.1016/j.ijproman.2006.07.009.
http://dx.doi.org/10.1016/j.ijproman.200...
PC2 T1
5 Smyth & Edkins (2007)Smyth, H., & Edkins, A. (2007). Relationship management in the management of PFI/PPP projects in the UK. International Journal of Project Management, 25(3), 232-240. http://dx.doi.org/10.1016/j.ijproman.2006.08.003.
http://dx.doi.org/10.1016/j.ijproman.200...
PE1 T1
6 Van Marrewijk et al. (2008)Van Marrewijk, A., Clegg, S. R., Pitsis, T. S., & Veenswijk, M. (2008). Managing public–private megaprojects: Paradoxes, complexity, and project design. International Journal of Project Management, 26(6), 591-600. http://dx.doi.org/10.1016/j.ijproman.2007.09.007.
http://dx.doi.org/10.1016/j.ijproman.200...
PE2 T4
7 Medda (2007)Medda, F. (2007). A game theory approach for the allocation of risks in transport public private partnerships. International Journal of Project Management, 25(3), 213-218. http://dx.doi.org/10.1016/j.ijproman.2006.06.003.
http://dx.doi.org/10.1016/j.ijproman.200...
PC2 T2
8 Toor & Ogunlana (2010)Toor, S.-R., & Ogunlana, S. O. (2010). Beyond the ‘iron triangle’: stakeholder perception of key performance indicators (KPIs) for large-scale public sector development projects. International Journal of Project Management, 28(3), 228-236. http://dx.doi.org/10.1016/j.ijproman.2009.05.005.
http://dx.doi.org/10.1016/j.ijproman.200...
PE1 T4
9 Shen et al. (2006)Shen, L. Y., Platten, A., & Deng, X. P. (2006). Role of public private partnerships to manage risks in public sector projects in Hong Kong. International Journal of Project Management, 24(7), 587-594. http://dx.doi.org/10.1016/j.ijproman.2006.07.006.
http://dx.doi.org/10.1016/j.ijproman.200...
PE2 T2
10 Kumaraswamy & Zhang (2001)Kumaraswamy, M. M., & Zhang, X. Q. (2001). Governmental role in BOT-led infrastructure development. International Journal of Project Management, 19(4), 195-205. http://dx.doi.org/10.1016/S0263-7863(99)00069-1.
http://dx.doi.org/10.1016/S0263-7863(99)...
PC1 T4
11 Ke et al. (2010a)Ke, Y., Wang, S., Chan, A. P., & Lam, P. T. (2010a). Preferred risk allocation in China’s public-private partnertship (PPP) projects. International Journal of Project Management, 28(5), 482-492. https://doi.org/10.1016/j.ijproman.2009.08.007.
https://doi.org/ https://doi.org/10.1016...
PE1 T2
12 Tang et al. (2010)Tang, L., Shen, Q., & Cheng, E. W. (2010). A review of studies on public–private partnership projects in the construction industry. International Journal of Project Management, 28(7), 683-694. http://dx.doi.org/10.1016/j.ijproman.2009.11.009.
http://dx.doi.org/10.1016/j.ijproman.200...
PC1 T4
13 Aritua et al. (2009)Aritua, B., Smith, N. J., & Bower, D. (2009). Construction client multi-projects–A complex adaptive systems perspective. International Journal of Project Management, 27(1), 72-79. http://dx.doi.org/10.1016/j.ijproman.2008.02.005.
http://dx.doi.org/10.1016/j.ijproman.200...
PC2 T4
14 Li et al. (2005a)Li, B., Akintoye, A., Edwards, P. J., & Hardcastle, C. (2005a). Critical success factors for PPP/PFI projects in the UK construction industry. Construction Management and Economics, 23(5), 459-471. http://dx.doi.org/10.1080/01446190500041537.
http://dx.doi.org/10.1080/01446190500041...
PE1 T4
15 Van Marrewijk (2007)Van Marrewijk, A. (2007). Managing project culture: the case of Environ Megaproject. International Journal of Project Management, 25(3), 290-299. http://dx.doi.org/10.1016/j.ijproman.2006.11.004.
http://dx.doi.org/10.1016/j.ijproman.200...
PE2 T4
16 Clifton & Duffield (2006)Clifton, C., & Duffield, C. F. (2006). Improved PFI/PPP service outcomes through the integration of Alliance principles. International Journal of Project Management, 24(7), 573-586. http://dx.doi.org/10.1016/j.ijproman.2006.07.005.
http://dx.doi.org/10.1016/j.ijproman.200...
PC2 T4
17 Jin & Zhang (2011)Jin, X. H., & Zhang, G. (2011). Modelling optimal risk allocation in PPP projects using artificial neural networks. International Journal of Project Management, 29(5), 591-603. http://dx.doi.org/10.1016/j.ijproman.2010.07.011.
http://dx.doi.org/10.1016/j.ijproman.201...
PE1 T2
18 Zhang (2007)Zhang, H. (2007). A redefinition of the project risk process: using vulnerability to open up the event-consequence link. International Journal of Project Management, 25(7), 694-701. http://dx.doi.org/10.1016/j.ijproman.2007.02.004.
http://dx.doi.org/10.1016/j.ijproman.200...
PC2 T2
19 Reijniers (1994)Reijniers, J. J. A. M. (1994). Organization of public-private partnership projects: the timely prevention of pitfalls. International Journal of Project Management, 12(3), 137-142. http://dx.doi.org/10.1016/0263-7863(94)90028-0.
http://dx.doi.org/10.1016/0263-7863(94)9...
PE2 T4
20 Hwang et al. (2013)Hwang, B. G., Zhao, X., & Gay, M. J. S. (2013). Public private partnership projects in Singapore: Factors, critical risks and preferred risk allocation from the perspective of contractors. International Journal of Project Management, 31(3), 424-433. http://dx.doi.org/10.1016/j.ijproman.2012.08.003.
http://dx.doi.org/10.1016/j.ijproman.201...
PE1 T2
21 Yeo & Tiong (2000)Yeo, K. T., & Tiong, R. L. (2000). Positive management of differences for risk reduction in BOT projects. International Journal of Project Management, 18(4), 257-265. http://dx.doi.org/10.1016/S0263-7863(99)00018-6.
http://dx.doi.org/10.1016/S0263-7863(99)...
PE2 T2
22 Flyvbjerg (2013)Flyvbjerg, B. (2013). Quality control and due diligence in project management: getting decisions right by taking the outside view. International Journal of Project Management, 31(5), 760-774. http://dx.doi.org/10.1016/j.ijproman.2012.10.007.
http://dx.doi.org/10.1016/j.ijproman.201...
PE2 T4
23 Bachy & Hameri (1997)Bachy, G., & Hameri, A. P. (1997). What to be implemented at the early stage of a large-scale project. International Journal of Project Management, 15(4), 211-218. http://dx.doi.org/10.1016/S0263-7863(96)00070-1.
http://dx.doi.org/10.1016/S0263-7863(96)...
PC2 T4
24 De Lemos et al. (2004)De Lemos, T., Eaton, D., Betts, M., & de Almeida, L. T. (2004). Risk management in the Lusoponte concession: a case study of the two bridges in Lisbon, Portugal. International Journal of Project Management, 22(1), 63-73. http://dx.doi.org/10.1016/S0263-7863(03)00013-9.
http://dx.doi.org/10.1016/S0263-7863(03)...
PE2 T2
25 Zou et al. (2014)Zou, W., Kumaraswamy, M., Chung, J., & Wong, J. (2014). Identifying the critical success factors for relationship management in PPP projects. International Journal of Project Management, 32(2), 265-274. http://dx.doi.org/10.1016/j.ijproman.2013.05.004.
http://dx.doi.org/10.1016/j.ijproman.201...
PE1 T4
26 Singh & Kalidindi (2006)Singh, L. B., & Kalidindi, S. N. (2006). Traffic revenue risk management through Annuity Model of PPP road projects in India. International Journal of Project Management, 24(7), 605-613. http://dx.doi.org/10.1016/j.ijproman.2006.07.008.
http://dx.doi.org/10.1016/j.ijproman.200...
PE2 T2
27 Devapriya (2006)Devapriya, K. A. K. (2006). Governance issues in financing of public–private partnership organisations in network infrastructure industries. International Journal of Project Management, 24(7), 557-565. http://dx.doi.org/10.1016/j.ijproman.2006.07.003.
http://dx.doi.org/10.1016/j.ijproman.200...
PC2 T3
28 Ke et al. (2010b)Ke, Y., Wang, S., & Chan, A. P. (2010b). Risk allocation in public-private partnership infrastructure projects: comparative study. Journal of Infrastructure Systems, 16(4), 343-351. http://dx.doi.org/10.1061/(ASCE)IS.1943-555X.0000030.
http://dx.doi.org/10.1061/(ASCE)IS.1943-...
PE1 T2
29 Edelenbos & Klijn (2009)Edelenbos, J., & Klijn, E. H. (2009). Project versus process management in public-private partnership: relation between management style and outcomes. International Public Management Journal, 12(3), 310-331. http://dx.doi.org/10.1080/10967490903094350.
http://dx.doi.org/10.1080/10967490903094...
PE1 T4
30 Daube et al. (2008)Daube, D., Vollrath, S., & Alfen, H. W. (2008). A comparison of Project Finance and the Forfeiting Model as financing forms for PPP projects in Germany. International Journal of Project Management, 26(4), 376-387. http://dx.doi.org/10.1016/j.ijproman.2007.07.001.
http://dx.doi.org/10.1016/j.ijproman.200...
PC2 T3
31 Li et al. (2005b)Li, B., Akintoye, A., Edwards, P. J., & Hardcastle, C. (2005b). Perceptions of positive and negative factors influencing the attractiveness of PPP/PFI procurement for construction projects in the UK: findings from a questionnaire survey. Engineering, Construction, and Architectural Management, 12(2), 125-148. http://dx.doi.org/10.1108/09699980510584485.
http://dx.doi.org/10.1108/09699980510584...
PE1 T3
32 Yu & Kwon (2011)Yu, J. H., & Kwon, H. R. (2011). Critical success factors for urban regeneration projects in Korea. International Journal of Project Management, 29(7), 889-899. http://dx.doi.org/10.1016/j.ijproman.2010.09.001.
http://dx.doi.org/10.1016/j.ijproman.201...
PE1 T4
33 Xu et al. (2012)Xu, Y., Sun, C., Skibniewski, M. J., Chan, A. P., Yeung, J. F., & Cheng, H. (2012). System Dynamics (SD)-based concession pricing model for PPP highway projects. International Journal of Project Management, 30(2), 240-251. http://dx.doi.org/10.1016/j.ijproman.2011.06.001.
http://dx.doi.org/10.1016/j.ijproman.201...
PE2 T3
34 Yang et al. (2010)Yang, J. B., Yang, C. C., & Kao, C. K. (2010). Evaluating schedule delay causes for private participating public construction works under the Build-Operate-Transfer model. International Journal of Project Management, 28(6), 569-579. http://dx.doi.org/10.1016/j.ijproman.2009.10.005.
http://dx.doi.org/10.1016/j.ijproman.200...
PE1 T4
35 Yuan et al. (2009)Yuan, J., Zeng, A. Y., Skibniewski, M. J., & Li, Q. (2009). Selection of performance objectives and key performance indicators in public–private partnership projects to achieve value for money. Construction Management and Economics, 27(3), 253-270. http://dx.doi.org/10.1080/01446190902748705.
http://dx.doi.org/10.1080/01446190902748...
PE1 T4
36 Biesenthal & Wilden (2014)Biesenthal, C., & Wilden, R. (2014). Multi-level project governance: trends and opportunities. International Journal of Project Management, 32(8), 1291-1308. http://dx.doi.org/10.1016/j.ijproman.2014.06.005.
http://dx.doi.org/10.1016/j.ijproman.201...
PC1 T4
37 Edkins & Smyth (2006)Edkins, A. J., & Smyth, H. J. (2006). Contractual management in PPP projects: evaluation of legal versus relational contracting for service delivery. Journal of Professional Issues in Engineering Education and Practice, 132(1), 82-93. http://dx.doi.org/10.1061/(ASCE)1052-3928(2006)132:1(82).
http://dx.doi.org/10.1061/(ASCE)1052-392...
PE1 T1
38 Liu & Wilkinson (2014b)Liu, T., & Wilkinson, S. (2014b). Large-scale public venue development and the application of Public–Private Partnerships (PPPs). International Journal of Project Management, 32(1), 88-100. http://dx.doi.org/10.1016/j.ijproman.2013.01.003.
http://dx.doi.org/10.1016/j.ijproman.201...
PE2 T3
39 De Schepper et al. (2014)De Schepper, S., Dooms, M., & Haezendonck, E. (2014). Stakeholder dynamics and responsibilities in Public–Private Partnerships: A mixed experience. International Journal of Project Management, 32(7), 1210-1222. http://dx.doi.org/10.1016/j.ijproman.2014.01.006.
http://dx.doi.org/10.1016/j.ijproman.201...
PE2 T1
40 Ling et al. (2014)Ling, F. Y. Y., Ong, S. Y., Ke, Y., Wang, S., & Zou, P. (2014). Drivers and barriers to adopting relational contracting practices in public projects: comparative study of Beijing and Sydney. International Journal of Project Management, 32(2), 275-285. http://dx.doi.org/10.1016/j.ijproman.2013.04.008.
http://dx.doi.org/10.1016/j.ijproman.201...
PE1 T1
41 Carbonara et al. (2014)Carbonara, N., Costantino, N., & Pellegrino, R. (2014). Concession period for PPPs: A win–win model for a fair risk sharing. International Journal of Project Management, 32(7), 1223-1232. http://dx.doi.org/10.1016/j.ijproman.2014.01.007.
http://dx.doi.org/10.1016/j.ijproman.201...
PE2 T5
42 Tang & Shen (2013)Tang, L., & Shen, Q. (2013). Factors affecting effectiveness and efficiency of analyzing stakeholders’ needs at the briefing stage of public private partnership projects. International Journal of Project Management, 31(4), 513-521. http://dx.doi.org/10.1016/j.ijproman.2012.10.010.
http://dx.doi.org/10.1016/j.ijproman.201...
PE1 T1
43 Jacobson & Ok Choi (2008)Jacobson, C., & Ok Choi, S. (2008). Success factors: public works and public-private partnerships. International Journal of Public Sector Management, 21(6), 637-657. http://dx.doi.org/10.1108/09513550810896514.
http://dx.doi.org/10.1108/09513550810896...
PE2 T4
44 Cheung & Chan (2011)Cheung, E., & Chan, A. P. (2011). Risk factors of public-private partnership projects in China: comparison between the water, power, and transportation sectors. Journal of Urban Planning and Development, 137(4), 409-415. http://dx.doi.org/10.1061/(ASCE)UP.1943-5444.0000086.
http://dx.doi.org/10.1061/(ASCE)UP.1943-...
PE1 T2
45 Osei-Kyei & Chan (2015)Osei-Kyei, R., & Chan, A. P. (2015). Review of studies on the Critical Success Factors for Public–Private Partnership (PPP) projects from 1990 to 2013. International Journal of Project Management, 33(6), 1335-1346. http://dx.doi.org/10.1016/j.ijproman.2015.02.008.
http://dx.doi.org/10.1016/j.ijproman.201...
PC1 T4
46 Guo et al. (2014)Guo, F., Chang-Richards, Y., Wilkinson, S., & Li, T. C. (2014). Effects of project governance structures on the management of risks in major infrastructure projects: a comparative analysis. International Journal of Project Management, 32(5), 815-826. http://dx.doi.org/10.1016/j.ijproman.2013.10.001.
http://dx.doi.org/10.1016/j.ijproman.201...
PE2 T2
47 Kakabadse et al. (2007)Kakabadse, N. K., Kakabadse, A. P., & Summers, N. (2007). Effectiveness of private finance initiatives (PFI): study of private financing for the provision of capital assets for schools. Public Administration and Development, 27(1), 49-61. http://dx.doi.org/10.1002/pad.433.
http://dx.doi.org/10.1002/pad.433...
PE2 T3
48 Verweij (2015a)Verweij, S. (2015a). Achieving satisfaction when implementing PPP transportation infrastructure projects: A qualitative comparative analysis of the A15 highway DBFM project. International Journal of Project Management, 33(1), 189-200. http://dx.doi.org/10.1016/j.ijproman.2014.05.004.
http://dx.doi.org/10.1016/j.ijproman.201...
PE2 T4
49 Liu et al. (2014b)Liu, J., Yu, X., & Cheah, C. Y. J. (2014b). Evaluation of restrictive competition in PPP projects using real option approach. International Journal of Project Management, 32(3), 473-481. http://dx.doi.org/10.1016/j.ijproman.2013.07.007.
http://dx.doi.org/10.1016/j.ijproman.201...
PC2 T3
50 Henisz (2006)Henisz, W. V. J. (2006). Governance issues in public private partnerships. International Journal of Project Management, 7(24), 537-538. PE2 T2
51 Codecasa & Ponzini (2011)Codecasa, G., & Ponzini, D. (2011). Public–private partnership: a delusion for urban regeneration? Evidence from Italy. European Planning Studies, 19(4), 647-667. http://dx.doi.org/10.1080/09654313.2011.548471.
http://dx.doi.org/10.1080/09654313.2011....
PE2 T4
52 Edelenbos & Teisman (2008)Edelenbos, J., & Teisman, G. R. (2008). Public-private partnership: on the edge of project and process management. Insights from Dutch practice: the Sijtwende spatial development project. Environment and Planning. C, Government & Policy, 26(3), 614-626. http://dx.doi.org/10.1068/c66m.
http://dx.doi.org/10.1068/c66m...
PE2 T4
53 Pitsis et al. (2014)Pitsis, T. S., Sankaran, S., Gudergan, S., & Clegg, S. R. (2014). Governing projects under complexity: theory and practice in project management. International Journal of Project Management, 32(8), 1285-1290. http://dx.doi.org/10.1016/j.ijproman.2014.09.001.
http://dx.doi.org/10.1016/j.ijproman.201...
PC2 T4
54 Liu et al. (2014a)Liu, J., Love, P. E., Smith, J., Regan, M., & Davis, P. R. (2014a). Life cycle critical success factors for public-private partnership infrastructure projects. Journal of Management Engineering, 31(5), 04014073. http://dx.doi.org/10.1061/(ASCE)ME.1943-5479.0000307.
http://dx.doi.org/10.1061/(ASCE)ME.1943-...
PC2 T4
55 Jefferies & McGeorge (2009)Jefferies, M., & McGeorge, W. D. (2009). Using public-private partnerships (PPPs) to procure social infrastructure in Australia. Engineering, Construction, and Architectural Management, 16(5), 415-437. http://dx.doi.org/10.1108/09699980910988348.
http://dx.doi.org/10.1108/09699980910988...
PE2 T3
56 Heravi & Hajihosseini (2011)Heravi, G., & Hajihosseini, Z. (2011). Risk allocation in public–private partnership infrastructure projects in developing countries: case study of the Tehran–Chalus toll road. Journal of Infrastructure Systems, 18(3), 210-217. http://dx.doi.org/10.1061/(ASCE)IS.1943-555X.0000090.
http://dx.doi.org/10.1061/(ASCE)IS.1943-...
PE2 T2
57 Ye et al. (2014)Ye, K., Shen, L., Xia, B., & Li, B. (2014). Key attributes underpinning different markup decision between public and private projects: A China study. International Journal of Project Management, 32(3), 461-472. http://dx.doi.org/10.1016/j.ijproman.2013.06.001.
http://dx.doi.org/10.1016/j.ijproman.201...
PE1 T3
58 Kwak et al. (2014)Kwak, Y. H., Walewski, J., Sleeper, D., & Sadatsafavi, H. (2014). What can we learn from the Hoover Dam project that influenced modern project management? International Journal of Project Management, 32(2), 256-264. http://dx.doi.org/10.1016/j.ijproman.2013.04.002.
http://dx.doi.org/10.1016/j.ijproman.201...
PE2 T4
59 Fogelberg & Thorpenberg (2012)Fogelberg, H., & Thorpenberg, S. (2012). Regional innovation policy and public-private partnership: the case of Triple Helix Arenas in Western Sweden. Science & Public Policy, 39(3), 347-356. http://dx.doi.org/10.1093/scipol/scs023.
http://dx.doi.org/10.1093/scipol/scs023...
PE2 T1
60 Roumboutsos & Pantelias (2015)Roumboutsos, A., & Pantelias, A. (2015). Allocating revenue risk in transport infrastructure public private partnership projects: how it matters. Transport Reviews, 35(2), 183-203. http://dx.doi.org/10.1080/01441647.2014.988306.
http://dx.doi.org/10.1080/01441647.2014....
PE2 T2
61 Chen et al. (2006)Chen, M. S., Lu, H. F., & Lin, H. W. (2006). Are the nonprofit organizations suitable to engage in BOT or BLT scheme? A feasible analysis for the relationship of private and nonprofit sectors. International Journal of Project Management, 24(3), 244-252. http://dx.doi.org/10.1016/j.ijproman.2005.08.002.
http://dx.doi.org/10.1016/j.ijproman.200...
PC2 T1
62 Lenferink et al. (2013)Lenferink, S., Tillema, T., & Arts, J. (2013). Public–private interaction in contracting: governance strategies in the competitive dialogue of dutch infrastructure projects. Public Administration, 91(4), 928-946. http://dx.doi.org/10.1111/padm.12033.
http://dx.doi.org/10.1111/padm.12033...
PE2 T1
63 Chowdhury et al. (2011)Chowdhury, A. N., Chen, P. H., & Tiong, R. L. (2011). Analysing the structure of public–private partnership projects using network theory. Construction Management and Economics, 29(3), 247-260. http://dx.doi.org/10.1080/01446193.2010.537354.
http://dx.doi.org/10.1080/01446193.2010....
PC2 T1
64 Henjewele et al. (2014)Henjewele, C., Sun, M., & Fewings, P. (2014). Comparative performance of healthcare and transport PFI projects: empirical study on the influence of key factors. International Journal of Project Management, 32(1), 77-87. http://dx.doi.org/10.1016/j.ijproman.2013.01.008.
http://dx.doi.org/10.1016/j.ijproman.201...
PE2 T4
65 Dulaimi et al. (2010)Dulaimi, M. F., Alhashemi, M., Ling, F. Y. Y., & Kumaraswamy, M. (2010). The execution of public–private partnership projects in the UAE. Construction Management and Economics, 28(4), 393-402. http://dx.doi.org/10.1080/01446191003702492.
http://dx.doi.org/10.1080/01446191003702...
PE2 T4
66 Rajan et al. (2013)Rajan, T. A., Gopinath, G., & Behera, M. (2013). PPPs and project overruns: evidence from road projects in India. Journal of Construction Engineering and Management, 140(5), 04013070. http://dx.doi.org/10.1061/(ASCE)CO.1943-7862.0000797.
http://dx.doi.org/10.1061/(ASCE)CO.1943-...
PC2 T4
67 Wang (2015)Wang, Y. (2015). Evolution of public–private partnership models in American toll road development: learning based on public institutions’ risk management. International Journal of Project Management, 33(3), 684-696. http://dx.doi.org/10.1016/j.ijproman.2014.10.006.
http://dx.doi.org/10.1016/j.ijproman.201...
PE2 T2
68 Chou & Pramudawardhani (2015)Chou, J. S., & Pramudawardhani, D. (2015). Cross-country comparisons of key drivers, critical success factors and risk allocation for public-private partnership projects. International Journal of Project Management, 33(5), 1136-1150. http://dx.doi.org/10.1016/j.ijproman.2014.12.003.
http://dx.doi.org/10.1016/j.ijproman.201...
PE1 T3
69 Bayley (2003)Bayley, M. (2003). Channel Tunnel Rail Link: financing and risk transfer. Proceedings of the Institution of Civil Engineers. Civil Engineering, 156(5), 28-35. http://dx.doi.org/10.1680/cien.2003.156.5.28.
http://dx.doi.org/10.1680/cien.2003.156....
PE2 T3
70 Yun et al. (2015)Yun, S., Jung, W., Han, S. H., & Park, H. (2015). Critical organizational success factors for public private partnership projects–a comparison of solicited and unsolicited proposals. Journal of Civil Engineering and Management, 21(2), 131-143. http://dx.doi.org/10.3846/13923730.2013.802715.
http://dx.doi.org/10.3846/13923730.2013....
PE1 T4
71 Mistarihi et al. (2013)Mistarihi, A., Hutchings, K., & Shacklock, A. (2013). Differing opinions do not spoil friendships: Managing Public–Private Partnership (Ppp) Infrastructure Projects in Jordan. Public Administration and Development, 33(5), 371-388. http://dx.doi.org/10.1002/pad.1651.
http://dx.doi.org/10.1002/pad.1651...
PE2 T1
72 Mota & Moreira (2015)Mota, J., & Moreira, A. C. (2015). The importance of non-financial determinants on public–private partnerships in Europe. International Journal of Project Management, 33(7), 1563-1575. http://dx.doi.org/10.1016/j.ijproman.2015.04.005.
http://dx.doi.org/10.1016/j.ijproman.201...
PC2 T4
73 Liu & Wilkinson (2014a)Liu, T., & Wilkinson, S. (2014a). Critical factors affecting the viability of using public-private partnerships for prison development. Journal of Management Engineering, 31(5), 05014020. http://dx.doi.org/10.1061/(ASCE)ME.1943-5479.0000324.
http://dx.doi.org/10.1061/(ASCE)ME.1943-...
PE2 T4
74 Carpintero & Petersen (2015)Carpintero, S., & Petersen, O. H. (2015). Bundling and Unbundling in Public–Private Partnerships: Implications for Risk Sharing in Urban Transport Projects. Project Management Journal, 46(4), 35-46. http://dx.doi.org/10.1002/pmj.21508.
http://dx.doi.org/10.1002/pmj.21508...
PE2 T2
75 Liu et al. (2015)Liu, J., Love, P. E., Smith, J., Regan, M., & Palaneeswaran, E. (2015). Review of performance measurement: implications for public–private partnerships. Built Environment Project and Asset Management, 5(1), 35-51. http://dx.doi.org/10.1108/BEPAM-12-2013-0070.
http://dx.doi.org/10.1108/BEPAM-12-2013-...
PC1 T4
76 Atmo & Duffield (2014)Atmo, G., & Duffield, C. (2014). Improving investment sustainability for PPP power projects in emerging economies: value for money framework. Built Environment Project and Asset Management, 4(4), 335-351. http://dx.doi.org/10.1108/BEPAM-10-2013-0051.
http://dx.doi.org/10.1108/BEPAM-10-2013-...
PC2 T3
77 Chang (2013)Chang, C. Y. (2013). A critical review of the application of TCE in the interpretation of risk allocation in PPP contracts. Construction Management and Economics, 31(2), 99-103. http://dx.doi.org/10.1080/01446193.2012.726365.
http://dx.doi.org/10.1080/01446193.2012....
PC1 T2
78 Abdul-Aziz (2012)Abdul-Aziz, A. R. (2012). Control mechanisms exercised in Malaysian housing public-private partnerships. Construction Management and Economics, 30(1), 37-55. http://dx.doi.org/10.1080/01446193.2011.654129.
http://dx.doi.org/10.1080/01446193.2011....
PE2 T1
79 Kayaga & Zhe (2007)Kayaga, S., & Zhe, L. (2007). Analysis of public-private partnerships for China's water service. Proceedings of the Institution of Civil Engineers - Municipal Engineer, 160(1), 7-15. http://dx.doi.org/10.1680/muen.2007.160.1.7.
http://dx.doi.org/10.1680/muen.2007.160....
PE2 T4
80 Santosh Kumar Delhi et al. (2012)Santosh Kumar Delhi, V., Mahalingam, A., & Palukuri, S. (2012). Governance issues in BOT based PPP infrastructure projects in India. Built Environment Project and Asset Management, 2(2), 234-249. http://dx.doi.org/10.1108/20441241211280864.
http://dx.doi.org/10.1108/20441241211280...
PE2 T4
81 Skander & Préfontaine (2014)Skander, D., & Préfontaine, L. (2014). The evolution of control mechanisms. The Journal of Modern Project Management, 1(3) PE2 T1
82 Perić (2012)Perić, M. (2012). Implementation of project management in the BOT model of public-private partnership in Croatian tourism. Ekonomski Pregled, 63(9-10), 518-540. PE2 T4
83 Amponsah & Forbes (2012)Amponsah, C. T., & Forbes, J. L. (2012). Public–private partnerships: critical factors for procurement of capital projects. Proceedings of the Institution of Civil Engineers-Management, Procurement and Law, 165(4), 211-221. PC2 T4
84 Lilley (2005)Lilley, M. D. G. (2005). Sharing Risks and Responsibilities through Public Private Partnerships. Engineers Australia, 77(7), 10-12. PC1 T2
85 Zhang et al. (2016b)Zhang, X., Bao, H., Wang, H., & Skitmore, M. (2016b). A model for determining the optimal project life span and concession period of BOT projects. International Journal of Project Management, 34(3), 523-532. http://dx.doi.org/10.1016/j.ijproman.2016.01.005.
http://dx.doi.org/10.1016/j.ijproman.201...
PC2 T5
86 Padalkar & Gopinath (2016)Padalkar, M., & Gopinath, S. (2016). Six decades of project management research: thematic trends and future opportunities. International Journal of Project Management, 34(7), 1305-1321. http://dx.doi.org/10.1016/j.ijproman.2016.06.006.
http://dx.doi.org/10.1016/j.ijproman.201...
PC1 T4
87 Roberts & Siemiatycki (2015)Roberts, D. J., & Siemiatycki, M. (2015). Fostering meaningful partnerships in public–private partnerships: innovations in partnership design and process management to create value. Environment and Planning. C, Government & Policy, 33(4), 780-793. http://dx.doi.org/10.1068/c12250.
http://dx.doi.org/10.1068/c12250...
PE2 T1
88 Lavlinskii et al. (2016)Lavlinskii, S. M., Panin, A. A., & Plyasunov, A. V. (2016). Comparison of models of planning public-private partnership. Journal of Applied and Industrial Mathematics, 10(3), 356-369. http://dx.doi.org/10.1134/S1990478916030066.
http://dx.doi.org/10.1134/S1990478916030...
PC2 T4
89 Keck (1996)Keck, P. (1996). Public/private partnerships play increasing role in disaster response. Public Works, 127(13), 24-25. PE2 T4
90 Hughes (2005)Hughes, M. (2005). Contractors hurry to finish HSL-Zuid. Railway Gazette International. PE2 T4
91 Pankratz & Walkenmeyer (2005)Pankratz, T., & Walkenmeyer, P. (2005). Global trends in PPPs benefit desalination projects. Water and Wastewater International, 20(4), 11-12. PC1 T4
92 Lenferink et al. (2014)Lenferink, S., Tillema, T., & Arts, J. (2014). Lifecycle driven planning of infrastructure: public and private experiences with more integrated approaches for managing project complexity. European Journal of Transport and Infrastructure Research, 14(2), 82-101. PC2 T4
93 Chou & Leatemia (2016)Chou, J. S., & Leatemia, G. T. (2016). Critical Process and Factors for Ex-Post Evaluation of Public-Private Partnership Infrastructure Projects in Indonesia. Journal of Management Engineering, 32(5), 05016011. http://dx.doi.org/10.1061/(ASCE)ME.1943-5479.0000436.
http://dx.doi.org/10.1061/(ASCE)ME.1943-...
PC2 T4
94 De Clerck & Demeulemeester (2016)De Clerck, D., & Demeulemeester, E. (2016). An ex ante bidding model to assess the incentive creation capability of a public–private partnership pipeline. International Journal of Project Management, 34(1), 117-131. http://dx.doi.org/10.1016/j.ijproman.2015.10.007.
http://dx.doi.org/10.1016/j.ijproman.201...
PC2 T3
95 Loosemore & Cheung (2015)Loosemore, M., & Cheung, E. (2015). Implementing systems thinking to manage risk in public private partnership projects. International Journal of Project Management, 33(6), 1325-1334. http://dx.doi.org/10.1016/j.ijproman.2015.02.005.
http://dx.doi.org/10.1016/j.ijproman.201...
PE2 T2
96 Cheng et al. (2016)Cheng, Z., Ke, Y., Lin, J., Yang, Z., & Cai, J. (2016). Spatio-temporal dynamics of public private partnership projects in China. International Journal of Project Management, 34(7), 1242-1251. http://dx.doi.org/10.1016/j.ijproman.2016.05.006.
http://dx.doi.org/10.1016/j.ijproman.201...
PE1 T4
97 Koops et al. (2016)Koops, L., Bosch-Rekveldt, M., Coman, L., Hertogh, M., & Bakker, H. (2016). Identifying perspectives of public project managers on project success: comparing viewpoints of managers from five countries in North-West Europe. International Journal of Project Management, 34(5), 874-889. http://dx.doi.org/10.1016/j.ijproman.2016.03.007.
http://dx.doi.org/10.1016/j.ijproman.201...
PE1 T4
98 Liu, T., et al. (2016a) PE1 T4
99 Verweij (2015b)Verweij, S. (2015b). Producing satisfactory outcomes in the implementation phase of PPP infrastructure projects: A fuzzy set qualitative comparative analysis of 27 road constructions in the Netherlands. International Journal of Project Management, 33(8), 1877-1887. http://dx.doi.org/10.1016/j.ijproman.2015.08.006.
http://dx.doi.org/10.1016/j.ijproman.201...
PC2 T1
  • Financial support: None.
  • How to cite: Magalhães, L., Figueiredo, L. B., & Jesus, L. T. (2020). Project management in public-private partnerships: a conceptual framework based on a systematic literature review. Gestão & Produção, 27(1), e3772. https://doi.org/10.1590/0104-530X3772-20

References

  • Abdul-Aziz, A. R. (2012). Control mechanisms exercised in Malaysian housing public-private partnerships. Construction Management and Economics, 30(1), 37-55. http://dx.doi.org/10.1080/01446193.2011.654129
    » http://dx.doi.org/10.1080/01446193.2011.654129
  • Akintoye, A., Hardcastle, C., Beck, M., Chinyio, E., & Asenova, D. (2003). Achieving best value in private finance initiative project procurement. Construction Management and Economics, 21(5), 461-470. http://dx.doi.org/10.1080/0144619032000087285
    » http://dx.doi.org/10.1080/0144619032000087285
  • Amponsah, C. T., & Forbes, J. L. (2012). Public–private partnerships: critical factors for procurement of capital projects. Proceedings of the Institution of Civil Engineers-Management, Procurement and Law, 165(4), 211-221.
  • Aritua, B., Smith, N. J., & Bower, D. (2009). Construction client multi-projects–A complex adaptive systems perspective. International Journal of Project Management, 27(1), 72-79. http://dx.doi.org/10.1016/j.ijproman.2008.02.005
    » http://dx.doi.org/10.1016/j.ijproman.2008.02.005
  • Atmo, G., & Duffield, C. (2014). Improving investment sustainability for PPP power projects in emerging economies: value for money framework. Built Environment Project and Asset Management, 4(4), 335-351. http://dx.doi.org/10.1108/BEPAM-10-2013-0051
    » http://dx.doi.org/10.1108/BEPAM-10-2013-0051
  • Bachy, G., & Hameri, A. P. (1997). What to be implemented at the early stage of a large-scale project. International Journal of Project Management, 15(4), 211-218. http://dx.doi.org/10.1016/S0263-7863(96)00070-1
    » http://dx.doi.org/10.1016/S0263-7863(96)00070-1
  • Bayley, M. (2003). Channel Tunnel Rail Link: financing and risk transfer. Proceedings of the Institution of Civil Engineers. Civil Engineering, 156(5), 28-35. http://dx.doi.org/10.1680/cien.2003.156.5.28
    » http://dx.doi.org/10.1680/cien.2003.156.5.28
  • Biesenthal, C., & Wilden, R. (2014). Multi-level project governance: trends and opportunities. International Journal of Project Management, 32(8), 1291-1308. http://dx.doi.org/10.1016/j.ijproman.2014.06.005
    » http://dx.doi.org/10.1016/j.ijproman.2014.06.005
  • Bing, L., Akintoye, A., Edwards, P. J., & Hardcastle, C. (2005). The allocation of risk in PPP/PFI construction projects in the UK. International Journal of Project Management, 23(1), 25-35. http://dx.doi.org/10.1016/j.ijproman.2004.04.006
    » http://dx.doi.org/10.1016/j.ijproman.2004.04.006
  • Brasil. (2004, 31 de dezembro). Lei nº 11.079 de 30 de dezembro de 2004. Institui normas gerais para licitação e contratação de parceria público-privada no âmbito da administração pública Brasília, DF: Diário Oficial da República Federativa do Brasil. Retrieved in 2017, August 11, from http://www.planalto.gov.br/ccivil_03/_ato2004-2006/2004/Lei/L11079.htm
    » http://www.planalto.gov.br/ccivil_03/_ato2004-2006/2004/Lei/L11079.htm
  • Carbonara, N., Costantino, N., & Pellegrino, R. (2014). Concession period for PPPs: A win–win model for a fair risk sharing. International Journal of Project Management, 32(7), 1223-1232. http://dx.doi.org/10.1016/j.ijproman.2014.01.007
    » http://dx.doi.org/10.1016/j.ijproman.2014.01.007
  • Carpintero, S., & Petersen, O. H. (2015). Bundling and Unbundling in Public–Private Partnerships: Implications for Risk Sharing in Urban Transport Projects. Project Management Journal, 46(4), 35-46. http://dx.doi.org/10.1002/pmj.21508
    » http://dx.doi.org/10.1002/pmj.21508
  • Carvalho, M., Fleury, A., & Lopes, A. P. (2013). An overview of the literature on technology roadmapping (TRM): contributions and trends. Technological Forecasting and Social Change, 80(7), 1418-1437. http://dx.doi.org/10.1016/j.techfore.2012.11.008
    » http://dx.doi.org/10.1016/j.techfore.2012.11.008
  • Chang, C. Y. (2013). A critical review of the application of TCE in the interpretation of risk allocation in PPP contracts. Construction Management and Economics, 31(2), 99-103. http://dx.doi.org/10.1080/01446193.2012.726365
    » http://dx.doi.org/10.1080/01446193.2012.726365
  • Chen, M. S., Lu, H. F., & Lin, H. W. (2006). Are the nonprofit organizations suitable to engage in BOT or BLT scheme? A feasible analysis for the relationship of private and nonprofit sectors. International Journal of Project Management, 24(3), 244-252. http://dx.doi.org/10.1016/j.ijproman.2005.08.002
    » http://dx.doi.org/10.1016/j.ijproman.2005.08.002
  • Cheng, Z., Ke, Y., Lin, J., Yang, Z., & Cai, J. (2016). Spatio-temporal dynamics of public private partnership projects in China. International Journal of Project Management, 34(7), 1242-1251. http://dx.doi.org/10.1016/j.ijproman.2016.05.006
    » http://dx.doi.org/10.1016/j.ijproman.2016.05.006
  • Cheung, E., & Chan, A. P. (2011). Risk factors of public-private partnership projects in China: comparison between the water, power, and transportation sectors. Journal of Urban Planning and Development, 137(4), 409-415. http://dx.doi.org/10.1061/(ASCE)UP.1943-5444.0000086
    » http://dx.doi.org/10.1061/(ASCE)UP.1943-5444.0000086
  • Chou, J. S., & Leatemia, G. T. (2016). Critical Process and Factors for Ex-Post Evaluation of Public-Private Partnership Infrastructure Projects in Indonesia. Journal of Management Engineering, 32(5), 05016011. http://dx.doi.org/10.1061/(ASCE)ME.1943-5479.0000436
    » http://dx.doi.org/10.1061/(ASCE)ME.1943-5479.0000436
  • Chou, J. S., & Pramudawardhani, D. (2015). Cross-country comparisons of key drivers, critical success factors and risk allocation for public-private partnership projects. International Journal of Project Management, 33(5), 1136-1150. http://dx.doi.org/10.1016/j.ijproman.2014.12.003
    » http://dx.doi.org/10.1016/j.ijproman.2014.12.003
  • Chowdhury, A. N., Chen, P. H., & Tiong, R. L. (2011). Analysing the structure of public–private partnership projects using network theory. Construction Management and Economics, 29(3), 247-260. http://dx.doi.org/10.1080/01446193.2010.537354
    » http://dx.doi.org/10.1080/01446193.2010.537354
  • Clifton, C., & Duffield, C. F. (2006). Improved PFI/PPP service outcomes through the integration of Alliance principles. International Journal of Project Management, 24(7), 573-586. http://dx.doi.org/10.1016/j.ijproman.2006.07.005
    » http://dx.doi.org/10.1016/j.ijproman.2006.07.005
  • Codecasa, G., & Ponzini, D. (2011). Public–private partnership: a delusion for urban regeneration? Evidence from Italy. European Planning Studies, 19(4), 647-667. http://dx.doi.org/10.1080/09654313.2011.548471
    » http://dx.doi.org/10.1080/09654313.2011.548471
  • Croom, S. (2009). Introduction to research methodology in operations management. In C. Karlsson (Ed.), Researching operations management (pp. 42-83). Routledge: Taylor & Francis Group.
  • Cumming, D. (2007). Government policy towards entrepreneurial finance: innovation investment funds. Journal of Business Venturing, 22(2), 193-235. http://dx.doi.org/10.1016/j.jbusvent.2005.12.002
    » http://dx.doi.org/10.1016/j.jbusvent.2005.12.002
  • Daube, D., Vollrath, S., & Alfen, H. W. (2008). A comparison of Project Finance and the Forfeiting Model as financing forms for PPP projects in Germany. International Journal of Project Management, 26(4), 376-387. http://dx.doi.org/10.1016/j.ijproman.2007.07.001
    » http://dx.doi.org/10.1016/j.ijproman.2007.07.001
  • De Clerck, D., & Demeulemeester, E. (2016). An ex ante bidding model to assess the incentive creation capability of a public–private partnership pipeline. International Journal of Project Management, 34(1), 117-131. http://dx.doi.org/10.1016/j.ijproman.2015.10.007
    » http://dx.doi.org/10.1016/j.ijproman.2015.10.007
  • De Lemos, T., Eaton, D., Betts, M., & de Almeida, L. T. (2004). Risk management in the Lusoponte concession: a case study of the two bridges in Lisbon, Portugal. International Journal of Project Management, 22(1), 63-73. http://dx.doi.org/10.1016/S0263-7863(03)00013-9
    » http://dx.doi.org/10.1016/S0263-7863(03)00013-9
  • De Schepper, S., Dooms, M., & Haezendonck, E. (2014). Stakeholder dynamics and responsibilities in Public–Private Partnerships: A mixed experience. International Journal of Project Management, 32(7), 1210-1222. http://dx.doi.org/10.1016/j.ijproman.2014.01.006
    » http://dx.doi.org/10.1016/j.ijproman.2014.01.006
  • Devapriya, K. A. K. (2006). Governance issues in financing of public–private partnership organisations in network infrastructure industries. International Journal of Project Management, 24(7), 557-565. http://dx.doi.org/10.1016/j.ijproman.2006.07.003
    » http://dx.doi.org/10.1016/j.ijproman.2006.07.003
  • Dulaimi, M. F., Alhashemi, M., Ling, F. Y. Y., & Kumaraswamy, M. (2010). The execution of public–private partnership projects in the UAE. Construction Management and Economics, 28(4), 393-402. http://dx.doi.org/10.1080/01446191003702492
    » http://dx.doi.org/10.1080/01446191003702492
  • Edelenbos, J., & Klijn, E. H. (2009). Project versus process management in public-private partnership: relation between management style and outcomes. International Public Management Journal, 12(3), 310-331. http://dx.doi.org/10.1080/10967490903094350
    » http://dx.doi.org/10.1080/10967490903094350
  • Edelenbos, J., & Teisman, G. R. (2008). Public-private partnership: on the edge of project and process management. Insights from Dutch practice: the Sijtwende spatial development project. Environment and Planning. C, Government & Policy, 26(3), 614-626. http://dx.doi.org/10.1068/c66m
    » http://dx.doi.org/10.1068/c66m
  • Edkins, A. J., & Smyth, H. J. (2006). Contractual management in PPP projects: evaluation of legal versus relational contracting for service delivery. Journal of Professional Issues in Engineering Education and Practice, 132(1), 82-93. http://dx.doi.org/10.1061/(ASCE)1052-3928(2006)132:1(82)
    » http://dx.doi.org/10.1061/(ASCE)1052-3928(2006)132:1(82)
  • El-Gohary, N. M., Osman, H., & El-Diraby, T. E. (2006). Stakeholder management for public private partnerships. International Journal of Project Management, 24(7), 595-604. http://dx.doi.org/10.1016/j.ijproman.2006.07.009
    » http://dx.doi.org/10.1016/j.ijproman.2006.07.009
  • Flyvbjerg, B. (2013). Quality control and due diligence in project management: getting decisions right by taking the outside view. International Journal of Project Management, 31(5), 760-774. http://dx.doi.org/10.1016/j.ijproman.2012.10.007
    » http://dx.doi.org/10.1016/j.ijproman.2012.10.007
  • Fogelberg, H., & Thorpenberg, S. (2012). Regional innovation policy and public-private partnership: the case of Triple Helix Arenas in Western Sweden. Science & Public Policy, 39(3), 347-356. http://dx.doi.org/10.1093/scipol/scs023
    » http://dx.doi.org/10.1093/scipol/scs023
  • Grimsey, D., & Lewis, M. K. (2002). Evaluating the risks of public private partnerships for infrastructure projects. International Journal of Project Management, 20(2), 107-118. http://dx.doi.org/10.1016/S0263-7863(00)00040-5
    » http://dx.doi.org/10.1016/S0263-7863(00)00040-5
  • Guo, F., Chang-Richards, Y., Wilkinson, S., & Li, T. C. (2014). Effects of project governance structures on the management of risks in major infrastructure projects: a comparative analysis. International Journal of Project Management, 32(5), 815-826. http://dx.doi.org/10.1016/j.ijproman.2013.10.001
    » http://dx.doi.org/10.1016/j.ijproman.2013.10.001
  • Henisz, W. V. J. (2006). Governance issues in public private partnerships. International Journal of Project Management, 7(24), 537-538.
  • Henjewele, C., Sun, M., & Fewings, P. (2014). Comparative performance of healthcare and transport PFI projects: empirical study on the influence of key factors. International Journal of Project Management, 32(1), 77-87. http://dx.doi.org/10.1016/j.ijproman.2013.01.008
    » http://dx.doi.org/10.1016/j.ijproman.2013.01.008
  • Heravi, G., & Hajihosseini, Z. (2011). Risk allocation in public–private partnership infrastructure projects in developing countries: case study of the Tehran–Chalus toll road. Journal of Infrastructure Systems, 18(3), 210-217. http://dx.doi.org/10.1061/(ASCE)IS.1943-555X.0000090
    » http://dx.doi.org/10.1061/(ASCE)IS.1943-555X.0000090
  • Hughes, M. (2005). Contractors hurry to finish HSL-Zuid. Railway Gazette International.
  • Hwang, B. G., Zhao, X., & Gay, M. J. S. (2013). Public private partnership projects in Singapore: Factors, critical risks and preferred risk allocation from the perspective of contractors. International Journal of Project Management, 31(3), 424-433. http://dx.doi.org/10.1016/j.ijproman.2012.08.003
    » http://dx.doi.org/10.1016/j.ijproman.2012.08.003
  • Jacobson, C., & Ok Choi, S. (2008). Success factors: public works and public-private partnerships. International Journal of Public Sector Management, 21(6), 637-657. http://dx.doi.org/10.1108/09513550810896514
    » http://dx.doi.org/10.1108/09513550810896514
  • Jefferies, M., & McGeorge, W. D. (2009). Using public-private partnerships (PPPs) to procure social infrastructure in Australia. Engineering, Construction, and Architectural Management, 16(5), 415-437. http://dx.doi.org/10.1108/09699980910988348
    » http://dx.doi.org/10.1108/09699980910988348
  • Jin, X. H., & Zhang, G. (2011). Modelling optimal risk allocation in PPP projects using artificial neural networks. International Journal of Project Management, 29(5), 591-603. http://dx.doi.org/10.1016/j.ijproman.2010.07.011
    » http://dx.doi.org/10.1016/j.ijproman.2010.07.011
  • Kakabadse, N. K., Kakabadse, A. P., & Summers, N. (2007). Effectiveness of private finance initiatives (PFI): study of private financing for the provision of capital assets for schools. Public Administration and Development, 27(1), 49-61. http://dx.doi.org/10.1002/pad.433
    » http://dx.doi.org/10.1002/pad.433
  • Kayaga, S., & Zhe, L. (2007). Analysis of public-private partnerships for China's water service. Proceedings of the Institution of Civil Engineers - Municipal Engineer, 160(1), 7-15. http://dx.doi.org/10.1680/muen.2007.160.1.7
    » http://dx.doi.org/10.1680/muen.2007.160.1.7
  • Ke, Y., Wang, S., Chan, A. P., & Lam, P. T. (2010a). Preferred risk allocation in China’s public-private partnertship (PPP) projects. International Journal of Project Management, 28(5), 482-492. https://doi.org/10.1016/j.ijproman.2009.08.007.
    » https://doi.org/ https://doi.org/10.1016/j.ijproman.2009.08.007
  • Ke, Y., Wang, S., & Chan, A. P. (2010b). Risk allocation in public-private partnership infrastructure projects: comparative study. Journal of Infrastructure Systems, 16(4), 343-351. http://dx.doi.org/10.1061/(ASCE)IS.1943-555X.0000030
    » http://dx.doi.org/10.1061/(ASCE)IS.1943-555X.0000030
  • Keck, P. (1996). Public/private partnerships play increasing role in disaster response. Public Works, 127(13), 24-25.
  • Koops, L., Bosch-Rekveldt, M., Coman, L., Hertogh, M., & Bakker, H. (2016). Identifying perspectives of public project managers on project success: comparing viewpoints of managers from five countries in North-West Europe. International Journal of Project Management, 34(5), 874-889. http://dx.doi.org/10.1016/j.ijproman.2016.03.007
    » http://dx.doi.org/10.1016/j.ijproman.2016.03.007
  • Kumaraswamy, M. M., & Morris, D. A. (2002). Build-operate-transfer-type procurement in Asian megaprojects. Journal of Construction Engineering and Management, 128(2), 93-102. http://dx.doi.org/10.1061/(ASCE)0733-9364(2002)128:2(93)
    » http://dx.doi.org/10.1061/(ASCE)0733-9364(2002)128:2(93)
  • Kumaraswamy, M. M., & Zhang, X. Q. (2001). Governmental role in BOT-led infrastructure development. International Journal of Project Management, 19(4), 195-205. http://dx.doi.org/10.1016/S0263-7863(99)00069-1
    » http://dx.doi.org/10.1016/S0263-7863(99)00069-1
  • Kwak, Y. H., Walewski, J., Sleeper, D., & Sadatsafavi, H. (2014). What can we learn from the Hoover Dam project that influenced modern project management? International Journal of Project Management, 32(2), 256-264. http://dx.doi.org/10.1016/j.ijproman.2013.04.002
    » http://dx.doi.org/10.1016/j.ijproman.2013.04.002
  • Lavlinskii, S. M., Panin, A. A., & Plyasunov, A. V. (2016). Comparison of models of planning public-private partnership. Journal of Applied and Industrial Mathematics, 10(3), 356-369. http://dx.doi.org/10.1134/S1990478916030066
    » http://dx.doi.org/10.1134/S1990478916030066
  • Lenferink, S., Tillema, T., & Arts, J. (2013). Public–private interaction in contracting: governance strategies in the competitive dialogue of dutch infrastructure projects. Public Administration, 91(4), 928-946. http://dx.doi.org/10.1111/padm.12033
    » http://dx.doi.org/10.1111/padm.12033
  • Lenferink, S., Tillema, T., & Arts, J. (2014). Lifecycle driven planning of infrastructure: public and private experiences with more integrated approaches for managing project complexity. European Journal of Transport and Infrastructure Research, 14(2), 82-101.
  • Li, B., & Akintoye, A. (2003). An overview of public-private partnership (pp. 3-30). Blackwell Science: Oxford, UK.
  • Li, B., Akintoye, A., Edwards, P. J., & Hardcastle, C. (2005a). Critical success factors for PPP/PFI projects in the UK construction industry. Construction Management and Economics, 23(5), 459-471. http://dx.doi.org/10.1080/01446190500041537
    » http://dx.doi.org/10.1080/01446190500041537
  • Li, B., Akintoye, A., Edwards, P. J., & Hardcastle, C. (2005b). Perceptions of positive and negative factors influencing the attractiveness of PPP/PFI procurement for construction projects in the UK: findings from a questionnaire survey. Engineering, Construction, and Architectural Management, 12(2), 125-148. http://dx.doi.org/10.1108/09699980510584485
    » http://dx.doi.org/10.1108/09699980510584485
  • Lilley, M. D. G. (2005). Sharing Risks and Responsibilities through Public Private Partnerships. Engineers Australia, 77(7), 10-12.
  • Ling, F. Y. Y., Ong, S. Y., Ke, Y., Wang, S., & Zou, P. (2014). Drivers and barriers to adopting relational contracting practices in public projects: comparative study of Beijing and Sydney. International Journal of Project Management, 32(2), 275-285. http://dx.doi.org/10.1016/j.ijproman.2013.04.008
    » http://dx.doi.org/10.1016/j.ijproman.2013.04.008
  • Liu, J., Gao, R., Cheah, C. Y., & Luo, J. (2016). Incentive mechanism for inhibiting investors’ opportunistic behavior in PPP projects. International Journal of Project Management, 34(7), 1102-1111. http://dx.doi.org/10.1016/j.ijproman.2016.05.013
    » http://dx.doi.org/10.1016/j.ijproman.2016.05.013
  • Liu, J., Love, P. E., Smith, J., Regan, M., & Davis, P. R. (2014a). Life cycle critical success factors for public-private partnership infrastructure projects. Journal of Management Engineering, 31(5), 04014073. http://dx.doi.org/10.1061/(ASCE)ME.1943-5479.0000307
    » http://dx.doi.org/10.1061/(ASCE)ME.1943-5479.0000307
  • Liu, J., Yu, X., & Cheah, C. Y. J. (2014b). Evaluation of restrictive competition in PPP projects using real option approach. International Journal of Project Management, 32(3), 473-481. http://dx.doi.org/10.1016/j.ijproman.2013.07.007
    » http://dx.doi.org/10.1016/j.ijproman.2013.07.007
  • Liu, J., Love, P. E., Smith, J., Regan, M., & Palaneeswaran, E. (2015). Review of performance measurement: implications for public–private partnerships. Built Environment Project and Asset Management, 5(1), 35-51. http://dx.doi.org/10.1108/BEPAM-12-2013-0070
    » http://dx.doi.org/10.1108/BEPAM-12-2013-0070
  • Liu, T., & Wilkinson, S. (2014a). Critical factors affecting the viability of using public-private partnerships for prison development. Journal of Management Engineering, 31(5), 05014020. http://dx.doi.org/10.1061/(ASCE)ME.1943-5479.0000324
    » http://dx.doi.org/10.1061/(ASCE)ME.1943-5479.0000324
  • Liu, T., & Wilkinson, S. (2014b). Large-scale public venue development and the application of Public–Private Partnerships (PPPs). International Journal of Project Management, 32(1), 88-100. http://dx.doi.org/10.1016/j.ijproman.2013.01.003
    » http://dx.doi.org/10.1016/j.ijproman.2013.01.003
  • Liu, T., Wang, Y., & Wilkinson, S. (2016). Identifying critical factors affecting the effectiveness and efficiency of tendering processes in Public–Private Partnerships (PPPs): A comparative analysis of Australia and China. International Journal of Project Management, 34(4), 701-716. http://dx.doi.org/10.1016/j.ijproman.2016.01.004
    » http://dx.doi.org/10.1016/j.ijproman.2016.01.004
  • Loosemore, M., & Cheung, E. (2015). Implementing systems thinking to manage risk in public private partnership projects. International Journal of Project Management, 33(6), 1325-1334. http://dx.doi.org/10.1016/j.ijproman.2015.02.005
    » http://dx.doi.org/10.1016/j.ijproman.2015.02.005
  • Medda, F. (2007). A game theory approach for the allocation of risks in transport public private partnerships. International Journal of Project Management, 25(3), 213-218. http://dx.doi.org/10.1016/j.ijproman.2006.06.003
    » http://dx.doi.org/10.1016/j.ijproman.2006.06.003
  • Mistarihi, A., Hutchings, K., & Shacklock, A. (2013). Differing opinions do not spoil friendships: Managing Public–Private Partnership (Ppp) Infrastructure Projects in Jordan. Public Administration and Development, 33(5), 371-388. http://dx.doi.org/10.1002/pad.1651
    » http://dx.doi.org/10.1002/pad.1651
  • Mota, J., & Moreira, A. C. (2015). The importance of non-financial determinants on public–private partnerships in Europe. International Journal of Project Management, 33(7), 1563-1575. http://dx.doi.org/10.1016/j.ijproman.2015.04.005
    » http://dx.doi.org/10.1016/j.ijproman.2015.04.005
  • Osei-Kyei, R., & Chan, A. P. (2015). Review of studies on the Critical Success Factors for Public–Private Partnership (PPP) projects from 1990 to 2013. International Journal of Project Management, 33(6), 1335-1346. http://dx.doi.org/10.1016/j.ijproman.2015.02.008
    » http://dx.doi.org/10.1016/j.ijproman.2015.02.008
  • Padalkar, M., & Gopinath, S. (2016). Six decades of project management research: thematic trends and future opportunities. International Journal of Project Management, 34(7), 1305-1321. http://dx.doi.org/10.1016/j.ijproman.2016.06.006
    » http://dx.doi.org/10.1016/j.ijproman.2016.06.006
  • Pankratz, T., & Walkenmeyer, P. (2005). Global trends in PPPs benefit desalination projects. Water and Wastewater International, 20(4), 11-12.
  • Perić, M. (2012). Implementation of project management in the BOT model of public-private partnership in Croatian tourism. Ekonomski Pregled, 63(9-10), 518-540.
  • Pinto, H. A. C., & Ang, H. G. (2015). Estruturação de Projetos de PPP e Concessão no Brasil: diagnóstico do modelo brasileiro e propostas de aperfeiçoamento Washington: International Finance Corporation - World Bank Group.
  • Pitsis, T. S., Sankaran, S., Gudergan, S., & Clegg, S. R. (2014). Governing projects under complexity: theory and practice in project management. International Journal of Project Management, 32(8), 1285-1290. http://dx.doi.org/10.1016/j.ijproman.2014.09.001
    » http://dx.doi.org/10.1016/j.ijproman.2014.09.001
  • Quelin, B., Cabral, S., Lazzarini, S. G., & Kivleniece, I. (2014). The Private Scope in Public-Private Partnerships: An International Cross-Sector Study. Business Policy & Strategy, 2014(1), 15727. http://dx.doi.org/10.5465/ambpp.2014.15727abstract
    » http://dx.doi.org/10.5465/ambpp.2014.15727abstract
  • Rajan, T. A., Gopinath, G., & Behera, M. (2013). PPPs and project overruns: evidence from road projects in India. Journal of Construction Engineering and Management, 140(5), 04013070. http://dx.doi.org/10.1061/(ASCE)CO.1943-7862.0000797
    » http://dx.doi.org/10.1061/(ASCE)CO.1943-7862.0000797
  • Reijniers, J. J. A. M. (1994). Organization of public-private partnership projects: the timely prevention of pitfalls. International Journal of Project Management, 12(3), 137-142. http://dx.doi.org/10.1016/0263-7863(94)90028-0
    » http://dx.doi.org/10.1016/0263-7863(94)90028-0
  • Roberts, D. J., & Siemiatycki, M. (2015). Fostering meaningful partnerships in public–private partnerships: innovations in partnership design and process management to create value. Environment and Planning. C, Government & Policy, 33(4), 780-793. http://dx.doi.org/10.1068/c12250
    » http://dx.doi.org/10.1068/c12250
  • Roumboutsos, A., & Pantelias, A. (2015). Allocating revenue risk in transport infrastructure public private partnership projects: how it matters. Transport Reviews, 35(2), 183-203. http://dx.doi.org/10.1080/01441647.2014.988306
    » http://dx.doi.org/10.1080/01441647.2014.988306
  • Santosh Kumar Delhi, V., Mahalingam, A., & Palukuri, S. (2012). Governance issues in BOT based PPP infrastructure projects in India. Built Environment Project and Asset Management, 2(2), 234-249. http://dx.doi.org/10.1108/20441241211280864
    » http://dx.doi.org/10.1108/20441241211280864
  • Scott, W. R. (1981). Organisations Englewood Cliffs: Rational, Natural and Open Systems.
  • Shen, L. Y., Platten, A., & Deng, X. P. (2006). Role of public private partnerships to manage risks in public sector projects in Hong Kong. International Journal of Project Management, 24(7), 587-594. http://dx.doi.org/10.1016/j.ijproman.2006.07.006
    » http://dx.doi.org/10.1016/j.ijproman.2006.07.006
  • Singh, L. B., & Kalidindi, S. N. (2006). Traffic revenue risk management through Annuity Model of PPP road projects in India. International Journal of Project Management, 24(7), 605-613. http://dx.doi.org/10.1016/j.ijproman.2006.07.008
    » http://dx.doi.org/10.1016/j.ijproman.2006.07.008
  • Skander, D., & Préfontaine, L. (2014). The evolution of control mechanisms. The Journal of Modern Project Management, 1(3)
  • Skietrys, E., Raipa, A., & Bartkus, E. V. (2008). Dimensions of the efficiency of public-private partnership. The Engineering Economist, 58(3)
  • Smyth, H., & Edkins, A. (2007). Relationship management in the management of PFI/PPP projects in the UK. International Journal of Project Management, 25(3), 232-240. http://dx.doi.org/10.1016/j.ijproman.2006.08.003
    » http://dx.doi.org/10.1016/j.ijproman.2006.08.003
  • Takey, S. M., & Carvalho, M. M. (2016). Fuzzy front end of systemic innovations: A conceptual framework based on a systematic literature review. Technological Forecasting and Social Change, 111, 97-109. http://dx.doi.org/10.1016/j.techfore.2016.06.011
    » http://dx.doi.org/10.1016/j.techfore.2016.06.011
  • Tang, L., & Shen, Q. (2013). Factors affecting effectiveness and efficiency of analyzing stakeholders’ needs at the briefing stage of public private partnership projects. International Journal of Project Management, 31(4), 513-521. http://dx.doi.org/10.1016/j.ijproman.2012.10.010
    » http://dx.doi.org/10.1016/j.ijproman.2012.10.010
  • Tang, L., Shen, Q., & Cheng, E. W. (2010). A review of studies on public–private partnership projects in the construction industry. International Journal of Project Management, 28(7), 683-694. http://dx.doi.org/10.1016/j.ijproman.2009.11.009
    » http://dx.doi.org/10.1016/j.ijproman.2009.11.009
  • Thamer, R., & Lazzarini, S. (2015). Projetos de parceria público-privada: fatores que influenciam o avanço dessas iniciativas. Revista de Administração Pública, 49(4), 819-846. http://dx.doi.org/10.1590/0034-7612119746
    » http://dx.doi.org/10.1590/0034-7612119746
  • Toor, S.-R., & Ogunlana, S. O. (2010). Beyond the ‘iron triangle’: stakeholder perception of key performance indicators (KPIs) for large-scale public sector development projects. International Journal of Project Management, 28(3), 228-236. http://dx.doi.org/10.1016/j.ijproman.2009.05.005
    » http://dx.doi.org/10.1016/j.ijproman.2009.05.005
  • Treasury, H. M. (2006). Public private partnerships: the governments approach London: United Kingdom for The Stationery Office.
  • Van Marrewijk, A. (2007). Managing project culture: the case of Environ Megaproject. International Journal of Project Management, 25(3), 290-299. http://dx.doi.org/10.1016/j.ijproman.2006.11.004
    » http://dx.doi.org/10.1016/j.ijproman.2006.11.004
  • Van Marrewijk, A., Clegg, S. R., Pitsis, T. S., & Veenswijk, M. (2008). Managing public–private megaprojects: Paradoxes, complexity, and project design. International Journal of Project Management, 26(6), 591-600. http://dx.doi.org/10.1016/j.ijproman.2007.09.007
    » http://dx.doi.org/10.1016/j.ijproman.2007.09.007
  • Verweij, S. (2015a). Achieving satisfaction when implementing PPP transportation infrastructure projects: A qualitative comparative analysis of the A15 highway DBFM project. International Journal of Project Management, 33(1), 189-200. http://dx.doi.org/10.1016/j.ijproman.2014.05.004
    » http://dx.doi.org/10.1016/j.ijproman.2014.05.004
  • Verweij, S. (2015b). Producing satisfactory outcomes in the implementation phase of PPP infrastructure projects: A fuzzy set qualitative comparative analysis of 27 road constructions in the Netherlands. International Journal of Project Management, 33(8), 1877-1887. http://dx.doi.org/10.1016/j.ijproman.2015.08.006
    » http://dx.doi.org/10.1016/j.ijproman.2015.08.006
  • Wang, Y. (2015). Evolution of public–private partnership models in American toll road development: learning based on public institutions’ risk management. International Journal of Project Management, 33(3), 684-696. http://dx.doi.org/10.1016/j.ijproman.2014.10.006
    » http://dx.doi.org/10.1016/j.ijproman.2014.10.006
  • Wang, Y., & Liu, J. (2015). Evaluation of the excess revenue sharing ratio in PPP projects using principal–agent models. International Journal of Project Management, 33(6), 1317-1324. http://dx.doi.org/10.1016/j.ijproman.2015.03.002
    » http://dx.doi.org/10.1016/j.ijproman.2015.03.002
  • Xu, Y., Sun, C., Skibniewski, M. J., Chan, A. P., Yeung, J. F., & Cheng, H. (2012). System Dynamics (SD)-based concession pricing model for PPP highway projects. International Journal of Project Management, 30(2), 240-251. http://dx.doi.org/10.1016/j.ijproman.2011.06.001
    » http://dx.doi.org/10.1016/j.ijproman.2011.06.001
  • Yang, J. B., Yang, C. C., & Kao, C. K. (2010). Evaluating schedule delay causes for private participating public construction works under the Build-Operate-Transfer model. International Journal of Project Management, 28(6), 569-579. http://dx.doi.org/10.1016/j.ijproman.2009.10.005
    » http://dx.doi.org/10.1016/j.ijproman.2009.10.005
  • Ye, K., Shen, L., Xia, B., & Li, B. (2014). Key attributes underpinning different markup decision between public and private projects: A China study. International Journal of Project Management, 32(3), 461-472. http://dx.doi.org/10.1016/j.ijproman.2013.06.001
    » http://dx.doi.org/10.1016/j.ijproman.2013.06.001
  • Yeo, K. T., & Tiong, R. L. (2000). Positive management of differences for risk reduction in BOT projects. International Journal of Project Management, 18(4), 257-265. http://dx.doi.org/10.1016/S0263-7863(99)00018-6
    » http://dx.doi.org/10.1016/S0263-7863(99)00018-6
  • Yu, J. H., & Kwon, H. R. (2011). Critical success factors for urban regeneration projects in Korea. International Journal of Project Management, 29(7), 889-899. http://dx.doi.org/10.1016/j.ijproman.2010.09.001
    » http://dx.doi.org/10.1016/j.ijproman.2010.09.001
  • Yuan, J., Zeng, A. Y., Skibniewski, M. J., & Li, Q. (2009). Selection of performance objectives and key performance indicators in public–private partnership projects to achieve value for money. Construction Management and Economics, 27(3), 253-270. http://dx.doi.org/10.1080/01446190902748705
    » http://dx.doi.org/10.1080/01446190902748705
  • Yun, S., Jung, W., Han, S. H., & Park, H. (2015). Critical organizational success factors for public private partnership projects–a comparison of solicited and unsolicited proposals. Journal of Civil Engineering and Management, 21(2), 131-143. http://dx.doi.org/10.3846/13923730.2013.802715
    » http://dx.doi.org/10.3846/13923730.2013.802715
  • Zhang, H. (2007). A redefinition of the project risk process: using vulnerability to open up the event-consequence link. International Journal of Project Management, 25(7), 694-701. http://dx.doi.org/10.1016/j.ijproman.2007.02.004
    » http://dx.doi.org/10.1016/j.ijproman.2007.02.004
  • Zhang, S., Gao, Y., Feng, Z., & Sun, W. (2015). PPP application in infrastructure development in China: institutional analysis and implications. International Journal of Project Management, 33(3), 497-509. http://dx.doi.org/10.1016/j.ijproman.2014.06.006
    » http://dx.doi.org/10.1016/j.ijproman.2014.06.006
  • Zhang, X. (2005). Critical success factors for public–private partnerships in infrastructure development. Journal of Construction Engineering and Management, 131(1), 3-14. http://dx.doi.org/10.1061/(ASCE)0733-9364(2005)131:1(3)
    » http://dx.doi.org/10.1061/(ASCE)0733-9364(2005)131:1(3)
  • Zhang, S., Chan, A. P., Feng, Y., Duan, H., & Ke, Y. (2016a). Critical review on PPP Research–A search from the Chinese and International Journals. International Journal of Project Management, 34(4), 597-612. http://dx.doi.org/10.1016/j.ijproman.2016.02.008
    » http://dx.doi.org/10.1016/j.ijproman.2016.02.008
  • Zhang, X., Bao, H., Wang, H., & Skitmore, M. (2016b). A model for determining the optimal project life span and concession period of BOT projects. International Journal of Project Management, 34(3), 523-532. http://dx.doi.org/10.1016/j.ijproman.2016.01.005
    » http://dx.doi.org/10.1016/j.ijproman.2016.01.005
  • Zou, W., Kumaraswamy, M., Chung, J., & Wong, J. (2014). Identifying the critical success factors for relationship management in PPP projects. International Journal of Project Management, 32(2), 265-274. http://dx.doi.org/10.1016/j.ijproman.2013.05.004
    » http://dx.doi.org/10.1016/j.ijproman.2013.05.004

Publication Dates

  • Publication in this collection
    13 Mar 2020
  • Date of issue
    2020

History

  • Received
    30 Jan 2017
  • Accepted
    03 Sept 2017
Universidade Federal de São Carlos Departamento de Engenharia de Produção , Caixa Postal 676 , 13.565-905 São Carlos SP Brazil, Tel.: +55 16 3351 8471 - São Carlos - SP - Brazil
E-mail: gp@dep.ufscar.br