The impact of the project management office on scientific research

Abstract

This article aims to demonstrate that the project management office, an organizational unit recognized by PMBOK®, can support scientists in research project management, so they can engage in other activities. In order to test the hypothesis, the theoretical framework and data collection of projects funded by the Research Support Foundation in the State of São Paulo (Fapesp) and executed at the Medical School of Ribeirão Preto (FMRP) from 2009 to 2015 were investigated. The study showed that scientists would have met the requirements of the funding agency without this support. However, the office impacted the financial management of the project, an initiative aligned with the practices of foreign universities, in which support to scientists has already become a routine part of institutional support.

Keywords:
project management; scientific research; success

Resumo

O objetivo deste artigo é demonstrar que o escritório de gestão de projetos, uma unidade organizacional reconhecida pelo guia Project Management Body of Knowledge (PMBOK®), pode apoiar o cientista na gestão de projetos de pesquisa, de modo que ele se dedique a outras atividades. Para testar a hipótese, detalha-se o marco teórico e a coleta de dados de projetos financiados pela Fundação de Apoio à Pesquisa no Estado de São Paulo (Fapesp) e executados na Faculdade de Medicina de Ribeirão Preto da Universidade de São Paulo (FMRP-USP) no período de 2009 a 2015. O estudo mostrou que os cientistas teriam cumprido os requisitos exigidos pela agência de financiamento sem esse apoio; porém, o escritório impactou a gestão financeira do projeto, uma iniciativa alinhada às práticas de universidades estrangeiras, nas quais o suporte a cientistas já se tornou parte rotineira do apoio institucional.

Palavras-chave:
gestão de projetos; pesquisa científica; sucesso

Resumen

El objetivo de este artículo fue demostrar que la oficina de gestión de proyectos, una unidad organizativa reconocida por PMBOK®, puede apoyar al científico en la gestión de proyectos de investigación, de modo que participe en otras actividades. Con el fin de probar la hipótesis, se han detallado el marco teórico y la recopilación de datos de los proyectos financiados por la Fundación de Apoyo a la Investigación en el Estado de São Paulo (Fapesp) y ejecutados en la Facultad de Medicina de Ribeirão Preto (FMRP) de 2009 hasta 2015. El estudio mostró que los científicos habrían cumplido los requisitos exigidos por la agencia de financiación sin ese apoyo; sin embargo, la oficina influenció en la administración financiera del proyecto, una iniciativa alineada con las prácticas de universidades extranjeras, en las cuales el apoyo a los científicos ya se ha convertido en una parte rutinaria del apoyo institucional.

Palabras clave:
gestión de proyectos; investigación científica; éxito

1. INTRODUTION

One type of project is scientific research. In Brazil, this type of project relies heavily on funding from sources outside research institutions or universities (which usually pay for basic infrastructure and salaries), with relevant public sector participation.

On January 27, 2017, Jornal da Ciência, a communication channel of the “Sociedade Brasileira para o Progresso da Ciência” (SBPC) - “Brazilian Society for the Advancement of Science” (SBPC), released the results of a study carried out by the “Conselho Nacional das Fundações de Apoio às Instituições de Ensino Superior e de Pesquisa Científica e Tecnológica” (CONFIES) -“National Council of Foundations to Support Higher Education Institutions and Scientific and Technological Research” (CONFIES) - between November and December of 2016, in which 301 Brazilian researchers were interviewed who coordinate research projects in 34 federal universities, distributed in 23 states and in the (Distrito Federal) - Federal District, capital of Brazil. This study revealed that a researcher spends on average 33% of his/her time to solve bureaucratic problems that mainly concern the purchase of materials, goods and inputs used in laboratories of Higher Education Institutions and Scientific and Technological Research. For CONFIES leader Fernando Peregrino, this result is “worrisome”, since 75% of the projects are financed by the public sector, that is, they are guided by the rules of bureaucratic management of the government itself (Monteiro, 2017Monteiro, V. (2017, 27 de janeiro). Burocracia consome mais de 30% do tempo dos cientistas, constata pesquisa. Recuperado dehttp://www.jornaldaciencia.org.br/burocracia-consome-mais-de-30-do-tempo-dos-cientistas-constata-pesquisa/
http://www.jornaldaciencia.org.br/burocr...
).

These managerial challenges found by scientists, however, have not been the focus of empirical studies (Cunningham, O’Reilly, O’Kane, & Mangematin, 2012Cunningham, J., O’Reilly, P., O’Kane, C., & Mangematin, V.(2014). The inhibiting factors that principal investigators experience in leading publicly funded research. The Journal of Technology Transfer, 39(1), 93-110. Recuperado dehttps://doi.org/10.1007/s10961-012-9269-4
https://doi.org/10.1007/s10961-012-9269-...
). To fill this gap, it is proposed that the project management office, an organizational unit recognized by PMBOK®, could support the scientific management of these projects, so that it engages in other activities.

In this context, the objective of this article is to identify if this type of organizational unit (the office) impacts the management of scientific research projects. Mainly, the objective is to identify specific variables for the management of scientific research projects; to identify how scientific research projects can be carried out if they contribute to the literature on project management, adding concepts from the applied literature to other contexts.

Five hypotheses were developed that tested the influence of the office on the traditional literature variables related to project success (time, cost and quality). These hypotheses were tested a review of the theoretical framework and the data collection of scientific research projects funded by the Foundation for Research Support in the State of São Paulo (FAPESP) and carried out in the Faculty of Medicine of Ribeirão Preto (FMRP), which office supports the financial management of these projects. This article depended on the data collection provided by the FMRP, which, in turn, also depended on the data collection by FAPESP, as there is no database available to the university’s top management on public and private funding of all scientific research projects.

2. THEORETICAL FRAMEWORK

Despite its importance, there is no consensus in the literature regarding the criteria that should be used to measure the project success (Berssaneti & Carvalho, 2015Berssaneti, F. T., & Carvalho, M. M. (2015). Identification of variables that impact project success in Brazilian companies. International Journal of Project Management, 33(3), 638-649.; Jha & Iyer, 2006Jha, K. N., & Iyer, K. C. (2006). Critical determinants of project coordination. International Journal of Project Management, 24(4), 314-322.; Liu & Cross, 2016Liu, W.-H., & Cross, J. A. (2016). A comprehensive model of project team technical performance. International Journal of Project Management, 34(7), 1150-1166.). The main concept is the one that considers the possibility of assisting the constraints of cost, time and quality, called “iron triangle” (Atkinson, 1999Atkinson, R. (1999). Project management: cost, time and quality, two best guesses and a phenomenon, its time to accept other success criteria. International Journal of Project Management, 17(6), 337-342.; Berssaneti & Carvalho, 2015Berssaneti, F. T., & Carvalho, M. M. (2015). Identification of variables that impact project success in Brazilian companies. International Journal of Project Management, 33(3), 638-649.; Cserháti & Szabó, 2014Cserháti, G., & Szabó, L. (2014). The relationship between success criteria and success factors in organisational event projects. International Journal of Project Management, 32(4), 613-624.; Ika, 2009Ika, L. A. (2009). Project success as a topic in project management journals. Project Management Journal, 40(4), 6-19.; Joslin & Müller, 2016Joslin, R., & Müller, R. (2016). The relationship between project governance and project success. International Journal of Project Management, 34(4), 613-626.; Kloppenborg, Tesch, & Manolis, 2014Kloppenborg, T. J., Tesch, D., & Manolis, C(2014). Project success and executive sponsor behaviors: empirical life cycle stage investigations. Project Management Journal, 45(1), 9-20.; Koops, Bosch-Rekveldt, Coman, Hertogh, & Bakker, 2016Koops, L., Bosch-Rekveldt, M., Coman, L., Hertogh, M., & Bakker, H. (2016). Identifying perspectives of public project managers on project success: comparing viewpoints of managers from five countries in North-West Europe. International Journal of Project Management, 34(5), 874-889.; Laursen & Svejvig, 2016Laursen, M., & Svejvig, P. (2016). Taking stock of project value creation: a structured literature review with future directions for research and practice. International Journal of Project Management, 34(4), 736-747.; Liu & Cross, 2016Liu, W.-H., & Cross, J. A. (2016). A comprehensive model of project team technical performance. International Journal of Project Management, 34(7), 1150-1166.; Milosevic & Patanakul, 2005Milosevic, D., & Patanakul, P. (2005). Standardized project management may increase development projects success. International Journal of Project Management, 23(3), 181-192.; Papke-Shields, Beise, & Quan, 2010Papke-Shields, K. E., Beise, C., & Quan, J. (2010). Do project managers practice what they preach, and does it matter to project success?International Journal of Project Management, 28(7), 650-662.; Turner & Zolin, 2012Turner, R., & Zolin, R. (2012). Forecasting success on large projects: developing reliable scales to predict multiple perspectives by multiple stakeholders over multiple time frames. Project Management Journal, 43(5), 87-99.; Williams, Ashill, Naumann, & Jackson, 2015Williams, P., Ashill, N. J., Naumann, E., & Jackson, E. (2015). Relationship quality and satisfaction: customer-perceived success factors for on-time projects. International Journal of Project Management, 33(8), 1836-1850.). According to this view, if the project met the schedule, it came close to budget and was executed as expected, so it is considered a success.

Another concept involved is project management. It is designed to ensure the success of a project (Berssaneti & Carvalho, 2015Berssaneti, F. T., & Carvalho, M. M. (2015). Identification of variables that impact project success in Brazilian companies. International Journal of Project Management, 33(3), 638-649.), which in turn depends on the perspective of the individual evaluating success (Jha & Iyer, 2006Jha, K. N., & Iyer, K. C. (2006). Critical determinants of project coordination. International Journal of Project Management, 24(4), 314-322.; Turner & Zolin, 2012Turner, R., & Zolin, R. (2012). Forecasting success on large projects: developing reliable scales to predict multiple perspectives by multiple stakeholders over multiple time frames. Project Management Journal, 43(5), 87-99.).

There is also the concept of critical success factors. They are basically related to characteristics, conditions or variables that can have a significant impact on the project success when properly sustained, maintained and managed (Milosevic & Patanakul, 2005Milosevic, D., & Patanakul, P. (2005). Standardized project management may increase development projects success. International Journal of Project Management, 23(3), 181-192.).

Pinto and Slevin (1987Pinto, J. K., & Slevin, D. P. (1987). Critical factors in successful project implementation. IEEE Transactions on Engineering Management, EM- 34(1), 22-27.) were the first researchers to publish critical success factors. Its ten success factors include: project mission, senior management support, project timeline, customer consultation, staffing, technical tasks, customer acceptance, monitoring and feedback, problem solving and communication.

Research into criteria and critical success factors has shown that it is impossible to develop a list that fits the needs of all projects because of the criteria and factors may be very different from one project to another.

For Creasy and Anantatmula (2013Creasy, T., & Anantatmula, V. S. (2013). From every direction: how personality traits and dimensions of project managers can conceptually affect project success. Project Management Journal, 44(6), 36-51.), Project Management Institute (PMI) believes that the project management office is one of the ways to achieve project success and project management maturity. According to this point of view, a more mature office tends to use tools, techniques and practices more often, more consistently and with better management.

Known in the literature as Project Management Office (PMO) has been created as a new organizational entity as part of the response to the new challenge of more numerous and strategically important projects.

Set up with the mission of taking responsibility and coordinating project-related activities, the project management office can be formed under different organizational structures. There seems to be an academic effort to list what their characteristics, responsibilities, and similar tasks are (Aubry, Müller, Hobbs, & Blomquist, 2010Aubry, M., Müller, R., Hobbs, B., & Blomquist, T. (2010). Project management offices in transition. International Journal of Project Management, 28(8), 766-778.). It has been suggested that this type of office facilitates knowledge transfer (Andersen, Henriksen, & Aarseth, 2007Andersen, B., Henriksen, B., & Aarseth, W. (2007). Benchmarking of project management office establishment: extracting best practices.Journal of Management in Engineering, 23(2), 97-104.) and the comparability among the managed projects (Andersen, Henriksen, & Aarseth, 2007Andersen, B., Henriksen, B., & Aarseth, W. (2007). Benchmarking of project management office establishment: extracting best practices.Journal of Management in Engineering, 23(2), 97-104.).

The PMO is used for many decades in some sectors, such as engineering, construction, oil and gas (Pellegrinelli & Garagna, 2009Pellegrinelli, S., & Garagna, L. (2009). Towards a conceptualisation of PMOs as agents and subjects of change and renewal. International Journal of Project Management, 27(7), 649-656.), telecommunications, aerospace and defense (Desouza & Evaristo, 2006Desouza, K. C., & Evaristo, J. R. (2006). Project management offices: a case of knowledge-based archetypes. International Journal of Information Management, 26(5), 414-423.), becoming more widespread in the middle of the 90. They were originally conceived as a means of capturing and disseminating good project management practices (Desouza & Evaristo, 2006Desouza, K. C., & Evaristo, J. R. (2006). Project management offices: a case of knowledge-based archetypes. International Journal of Information Management, 26(5), 414-423.) and are being conceptualized as the main method to effect changes in large companies (Pellegrinelli & Garagna, 2009Pellegrinelli, S., & Garagna, L. (2009). Towards a conceptualisation of PMOs as agents and subjects of change and renewal. International Journal of Project Management, 27(7), 649-656.). However, according to Alves, Costa, Quelhas, Silva, and Pimentel (2013Alves, R. O., Costa, H. G., Quelhas, O. L. G., Silva, L. E., & Pimentel, L. B. (2013). Melhores práticas em implantação de escritório de gerenciamento de projeto: desenvolvimento de referenciais de sucesso. Produção, 23(3), 582-594.), “the implementation of a project management office is still very susceptible to failure”.

In addition, project management offices can present various roles and functions (Pellegrinelli & Garagna, 2009Pellegrinelli, S., & Garagna, L. (2009). Towards a conceptualisation of PMOs as agents and subjects of change and renewal. International Journal of Project Management, 27(7), 649-656.), sizes, structures and accounts rendering (Desouza & Evaristo, 2006Desouza, K. C., & Evaristo, J. R. (2006). Project management offices: a case of knowledge-based archetypes. International Journal of Information Management, 26(5), 414-423.). There are researches focused on the role of the project management office as a facilitator of the project manager and the organization, in the sense of understanding to apply professional practices of project management, as well as adapting and integrating business interests into project management efforts (Hill, 2004Hill, G. M. (2004). Evolving the project management office: a competency continuum. Information Systems Management, 21(4), 45-51.). Another line of research studies the relation between the functions and the project performance (Dai & Wells, 2004Dai, C. X., & Wells, W. G. (2004). An exploration of project management office features and their relationship to project performance. International Journal of Project Management, 22(7), 523-532.).

3. METHODOLOGY

The sample was collected in three stages. The first step consisted in signing the Term of Consent and Confidentiality. The data collection was carried out with the FMRP, which made available the variables referring to the scientific research projects granted by FAPESP in the period from 2009 to 2015. The second step was done through a query to the electronic address <http://www.fapesp.br>. The third step was done according to the parameters of the theoretical framework and practical knowledge.

Whereas: a) FMRP’s project management office began operations on September 1, 2010; b) there were aids granted from 2015 and still in progress at the time of writing the article and therefore were not included in the analysis; c) the office does not help the fellows, so these aids were not analyzed, 309 cases remain. All these data were organized and analyzed.

The success of the project is the dependent variable and the critical success factors are the independent variables. There are five dependent variables and one independent variable, all separately analyzed.

The chi-square independence test was applied using the Minitab® software version 17. The objective was to verify if the observed value of one variable depends on the observed value of another variable, i.e, which variables could contribute to the success of a research project scientific basis. The five dependent variables (INDTEMPO, INDPC, INDRC, INDQ and INDVALOR) were inserted into the rows and the columns EGP independent variable.

4. RESULTS

In this section, we present the search results.

  • Hypothesis 1: Fulfillment of original project schedule (INDTEMPO = Time Indicator)

This test revealed that office support impacted the time variable. In the expected count of projects supported by (EGP = Public Management) and without of term, 92.41 projects could have increased deadlines but in fact, 79 had not.

Table 1
Test result for the Time Indicator
  • Hypothesis 2: Requirements of the funding agency (Indicator of Accounts)

This test revealed that office support impacts the accountability variable, INDPC = Indicator of Accounts). Note that when the scientist has the support of the project management office, accountability has less value than when it does not have such support, highlighting the impact of team knowledge in compliance with the standard of the financing agency.

Table 2
Test result for the Indicator of Accounts
  • Hypothesis 3: Requirements of the funding agency (Scientific Report Indicator)

This test revealed that office support does not impact the variable INDRC=Scientific Report. Note that when the scientist has the support of the office, the scientific report should have fewer reservations compared to when it does not have such support. It is interesting to note that when the scientist has the support of the office the number of reservations is equivalent to when he does not have the support, emphasizing that it depends on the scientist the attendance of the required standard knowledge in the area.

Table 3
Test result for the Scientific Report Indicator
  • Hypothesis 4: Compliance with Quality (Indicator of Accounts and Scientific Report)

This test revealed that office support impacts the quality variable (INDQ= Quality). Note that when the scientist has the support of the office, these requirements of the funding agency have fewer reservations compared to when they do not have such support. It is interesting to point out once again that when the scientist has the support of the project management office, the number of reservations is also lower, a fact expected from a practical point of view due to the team’s knowledge in attending of the financing agency standard.

Table 4
Result of the test for the Indicator of Accounts and Scientific Report
  • Hypothesis 5: Compliance with the budget planned for the project (Value Indicator)

This test revealed that office support impacts the variable, INDVALOR=Value. Note that when the scientist has the support of the office, the value of the project tends to be different from three hundred thousand reais (R$ 300,000.00). In another analysis, the scientist would tend to delegate financial management of the project to the management office depending on the amount awarded by the funding agency.

Table 5
Test result for the Value Indicator

When assessing the significance of the chi-square statistic, the p-value (0.000) is lower than the significance level of 0.05. Therefore, at a significance level of 0.05, we reject the null hypothesis and conclude that there is a statistically significant association among the variables, except for the scientific report variable, as expected.

5. CONCLUSION

This article provided evidence that the Project Management Office, an organizational unit recognized by PMBOK®, could support the scientist in the management of research projects. To achieve the objective, five hypotheses were developed, which tested the influence of the office about traditional variables of the literature on project success (time, cost and quality), using the theoretical framework and data collection of scientific research projects financed by FAPESP and executed in the FMRP from 2009 to 2015. The hypotheses were tested using the chi-square test of independence.

The study showed that the office can contribute to the success of a scientific research project. Scientists would have fulfilled the standards required by the funding agency without such support; however, it has been shown that the office impacts the financial management of the project. Either the scientist is spared bureaucratic tasks or he can dedicate time to other tasks, an expected result from the point of view of the theoretical framework. This type of initiative is aligned with the practices of foreign universities, where support for scientists has already become a routine part of institutional support (Grants Management Office).

In addition to supporting scientists in project management, the office assists funding agencies in fulfilling their institutional mission of maintaining accountability within legal requirements and in pattern which answer to that required by government control agencies.

The study was limited to the sample and the period chosen. Besides the office reviewed focuses only on the financial management of the project. Therefore, there must be other variables that could contribute to success when other tasks are evaluated.

In the case of requirements of this type of public funding, accountability and the scientific report were considered a quality measure for the success of the scientific research project. However, there must be other variables that could contribute to success when this type of financing is evaluated.

As suggestions for future research, list:

  • Application of the tests to projects financed by other agencies, opening the discussion, for example, on financing rules (public and private).

  • Application of a survey to the scientists who count and who do not count on the support of the project management office of FMRP, to make sure the perception of success of the project.

  • Implementation of a shared project management center at USP’s Campus in Ribeirão Preto. This point of view is supported by the argument that this center could attend to the managerial demands of funding agencies more efficiently, assuming that the standard is the same for all project types.

Hoping that the article contributes to the discussion of the variables that could impact the research project success, especially in the sights of the current scenario of competition for resources from funding agencies and search for the relevance and impact of the science produced in Brazil.

Not only can this article contribute to open the decision-makers mind (university administrators and business school leaders, including scientists), as to the importance of training people to administer scientific research projects, but also it is suggested to include specificity to the coverages of PMBOK®.

REFERÊNCIAS

  • Alves, R. O., Costa, H. G., Quelhas, O. L. G., Silva, L. E., & Pimentel, L. B. (2013). Melhores práticas em implantação de escritório de gerenciamento de projeto: desenvolvimento de referenciais de sucesso. Produção, 23(3), 582-594.
  • Andersen, B., Henriksen, B., & Aarseth, W. (2007). Benchmarking of project management office establishment: extracting best practices.Journal of Management in Engineering, 23(2), 97-104.
  • Atkinson, R. (1999). Project management: cost, time and quality, two best guesses and a phenomenon, its time to accept other success criteria. International Journal of Project Management, 17(6), 337-342.
  • Aubry, M., Müller, R., Hobbs, B., & Blomquist, T. (2010). Project management offices in transition. International Journal of Project Management, 28(8), 766-778.
  • Berssaneti, F. T., & Carvalho, M. M. (2015). Identification of variables that impact project success in Brazilian companies. International Journal of Project Management, 33(3), 638-649.
  • Creasy, T., & Anantatmula, V. S. (2013). From every direction: how personality traits and dimensions of project managers can conceptually affect project success. Project Management Journal, 44(6), 36-51.
  • Cserháti, G., & Szabó, L. (2014). The relationship between success criteria and success factors in organisational event projects. International Journal of Project Management, 32(4), 613-624.
  • Cunningham, J., O’Reilly, P., O’Kane, C., & Mangematin, V.(2014). The inhibiting factors that principal investigators experience in leading publicly funded research. The Journal of Technology Transfer, 39(1), 93-110. Recuperado dehttps://doi.org/10.1007/s10961-012-9269-4
    » https://doi.org/10.1007/s10961-012-9269-4
  • Dai, C. X., & Wells, W. G. (2004). An exploration of project management office features and their relationship to project performance. International Journal of Project Management, 22(7), 523-532.
  • Desouza, K. C., & Evaristo, J. R. (2006). Project management offices: a case of knowledge-based archetypes. International Journal of Information Management, 26(5), 414-423.
  • Hill, G. M. (2004). Evolving the project management office: a competency continuum. Information Systems Management, 21(4), 45-51.
  • Ika, L. A. (2009). Project success as a topic in project management journals. Project Management Journal, 40(4), 6-19.
  • Jha, K. N., & Iyer, K. C. (2006). Critical determinants of project coordination. International Journal of Project Management, 24(4), 314-322.
  • Joslin, R., & Müller, R. (2016). The relationship between project governance and project success. International Journal of Project Management, 34(4), 613-626.
  • Kloppenborg, T. J., Tesch, D., & Manolis, C(2014). Project success and executive sponsor behaviors: empirical life cycle stage investigations. Project Management Journal, 45(1), 9-20.
  • Koops, L., Bosch-Rekveldt, M., Coman, L., Hertogh, M., & Bakker, H. (2016). Identifying perspectives of public project managers on project success: comparing viewpoints of managers from five countries in North-West Europe. International Journal of Project Management, 34(5), 874-889.
  • Laursen, M., & Svejvig, P. (2016). Taking stock of project value creation: a structured literature review with future directions for research and practice. International Journal of Project Management, 34(4), 736-747.
  • Liu, W.-H., & Cross, J. A. (2016). A comprehensive model of project team technical performance. International Journal of Project Management, 34(7), 1150-1166.
  • Milosevic, D., & Patanakul, P. (2005). Standardized project management may increase development projects success. International Journal of Project Management, 23(3), 181-192.
  • Monteiro, V. (2017, 27 de janeiro). Burocracia consome mais de 30% do tempo dos cientistas, constata pesquisa Recuperado dehttp://www.jornaldaciencia.org.br/burocracia-consome-mais-de-30-do-tempo-dos-cientistas-constata-pesquisa/
    » http://www.jornaldaciencia.org.br/burocracia-consome-mais-de-30-do-tempo-dos-cientistas-constata-pesquisa/
  • Papke-Shields, K. E., Beise, C., & Quan, J. (2010). Do project managers practice what they preach, and does it matter to project success?International Journal of Project Management, 28(7), 650-662.
  • Pellegrinelli, S., & Garagna, L. (2009). Towards a conceptualisation of PMOs as agents and subjects of change and renewal. International Journal of Project Management, 27(7), 649-656.
  • Pinto, J. K., & Slevin, D. P. (1987). Critical factors in successful project implementation. IEEE Transactions on Engineering Management, EM- 34(1), 22-27.
  • Turner, R., & Zolin, R. (2012). Forecasting success on large projects: developing reliable scales to predict multiple perspectives by multiple stakeholders over multiple time frames. Project Management Journal, 43(5), 87-99.
  • Williams, P., Ashill, N. J., Naumann, E., & Jackson, E. (2015). Relationship quality and satisfaction: customer-perceived success factors for on-time projects. International Journal of Project Management, 33(8), 1836-1850.
  • [Translated version] Note: All quotes in English translated by this article’s translator.

Publication Dates

  • Publication in this collection
    10 Jan 2020
  • Date of issue
    Nov-Dec 2019

History

  • Received
    12 Apr 2018
  • Accepted
    17 Aug 2018
Fundação Getulio Vargas Fundaçãoo Getulio Vargas, Rua Jornalista Orlando Dantas, 30, CEP: 22231-010 / Rio de Janeiro-RJ Brasil, Tel.: +55 (21) 3083-2731 - Rio de Janeiro - RJ - Brazil
E-mail: rap@fgv.br